RRA - Item 2 - Garvey Ave Community Center and Senior Housing Project (Change Order to Modify Plan for Storm Drain Connection to Rio Hondo Channel)Memorandum To: Frank Tripepi, Executive Director From: Stephen Copenhaver, GRC Date: January 1.5, 2002 Subject: Garvey Avenue Community Center and Senior Housing Project Change Order to modify plans for storm drain connection to Rio Hondo Channel The Garvey Avenue Community Center and Senior Housing Project plans rely on a storm drain connection to the Rio Hondo Channel to provide flood control measures. Original plans for this connection were estimated to cost around $15,000. The Army Corps .of Engineers, the acting authority, reviewed the original plans and required some significant changes to receive their approval. These changes included the size and location of the storm drain connection. The storm drain plans have been modified to meet these changes, and the new plans, attached to this document, have been approved by the Army Corps. These changes to the plan are estimated to cost an additional $68,900 above the originally approved amount. Recommendations It is recommended that the Agency approve the change order for the Army Corps of Engineers mandated work in the amount of $68,900. AGENDA JAN 2 2 2s02 02 ITEM No. The purpose of this memo is to seek approval of a change order for additional funds to.establish a site connection to Rio Hondo Channel pursuant to Army Corps of Engineers requirements. Connection to Rio Hondo Channel Sent By: KPRS CONSTRUCTION: .I, 714 529 5769; Oct-25-01 11:15AM; Page 10117 rP