State Route 710 StudyAlternatives Analysis Report
QD Metro Acronyms and Abbreviations
State Route 710 Study
Alternatives Analysis Report
December 2012
Alternatives Analysis Report
M etro Executive Summary
ES.1.0 Need and Purpose
ES. 1.1 Background and History
The SR 710 Study is the culmination of along history of efforts to address north -south mobility in the
western San Gabriel Valley and east and northeast Los Angeles. The history of the planning efforts
dates back to 1933 when Legislative Route 167, later renamed SR 7, was defined to run from San
Pedro east to Long Beach and north to the vicinity of Monterey Park. The majority of this route has
been constructed and incorporated into the Interstate Highway System as Interstate 710 (1 -710). In
1959, the proposed northern limits of SR 7 were extended to the planned Foothill Freeway (now 1 -210).
Over the years, planning efforts continued to address community and agency concerns, eventually
leading to the issuance ofa Record of Decision (ROD) in 1998 bythe Federal Highway Administration
(FHWA) for a surface freeway. After litigation initiated by some of the affected communities, FHWA
rescinded the ROD in 2003, citing changes in project circumstances such as funding uncertainty and
the opening of the Metro Gold line to Pasadena, and requiring a more thorough evaluation ofthe
feasibility of a bored tunnel.
In 2006, Metro and Caltrans conducted two tunnel feasibility assessments, the Route 770 Tunnel
Technical Feasibility Assessment Report and the 5R -770 Tunnel Technical Study, to evaluate the
feasibility of constructing a tunnel to complete the planned SR 710 freeway route that would lessen the
potential impacts associated with a surface route. The studies found that a tunnel would be a viable
solution and would warrant more detailed evaluation. In November 2008, Measure R (a half -cent sales
tax dedicated to transportation projects in Los Angeles County) was approved by a two- thirds majority
of County voters. Included in the Measure R plan is the commitment of $780 million to improve the
connection between the SR 710 and 1 -210 freeways.
In March 2011, Caltrans published a Notice of Intent (NOI) under the National Environmental Policy
Act (NEPA) and a Notice of Preparation (NOP) under the California Environmental Quality Act
(CEQA) to initiate the environmental review process for the "Interstate 710 North Gap Closure'
project. The environmental review process began with the "SR -710 Conversations" outreach effort, led
by Metro, including 21 pre - scoping and scoping meetings throughout the study area in March and
April of 2011. Metro also initiated the "State Route 710 Gap Closure Transit Profile Study" to gather
transit service and patronage data and to assess current and future transit travel markets within the
study area.
ES.1.2 Study Area
The study area is approximately 100 square miles and is generally bounded by the 1 -210 freeway on the
north, the 1 -605 freeway on the east, the 1 -10 freeway on the south, and the 1 -5 and SR 2 freeways on
the west. The study area is illustrated in Figure ES -1. According to data from the Southern California
Association of Governments (SCAG), the study area had a population of 1.18 million people in 2008,
and 450,000 jobs were located in the study area. By 2035, the study area is forecast to have a
population of 1.33 million people and an employment base of 507,000 jobs.
ES.1.3 Need
The study area is centrally located within the extended urbanized area of Southern California. With few
exceptions, the area from Santa Clarita in the north to San Clemente in the south, a distance of
approximately 90 miles, is continuously urbanized. Physical features such as the San Gabriel
Mountains and Angeles National Forest on the north, and the Puente Hills and Cleveland National
SR 710 Study
December 2012 Page ES -1
T
o m
w r
Al
U
�N
N
N
M e
='
b
f
w
41 L
1& Pe amp
t W
� y c
o' y 7� sunv
L
s„ep fle} T ...__7a yrv°w
J \
tlf. o
f o 0 up k-
0
t`
Alternatives Analysis Report
_QDMetro Executive Summary
Forest on the south, have concentrated urban activity between the Pacific Ocean and these physical
constraints. This urbanized area functions as a single social and economic region, identified by the
Census Bureau as the Los Angeles -Long Beach -Santa Ana metropolitan statistical area (MSA).
There are seven major east -west freeway routes (SR 118, US- 101 /SR 134/1 -210, 1 -10, SR 60,1-105, SR
91, SR 22) and seven major north -south freeway routes (1 -405, US- 101 /US -170, 1 -5, 1- 110 /SR 110,
1 -710, 1 -605, and SR 57) in the central portion of the Los Angeles -Long Beach -Santa Ana MSA. Of the
seven north -south routes, four of them are located partially within the study area (1 -5, 1- 110 /SR 110, 1-
710, and 1 -605), and two of these (1- 110 /SR 110 and 1 -710) terminate within the study area without
connecting to another freeway. As a result, a very large amount of north -south regional travel demand
is concentrated on a few freeways, or diverted to local streets within the study area. This effect is
exacerbated by the overall southwest -to- northeast orientation of 1 -605, which makes it an unappealing
route for traffic between the southern part of the region and the urbanized areas to the northwest in
the San Fernando Valley, the Santa Clarita Valley, and the Arroyo- Verdugo region.
The lack of continuous north -south transportation facilities in the study area has the following
consequences, which have been identified as the elements of need for the project:
• It degrades the overall efficiency of the larger regional transportation system.
• It causes congestion on freeways in the study area.
• It contributes to congestion on the local streets in the study area.
• It results in poor transit operations within the study area.
