RRA - Item 2 - Garvey Ave Community Center and Senior Housing Project (Change Order to Modify Plan for Storm Drain Connection to Rio Hondo Channel)Memorandum
To: Frank Tripepi, Executive Director
From: Stephen Copenhaver, GRC
Date: January 1.5, 2002
Subject: Garvey Avenue Community Center and Senior Housing Project
Change Order to modify plans for storm drain connection to Rio
Hondo Channel
The Garvey Avenue Community Center and Senior Housing Project plans rely on a
storm drain connection to the Rio Hondo Channel to provide flood control measures.
Original plans for this connection were estimated to cost around $15,000. The Army
Corps .of Engineers, the acting authority, reviewed the original plans and required
some significant changes to receive their approval. These changes included the size
and location of the storm drain connection. The storm drain plans have been
modified to meet these changes, and the new plans, attached to this document, have
been approved by the Army Corps. These changes to the plan are estimated to cost
an additional $68,900 above the originally approved amount.
Recommendations
It is recommended that the Agency approve the change order for the Army Corps of
Engineers mandated work in the amount of $68,900.
AGENDA
JAN 2 2 2s02
02
ITEM No.
The purpose of this memo is to seek approval of a change order for additional funds
to.establish a site connection to Rio Hondo Channel pursuant to Army Corps of
Engineers requirements.