ES. 1.4 Purpose
Based on the needs discussed above related to the regional transportation system, congestion on
freeways in the study area, cut - through traffic that affects local streets in the study area, and poor
transit operations within the study area, the following project purpose has been established:
The purpose of the proposed action is to effectively and efficiently accommodate regional and
local north -south travel demands in the study area of the western San Gabriel Valley and
east /northeast Los Angeles, including the following considerations:
• Improve efficiency of the existing regional freeway and transit networks;
• Reduce congestion on local arterials adversely affected due to accommodating regional traffic
volumes;
• Minimize environmental impacts related to mobile sources.
ES. 1.5 Objectives
To address the four elements of need for the project, five objectives related to the performance of the
transportation system were developed as shown in Table ES -1.
Table ES -1. Transportation System Objectives
Element of Need -
Objective
Regional transportation system
1. Minimize travel time
2. Improve connectivit and mobilit
Congestion on study area freeways
3. Reduce congestion on freeway system
Congestion on local streets
4. Reduce congestion on local streets stem
Transit operations in study area
5. Increase transit ridershi
SR 710 Study
December 2012 Page ES -3
AA
Alternatives Analysis Report
Executive Summary
Three additional objectives were developed to address environmental impacts, planning
considerations, and cost efficiency as shown in Table ES -2.
Table ES -2. Environmental and Other Project Objectives
Value or Concern
Objective
Environment and communities
6. Minimize environmental and community impacts
related to transportation
Consistency with plans
7. Assure consistency with regional plans and
strategies
Provide financially feasible
8. Maximize the cost - efficiency of public
transportation solutions
investments
ES.2.0 Alternatives Considered
A wide range of possible transportation alternatives was identified based on past studies and
comments received during the "SR -710 Conversations" from stakeholders including elected officials,
city and agency staff, and the community. The resulting options were evaluated and refined through a
sequential screening process to identify the alternatives that best meet the Need and Purpose of the
study. The following sections describe the screening process, selection criteria, and the alternatives
selected for evaluation via conceptual engineering and initial environmental analysis in this
Alternatives Analysis (AA).
ES.2.1 Screening Criteria and Selection Process
The screening of alternatives followed a sequential process summarized below and illustrated
in Figure ES -2:
r' X51
Figure ES -2: Screening Process
• Preliminary Screening — An unscreened set of alternatives was identified during project initiation
through a process that included a review of prior studies and public input received during the "710
Conversations" scoping process conducted by Metro and Caltrans in 2011. From this large set of
alternatives, the preliminary screening step led to the identification of the preliminary set of
alternatives, consisting of 42 alternatives representing a reasonable range of modes and
alignments. Criteria used for the preliminary screening included the potential to accommodate
regional north -south travel, reduce local street congestion, minimize community impacts,
minimize the potential to encounter contaminated soil and groundwater, and accommodate
ridership potential (for relevant modes). Within each travel mode, alternatives were evaluated
against each other, and the most promising alternatives from each mode were selected to be
included in the preliminary set of alternatives.
• Initial Screening —The initial screening evaluated the preliminary set of alternatives based on the
eight project objectives described in Section 1.5. In general, the initial screening relied on available
data and schematic representations of each alternative. To find the best performing alternatives
SR 710 Study
December 2012 Page ES-4
Alternatives Analysis Report
M etro Executive Summary
within each mode in the initial screening, the performance of each alternative was compared only
to that of other alternatives of the same mode. This evaluation step resulted in the identification of
the initial set of alternatives, consisting of 12 alternatives and representing each mode from the
preliminary set of alternatives.
Secondary Screening — In the secondary screening step of the AA phase, the initial set of
alternatives was studied and evaluated using detailed performance measures reflecting the eight
project objectives. Additional engineering and environmental evaluation of each alternative was
conducted, based on travel demand and ridership forecasting specific to each alternative and the
conceptual -level engineering plans. The alternatives performing best on the secondary screening
will be further developed and enhanced for evaluation during the Project Approval and
Environmental Documentation (PA /ED) phase, along with possible hybrid or combination
alternatives.
ES.2.2 Initial Set of Alternatives
The initial set of alternatives was screened from the preliminary set of alternatives and represents a
range of modes and alignments. The No Build Alternative, the TSM /TDM Alternative, and the 10
"build" alternatives (as well as three design variations) are described below.
ES.2.2.1 No Build Alternative
The No Build Alternative includes all ofthe projects that are identified in the financially constrained
project list of SCAG's 2008 Regional Transportation Plan (RTP): Making the Connections. The No
Build Alternative also includes currently planned projects in Los Angeles County that are identified in
Measure R, as well as those in the "Constrained Plan" of Metro's 2009 Long Range Transportation
Plan (through the year 2035). The No Build Alternative does not include any project in the SR 710
corridor in the study area.
ES.2.2.2 Transportation System Management/ Transportation Demand
Management (TSM/TDM) Alternative
The TSM /TDM Alternative consists of strategies and improvements to increase efficiency and capacity
for all modes in the transportation system with lower capital cost investments and /or lower potential
impacts such as substantially increased bus service in the study area, active transportation (pedestrian
and bicycle) facilities, intersection spot improvements, local street improvements, and Intelligent
Transportation Systems (ITS) elements. The transit service improvements included in the TSM /TDM
Alternative are illustrated in Figure ES -3. These transit improvements are also included in the BRT and
LRT alternatives, but are not included in the freeway and highway alternatives.
ES.2.2.3 Bus Rapid Transit (BRT) Alternatives
The BRT alternatives would provide higher speed, high frequency bus service operating in a
combination of new, dedicated bus lanes and existing, mixed -flow traffic lanes. Bus priority methods
such as synchronized traffic signal timing and preferential treatment of bus arrivals at signalized
intersections would also be incorporated into the BRT system. The BRT alternatives also include all of
the additional transit service provided in the TSM /TDM alternative, except where those services
overlap with the BRT service itself. The BRT alternatives are illustrated in Figure ES -4.
BRT -1. Alternative BRT -1 would provide BRT service between Los Angeles Union Station and the Jet
Propulsion Laboratory (JPL) in La Canada Flintridge.
SR 710 Study
December 2012 Page ES -5
o ,c
y �
ro
m
C
m
C7
a�
0
0
a
U
U
.
td
Lti
N
�
/r
M
W
N
Fw
b0
O
r
�i
Alternatives Analysis Report
M etro Executive Summary
Figure ES-4: BRT Alternatives
SR 710 Study
December 2012 Page ES -7
M
Alternatives Analysis Report
Executive Summary
BRT-6. Alternative BRT -6 would provide BRT service between Whittier Boulevard, just south of the
Gold Line Atlantic Station, and Pasadena City College (PCC) and the California Institute of Technology
(Caltech) in Pasadena.
BRT -6A Alternative BRT -6A is a design variation of Alternative BRT -6 but with a different terminal loop
than Alternative BRT -6. Instead of traveling both eastbound and westbound on Colorado Boulevard,
Alternative BRT -6A would travel only eastbound on Colorado Boulevard and then return westbound on
California Boulevard after stopping at PCC and Caltech.
FS.2.2.4 Light Rail Transit (LRT) Alternatives
The LRT alternatives would be similar to the Metro Gold Line and Metro Blue Line currently operated
by Metro in Los Angeles County. LRT systems typically operate along dedicated rights -of -way at- grade,
but can be built in aerial or underground configurations where necessary. They are electrically powered
through an overhead catenary system. In dedicated right -of -way, Metro LRT vehicles can operate at
speeds of up to 65 mph. The LRT alternatives include all of the additional transit service provided in
the TSM/TDM alternative, except where those services overlap with the LRT service itself. The LRT
alternatives are illustrated in Figure ES -5.
LRT -4A Alternative LRT-4A would begin at an aerial station on Mednik Avenue adjacent to the existing
East LA Civic Center Station on the Metro Gold Line. It would remain elevated as it travels north to a
station adjacent to Cal State LA, then descend into a tunnel north of Valley Boulevard and end at an
underground station beneath the existing Fillmore Station on the Metro Gold Line.
IRT -4B. Alternative LRT -413 was developed as a design variation of Alternative LRT -4A to reduce the
length of tunneling required. Alternative LRT -413 would follow the same path as Alternative LRT -4A to
the Cal State LA Station. Instead of immediately entering a tunnel, Alternative LRT -413 would continue
on an elevated structure above Mission Road, turning north on Palm Avenue where it would descend
to grade on Palm Avenue. Alternative LRT -413 would then enter a bored tunnel before Main Street and
continue along an alignment similar to that of Alternative LRT-4A.
LRT -4D. Alternative LRT -413 was developed as a design variation of Alternative LRT -4A to eliminate the
bored tunnel section and use only cut - and -cover tunnel techniques. Alternative LRT -4D would
originate at an underground station beneath Beverly Boulevard, near the existing Atlantic Station on
the Metro Gold Line and end at an underground station beneath the existing Fillmore Station on the
Metro Gold Line.
LRT -6. Alternative LRT -6 would connect the existing Atlantic and Fillmore stations on the Metro Gold
Line. Alternative LRT -6 would begin at an aerial station on Atlantic Boulevard near Pomona Boulevard
and terminate with a new, elevated station above the existing Fillmore Station on the Metro Gold Line.
The alternative would consist of at -grade and aerial segments.
ES.2.2.5 Freeway Alternatives
The four freeway alternatives would extend SR 710 as an access - controlled freeway with a total of four
travel lanes in each direction. Three of the freeway alternatives (F -2, F -5, and F -7) would be
constructed in tunnels, using primarily bored tunnels with short segments of cut - and -cover tunnels to
access the bored tunnel. The fourth freeway alternative (F -6) consists primarily of a combination of
surface and depressed segments, with one short cut - and -cover tunnel segment. The freeways would
be open to all vehicles without restrictions, except for a prohibition on hazardous materials in tunnels.
Figure ES -6 illustrates the alignment of the freeway alternatives.
SR 710 Study
December 2012 Page ES-8
Alternatives Analysis Report
-QDMetro Chapter 8 — References
Figure ES -5: IRT Alternatives
SR 710 Study
December 2012 Page 1
QD Alternatives Analysis Report
M et MA Chapter 8 — References
p -
.
r ,
Figure ES-6:
Freeway Alternatives
I South
Pasadena
on o ` .
Los Angeles
$
I ______ - -_ _
--^.,__s
w -.,� ✓ ,�
w'.
,✓
i
1
r
I
P. —
lerchenge,,,
El Sereho
rchang
i
toad
_.
}
NO al '
f Into age
`
Intercha
Unl
%'
�
�,
_
•..
P ddetts -_
sedan
zj:
x . -
�=
r
k
'San trop Bd - 1t
-
1
T
� '•
r
J 'S
i
larLL6li
t
_
-
p -
.
r ,
J
I South
Pasadena
on o ` .
Los Angeles
I ______ - -_ _
--^.,__s
w -.,� ✓ ,�
Los Angeles
i
1
I
rn ols
1
i
El Sereho
,.�✓
i
toad
_.
}
NO al '
f Into age
Interchange .j___ _ �____
Interchke"^.N ' hehge'�
I F i
t!gaadP }{ Overpass saw At -grade Section saaon Bored Tunnel Section Railroad
O Interchange asson Depressed Section Existing Freeway Metro Cold Line/Station
Cut and Coversection --- Existing Road "` °j qty Boundary
saa� Elevated section saa�
SR710 Study
December 2012 Page 2
Alternatives Analysis Report
0 Metro Chapter 8 — References
F -2. Alternative F -2 would originate at the existing SR 710 stub north of the 1 -10 freeway and connect to
SR 2 between the Verdugo Road and SR 134 interchanges. The alternative would bean eight -lane
freeway primarily constructed in two bored tunnels. Each tunnel would be dedicated to either
northbound or southbound travel, with two lanes on each oftwo levels in each tunnel.
F -5. Alternative F -5 would also originate at the existing SR 710 stub north of 1 -10, similar to Alternative
F -2, and connect to the SR 134 freeway near the Colorado Boulevard interchange. This alternative
would also be an eight -lane freeway with two bored tunnels for directional travel similar to Alternative
F -2. Alternative F -2 would provide interchange access to the SR 134 /SR 710 interchange both to and
from SR 134 for both eastbound and westbound travel and interchange access to Valley.
F -6. Alternative F -6 would also originate at the existing SR 710 stub north of 1 -10, but would consist of
a combination of surface and depressed freeway segments, ultimately connecting to the existing SR
710 stub south of the 1- 210 /SR 134 interchanges in Pasadena. Generally, Alternative F -6 would follow a
very similar alignment to the "Meridian Variation" approved in the Record of Decision in 1998. Ramps
would provide access to the freeway from Valley Boulevard, Mission Road /Alhambra Avenue,
Huntington Drive, and Del Mar Boulevard.
F -7. Alternative F -7 would also originate at the existing SR 710 stub north of 1 -10. It would connect via
a bored tunnel to the existing SR 710 stub south of the 1- 210 /SR 134 interchanges in Pasadena. This
alternative would also be an eight -lane freeway with two bored tunnels for directional travel similar to
Alternative F -2.
FS.2.2.6 Highway Alternatives
The highway /arterial alternatives would extend SR 710 by providing major roadway improvements to
existing arterials in the study area. Each ofthese alternatives would provide three lanes in each
direction along the length ofthe alignments. Where possible, the roadway widening associated with
each alternative is limited to one side of the existing roadway to reduce the number of property
acquisitions. Properties would be maintained on the other side of the roadway and in many areas have
a frontage road for access. Figure ES -7 illustrates the alignment of the highway alternatives.
H -2. Alternative H -2 would begin at the existing SR 710 stub north of 1 -10 and connect the SR 710
freeway directly to Concord Avenue. The SR 710 freeway would come to an end at Valley Boulevard and
transition to a major arterial that would travel over Valley Boulevard, the Union Pacific Railroad
(UPRR) tracks, and Mission Road /Alhambra Avenue to Concord Avenue. The alignment would
ultimately end near the intersection of San Rafael Avenue and Linda Vista Avenue.
H-6. Alternative H -6 would also begin at the existing SR 710 stub north of 1 -10 and connect the SR 710
freeway directly to Sheffield Avenue. The SR 710 freeway would come to an end at Valley Boulevard and
transition to a major arterial that would travel over Valley Boulevard, the UPRRtracks, and Mission
Road /Alhambra Avenue to Sheffield Avenue. The alignment would then continue to Huntington Drive,
to Fair Oaks Avenue, to Columbia Street, and then to Pasadena Avenue. just north ofthe intersection
of Pasadena Avenue and Bellefontaine Street, the roadway would split into a northbound segment
along Pasadena Avenue and a southbound segment along Saint John Avenue. The improvements in
both directions would end near Del Mar Boulevard.
SR 710 Study
December 2012 Page 3
AA
Figure ES -7: Highway Alternatives
2012
SR 710
Alternatives Analysis Report
Chapter 8 — References
Page 4
Alternatives Analysis Report
-QDMetro Chapter 8— References
ES.3.0 Transportation System Performance
The initial set of alternatives was evaluated against the five project objectives that were developed to
address the project need. For each of these objectives, 20 detailed performance measures were
developed as shown in Table ES -3.
Table ES -3: Transportation System Performance Measures
Objective
Performance Measures
1. Minimize travel time
Point -to -point travel time- vehicular
Point -to -point travel time -transit
Reduction in vehicle hours traveled (VHT)
Percentage of travel on managed facilities
2. Improve connectivity and mobility
New interchanges /transit connections
jobs reachable within fixed time
Transit boardings
Arterial volumes
Freeway throughput
3. Reduce congestion on freeway system
Facility miles operating at LOS Fl or worse
Facility miles operating at LOS E or FO
Vehicle miles traveled (VMT) on congested freeway segments
4. Reduce congestion on local street
Percent of intersections with congested approaches
system
Average v/c on arterials
VMT on arterials
Arterial cut - through percentage
North -south travel on arterials
5. Increase transit ridership
Increase in transit ridership
Percent of population within 1/4 mile of transit
Transit mode share
Based on each alternative's performance on the component performance measures that contribute to
the evaluation of each objective, a score from 1 to 7 was calculated for each objective, with 1 indicating
least favorable performance on that objective and 7 indicating the most favorable performance. Table
ES -4 summarizes the performance of each of the alternatives. The detailed evaluation of each of the
alternatives on each of the performance measures is presented in Chapter 3, and the calculation of the
1 to 7 score on each objective is described in Chapter 7.
SR710 Study
December 2012 Page 5
Table ES -4: Summary of Transportation System Performance Measures
M
ES.3.1 Minimizing Travel Time
Alternatives Analysis Report
Chapter 8 - References
The project objective of minimizing travel times in the Southern California region was evaluated using
several different measures including average point -to -point travel times for trips made by private
vehicles, average point -to -point travel times for trips made by transit, total vehicle hours traveled
(VHT), and others discussed in more
detail in Chapter 3. Figure ES -8: Regional Vehicular Travel
Time Performance
For travel time savings for automobile
trips, Alternatives F -2, F -6, and F -7
provide the greatest savings, as shown
in Figure ES -8. Alternative F -5 provides
somewhat less travel time savings.
None of the transit or highway
alternatives provides substantial travel
times savings for automobile trips.
For reducing point -to -point travel
times for transit trips in the study area,
Alternatives BRT -1, LRT-4A, LRT -4B,
LRT -4D, and LRT -6 are most effective,
and Alternatives BRT -6 and BRT -6A are
about half as effective, as shown in
Figure ES -9. None of the freeway or
highway alternatives are effective at
reducing point -to -point travel times for
100
> 90
F 80
5 70
°0 60
50
40 MMMM
1 30
- .._1_.. MINIM
€ O`� ti P P P ti 4 Z t
Z =o � 4 4r ro� �� „� q.
4i
Figure ES -9: Regional Transit Travel
Time Performance
e
rr
F
5
0
100
90
80
70
60
transit trips. 50 - - - -
40 1 1 Jill JI.I -'
The reduction in VHT includes all 30 0
vehicular (automobile and truck) trips ti 10
made during the a.m. and p.m. peak 0
.tea ar b� i' 0 0 b '� h 4P 1 1. b
periods in the six - county SCAG region. z 0 S r O �> e �p 4C t a AL' Z
The TSM /TDM Alternative and the =� m
transit alternatives are more effective at ay
this measure than the freeway and
highway alternatives, primarily because they remove some vehicular trips. The TSM /TDM Alternative,
BRT alternatives, and LRT alternatives reduce total VHT during the a.m. and p.m. peak periods by
89,000 to 102,000 hours. Alternatives F -2, F -5, F -6, F -7, H -2, and H -6 each reduce total VHT by a total
of 7,000 to 14,000 miles, since they do not include the transit improvements from the TSM /TDM
Alternative.
ES.3.2 Improving Connectivity and Mobility
The project objective of improving connectivity and mobility in the region was evaluated using several
different measures including: jobs reachable within a fixed time, increase in transit boardings,
reduction in arterial volumes, increase in north -south freeway throughput, and others discussed in
more detail in Chapter 3.
SR710 Study
December 2012 Page 6
Alternatives Analysis Report
M etro Chapter 8 - References
The No Build Alternative would not Figure ES -10: Recovery of Lost Job Accesstbi1ity
enhance connectivity or mobility in the °
region and travel conditions would 200 -
worsen due to growth in population 4�
and employment in the area. 150 - - -
Because of increasing congestion and 8 100 -- - -
delay on the regional transportation
network, the number of jobs accessible 50 - -
to residents of the study area within ,g 0 - - -- - --
25.3 minutes (the average commute 0 Ip ,�v ,� , ,� �ti �p
time in the United States) will decrease o C & m m Q $~
by 2035. Each of the alternatives was
evaluated based on the percentage of
this decrease in job accessibility that
the alternative would restore. As shown in Figure ES -10, Alternative F -6 performs best on this
measure, compensating for the entire decrease in job accessibility due to freeway congestion and
making additional jobs accessible. The highway alternatives only restore about half ofthe decrease in
job accessibility. The TSM /TDM Alternative, the BRT alternatives, and the LRT alternatives only
minimally compensate for the lost job accessibility.
Regional travel on transit routes through the study area is depressed because transit speeds in the
study area are slow. The increase in the number of transit boardings on north -south routes through
the study area reflects the performance of each alternative in attracting regional trips to transit. The
TSM /TDM Alternative and Alternative BRT -1 would result in an increase of approximately 25,000 total
daily boardings on north -south transit routes through the study area compared to the No Build
Alternative. Alternatives BRT -6, BRT -6A, LRT -4A, LRT -4B, LRT -4D perform slightly better, generating an
increase of approximately 30,000 total daily boardings. None of the freeway or highway alternatives
increase transit boardings.
As shown in Figures ES -11 and ES -12,
Alternatives F -5 and F -7 perform the
best at increasing north -south
throughput on the freeways in the
study area and reducing traffic volumes
on local north -south streets. These two
alternatives increase north -south
freeway throughput by 140,000 vehicles
per day, while removing 80,000 or
more daily vehicle trips from local
north -south streets. Alternatives F -2
and F -6 perform slightly less well on
these measures. None of the BRT or
LRT alternatives increase freeway
throughput or reduce traffic volumes
on local streets. The TSM/TDM
Figure ES -11: North -South Freeway
'Ihroughput (1000s)
1,200 __ _.. _.....
0
0
0
9
ca
.9
1,100
_..
1 900
1111'
800
2° a o _Q� � Ate: �A4 A: Ap
by
A
SR 710 Study
December 2012 Page 7
Alternatives Analysis Report
QD Metro Cbapter 8— Reference
Alternative, Alternative H -2 and Figure ES -12: Change in Daily Arterial
Alternative H -6 increase traffic volumes s Volumes (1000s)
on local streets and decrease volumes a 50
on freeways. - 25 _- _- - ■®
F,S.3.3 Congestion on 0
Freeway System -2 ' ' I
a so
One of the performance measures - 75
used to evaluate the project objective 100
of reducing congestion on the freeway z 125
system in the study area was the total Q 4 � tip y g p P ;p 40 � 4 4 � 4L, Z V Z D
vehicle miles traveled (VMT) on o C ro� ro or 4- � .�
congested freeway segments in the study At
area and total directional miles of
roadway facilities projected to operate at different levels of service (LOS). Severely congested facilities
were identified by calculating the total directional miles operating at LOS Fl (more than 10 percent
over capacity) or worse in 2035 during the a.m. or p.m. peak periods. Under the No Build Alternative,
the number of roadway facility miles operating at LOS Fl during the a.m. or p.m. peak periods is
projected to increase from 64 in 2008 to 100 in 2035. All transit - related alternatives provide only a
small benefit on the number of miles of freeway operating at LOS Fl, reducing it by less than five
percent. The freeway alternatives all provide reductions of at least 17 percent, with Alternative F -6
providing a reduction of more than 25 percent. The highway alternatives provide reductions of up to
12 percent.
ES.3.4 Congestion on Local Street System
Two of the performance measures used to evaluate the project objective of reducing congestion on the
local street system (arterial and collector roadways) in the study area was the total daily VMT on local
streets and the number of vehicle trips traveling on local streets that have neither an origin nor a
destination within the study area ( "cut- through traffic ").
Figure ES -13 shows total daily VMT on
the local street system in the study Figure ES -13: Arterial VMT (in millions)
area for each of the alternatives. Under
the No Build Alternative, the daily 7,2 —
arterial VMT in the study area will 0 7.0 —
increase from 6 million miles to 7 E 6.8
million miles. TSM /TDM 6.6
Alternative, the e L RT alternatives, and 6.4
the BRT alternatives have a minimal 6.2 I
effect on arterial VMT. The freeway b Q CO p p v h b � ti b
alternatives reduce daily arterial VMT Q S CQ m m� � � e ` ` 4
by 400,000 to 600,000 miles, with
Alternative F -6 providing the greatest
reduction, followed by Alternative F -7.
The highway alternatives add more arterial capacity along certain routes, which draws vehicle trips
onto the arterial street network. Alternative H -2 increases daily arterial VMT in the study area by 62,000
miles, while Alternative H -6 decreases daily arterial VMT by 75,000 miles.
SR710 Study
December 2012 Page 8
Alternatives Analysis Report
-QD Metro Chapter 8— References
Under the No Build Alternative by
2035, the percentage of cut-through
traffic will increase from 19 percent to
25 percent. As shown in Figure ES -14,
the TSM /TDM Alternative, the LRT
alternatives, and the BRT alternatives
result in no change in the percentage
of cut - through traffic. All of the freeway
alternatives reduce cut - through traffic
by 30 to 60 percent, with Alternative F-
7 being the most effective on this
measure. The highway alternatives also
result in no change in the percentage
of cut- through traffic.
ES.3.5 Transit Ridership
One of the performance measures
used to evaluate the project objective
of increasing transit ridership was the
ability to attract new transit riders. As
shown in Figure ES -15, the TSM /TDM
Alternative is forecast to attract over
16,000 new transit riders daily by 2035.
The BRT and LRT alternatives are
forecast to attract approximately
19,000 to 20,000 new riders. None of
the freeway or highway alternatives
attract new transit riders.
v
v 30%
0 25%
w
xeo 20%
2 15%
10%
5%
0%
E
Pi onra FC -14- Arheria i Oit- 'Ihrrni uh Pvrrrn to mr
4 A ti ti 'Fg P p p 1
W 0� ar �~ �~
1 111 11
4 4 4 4 2 jb
Figure FS -15: New Transit Riders
.a 25,000 _.... .__.. _..__ _...........
20,000 __......
15,000
H
10,000 .... _. _.
Z 5,000
0
43 1 p A2 h q P A 4' 4 4 4 2 s
04 h *
ti
■Riders generated by TSM/TDM service improvements
ES.4.0 Environmental and Other Performance Measures
This section describes the performance ofeach alternative in the initial set ofalternatives on the
performance measures related to the three project objectives pertaining to environmental impacts,
planning considerations, and cost efficiency. For each of these objectives, 22 detailed performance
measures were developed as shown in Table ES -5. This section describes the performance of the initial
set of alternatives on select performance measures related to these three project objectives shown in
Table ES -5.
Table ES -6 summarizes the performance of each ofthe alternatives on the three project objectives
pertaining to environmental and other concerns, with each alternative's performance on the
component performance measures assigned a score from 1 to 7 as was done for the transportation
system. The detailed evaluation of each of the alternatives on each of the performance measures is
presented in Chapter 4, and the calculation of the 1 to 7 score on each objective is described in
Chapter 7.
SR 710 Study
2012 Page
Alternatives Analysis Report
M etro Chapter 8— References
Table ES -5: Environmental and Other Performance Measures
Objective
Performance Measures
6. Minimize environmental and
Right -of -Way
community impacts related to
Full or partial residential or business acquisitions
transportation
Human Environment
Recreational /community sites impacted
Archeological sites impacted
Properties over 45 years old impacted
Significant historic resources impacted
Increase in noise exposure
Increase in mobile- source airtoxics (MSATs)
Increase in regional criteria pollutants
Increase in greenhouse gas (GHG) emissions
Hazardous waste sites impacted
Visual intrusion in communities
Scenic corridors impacts
Natural Environment
Areas of high paleontological sensitivity impacted
Exposure to adverse geotechnical conditions
Sensitive habitats impacted
Drainages impacted
7. Assure consistency with regional plans
Consistency with RTP/SCS goals
and strategies
Consistency with Measure R goals
Consistency with Metro LRTP goals
8. Maximize the cost - efficiency of public
Construction and right -of -way costs
investments
Available funding
Technical feasibilit
The environmental and community impacts discussed below have been identified based on
conceptual engineering of each of the alternatives. For alternatives that are evaluated further in the
Project Approval /Environmental Document (PA /ED) phase, designs will be refined to avoid or
minimize impacts to the extent possible. In addition, where feasible, mitigation measures will be
identified to reduce impacts that cannot be avoided.
Table ES -6: Summary of Environmental and Other Performance Measures
SR 710 Study
December 2012 Page 10
Alternatives Analysis Report
-QD Metro Chapter 8 — References
ESAI Environmental and Community Impacts
Property Acquisition. Potential property acquisitions were evaluated based on the total number of
residential or business acquisitions required for each alternative. The No Build Alternative and
Alternatives BRT -6 and BRT -6A would not require any property acquisitions. However, Alternatives
BRT -6 and BRT -6A would have a considerable impact to on- street parking and loading areas that
would affect businesses.
Of the remaining alternatives,
Alternative F -7 would require the Figure ES -16: Full Property Acquisitions
fewest property acquisitions (5), as "0 700 — - -
shown in Figure ES -16. Alternative 600 - -
BRT -1 would require the second least P 500 -
(19), but it would have a considerable o 300
i mpact to on- street parking and a 200
loading areas that would affect > 100
businesses, although this number z 0 W.
would be smaller than under a� a ap 4 p ~ pro Y 4' t' � � Z:
Alternatives BRT -6 and BRT -6A. The c r m 4' m� ' � ��
TSM /TDM Alternative and Alternatives le 4V
LRT-4A and LRT -4B would require
between 50 and 55 property
acquisitions. Alternatives LRT -4D and H -6 would require 103 and 184 acquisitions, respectively.
Alternatives F -2 and F -5 would require 313 and 255 acquisitions, respectively, which would be
concentrated around the north portal ofthe tunnels in these alternatives. Alternatives LRT -6 and F -6
would require 214 and 476 acquisitions, respectively, which would be spread along the alignments of
each of these alternatives. Alternative H -2 would require 632 acquisitions, which would also be spread
along the alignment ofthis alternative.
Cultural Resources. Potential impacts to cultural resources were evaluated based on the number of
known archaeological sites, historic (45 years or older) resources, and designated historic
districts /buildings potentially affected. None ofthe alternatives would impact any known
archaeological sites. The No Build Alternative would not result in any impacts to historic properties.
Alternative H -2 would have the greatest potential impact to historic resources and designated historic
districts /buildings with the potential to impact 1,055 historic - period buildings, 4 historic districts, 12
National Register eligible /listed properties, and 7 locally eligible /designated properties. The BRT
alternatives, TSM /TDM Alternative, Alternatives F- 7,LRT -4A, LRT -4B, and LRT -4D, would have the least
impacts to cultural resources impacting between 9 and 115 historic - period buildings and eight or less
historic districts, National Register eligible /listed properties, and /or locally eligible /designated
properties.
Noise. Noise impacts were evaluated by using the Federal Highway Administration (FHWA) Highway
Traffic Noise Prediction Model (FHWA RD -77 -108) to calculate the change in traffic noise levels
adjacent to 15 different freeway segments along 1 -210, SR 134, SR 710, 1 -110, 1 -10, 1 -710, 1 -605, SR 2,
and 1 -5, as well as for the non - tunnel sections of the alignments ofthe freeway and highway
alternatives.
SR 710 Study
December 2012 Page 11
Alternatives Analysis Report
QD Metro Chapter 8— Referen
The change in noise levels exposure Figure ES -17: Percentage Increase in Sensitive land Uses
under each alternative results from the to Unacceptable Noise Level
change in traffic patterns and volume
associated with each alternative.
Compared to the No Build Alternative, 5.0
the BRT and LRT alternatives would a 4.0
result in a small reduction in the W 3.0 _
acreage of sensitive land uses that 0 2.0 -
would be exposed to noise levels a 1.0 - - -
exceeding 65 dBA Leq, as shown in 0.0
Figure ES -17. Alternatives F -2, F -5, F -6, -1 _
F -7, H -2, and H -6 would result in an 4A C 4C 4 4 i p
increase in the number of sensitive
land uses that would be exposed to �+
noise levels exceeding 65 dBA Leq,
with Alternatives F -2 and F -6 resulting in the greatest increase of all alternatives. The No Build
Alternative would not result in any change to noise exposure within the study area.
Air Quality. Air quality impacts were Figure ES -18: Change in GHG Emissions Based on
evaluated by calculating the regional Regional VMT /VHT
vehicle emissions associated with each
alternative compared to the No Build 0.50 - -
Alternative for 2035 conditions. 0 . 0 00
Emissions were calculated using the — —
EMFAC 2007 emissions model with -0.50
data on VMT, VHT, and vehicle hours
of delay (VHD) from the traffic model. -1.00
Emission types evaluated included -1.50 - - - -
Mobile Source Air Toxics(MSAT),
criteria pollutants, and greenhouse -2.00
P 0 Q b N.) b 1 NIP
gases. All alternatives, with the 4u r o �� m�� e � �p > 'e 4' a' t s r
exception of Alternatives F -2, F -5, = ���r
F -6, F -7, H -2 and H -6 would result in
minor reductions of regional vehicle emissions primarily due to reductions in VMT, VHT, and VHD, as
shown in Figure ES -18. The other alternatives would result in minor increases in the various emissions
types; however, it should be noted that the regional -level methodology used in this analysis does not
take into account any reductions from the air scrubbers proposed for the tunnel alternatives. The
increases of regional vehicle emissions are primarily due to increases in VMT associated with the
freeway and highway alternatives. The No Build Alternative would not result in any change to regional
vehicle emissions beyond those estimated for this analysis.
Visual Resources. Visual impacts were assessed by evaluating the alternative's visual intrusion into the
surrounding communities and designated scenic corridors or vistas. Caltrans' Visual Impact Analysis
screening checklist was used for this analysis. The No Build Alternative would not result in visual
intrusion in the communities within the study area. The TSM /TDM Alternatives and the BRT
alternatives would result in low visual intrusion into communities. The freeway, highway, and LRT
alternatives would all result in high visual intrusion into communities, especially at areas of cut -and-
cover construction, tunnel openings, aerial structures, and roadway widenings within communities. In
SR 710 Study
December 2012 Page 12
Alternatives Analysis Report
-QDMetr(j Chap 8 — Refe
addition, Alternatives F -2, F -5, and H -2 would impact a portion of the Arroyo Parkway, a designated
scenic parkway.
Geological Conditions. Geological conditions were evaluated based on the percentage of the alignment
of each alternative within potentially liquefiable zones, subsurface material variability, or formational
materials known to contain natural gas that could be impacted by an alternative. In addition, the
number of active and potentially active faults crossing the alignment of an alternative were considered.
The No Build Alternative would not result in any changes to geological conditions in the study area;
however, the existing conditions do pose some risk to existing facilities within the study area.
Alternatives LRT -4A, LRT-4B, LRT -4D, F -2, F -5, and F -7 would have the greatest potential to encounter
adverse geotechnical conditions of concern, while the TSM /TDM Alternative would have the least
potential.
ES.4.2 Consistency with Regional Plans and Strategies
The alternatives were evaluated for consistency with the goals and objectives of the Southern
California Associated Government's (SLAG) 2012 -2035 Regional Transportation Plan /Sustainable
Communities Strategy (RTP /SCS), Measure R, and Metro's Long Range Transportation Plan (LRTP).
The No Build Alternatives is not consistent with any of the goals /objectives in these three planning
documents. The goals and objectives of SCAG's RTP /SCS focus on maximizing mobility and
accessibility and ensuring safety, reliability, sustainability, and productivity of the regional
transportation system; therefore, the BRT, LRT, and freeway alternatives have the greatest consistency
with goals /objectives in SCAG's RTP /SCS, while the highway alternatives have the least consistency.
The goals /objectives of Measure R focus on reducing congestion, improving traffic flow, improving
mobility, and increasing public transportation; therefore, the BRT and freeway alternatives have
consistency with the most goals /objectives of Measure R, followed by the LRT alternatives, while the
TSM /TDM and highway alternatives are the least consistent. Of all alternatives, the TSM /TDM
Alternative is consistent with the most goals /objectives in Metro's LRTP through implementation of
signal synchronizations, ITS technologies, bicycle and pedestrian improvements, and bus signal
prioritization.
ES.4.3 Maximizing Cost - Efficiency
The project objective of maximizing the cost - efficiency of public investments was evaluated using
three measures: estimated construction and right -of -way costs, the availability offunding, and
technical feasibility. The TSM/TDM Alternative and the BRT alternatives have the lowest capital and
right -of -way costs, other than the No Build Alternative. Alternative LRT -6 is expected to have the lowest
total capital and right -of -way cost of the LRT alternatives. Among the freeway alternatives, Alternative
F -6 is expected to have the lowest capital cost, because it has no bored tunnel segments and only a
short cut - and -cover tunnel segment. In addition, it makes use of existing infrastructure at the SR
710 /SR 134/1 -210 interchange and existing Caltrans right -of -way along the alignment. Among the
freeway tunnel alternatives, Alternative F -7 is expected to have the lowest capital and right -of -way costs
because it has the most direct tunnel and it also makes use of existing infrastructure at the SR 710 /SR
134/1 -210 interchange and existing Caltrans right -of -way at either end of the alignment.
The No Build Alternative, the TSM /TDM Alternative, the BRT alternatives, and the highway alternatives
were rated the highest among the alternatives on the measure of the availability of funding because
they could all be constructed within the Measure R budget for the project. The freeway alternatives
were rated slightly lower on the measure of the availability of funding because, while they would exceed
SR710 Study
December 2012 Page 13
M
Alternatives Analysis Report
Chapter S — References
the Measure R budget, it is expected that potential toll revenues could be used to fund construction of
these alternatives based on an independent study conducted by Metro that concludes that freeway
tunnel alternatives could be funded by future toll revenues. The LRT alternatives were rated lower than
the freeway alternatives on the measure of the availability of funding because they exceed the
Measure R budget, and transit fares would not be sufficient to fund their construction.
All of the alternatives were determined to be technically feasible, as similar facilities have been or are
being constructed in North America.
ES.5.0 Outreach Activities
ES.5.1 Project Scoping
The SR 710 project public outreach began in February 2011 with the "SR 710 Conversations," a series
of scoping meetings that began with 21 pre - scoping and scoping meetings throughout the study area.
The formal scoping period extended from March 3, 2011, through April 14, 2011, during which time
Caltrans and Metro accepted comments on the proposed project. All scoping comments were
documented in the 770North Gap Closure, Scoping5ummary Report, Volumes I and 11, dated
September 2011. The scoping comments were reviewed and analyzed to develop the project's updated
purpose and need, evaluation criteria, performance measures, and preliminary alternatives. This set
the foundation for the start of the Alternatives Analysis.
ES.5.2 Community/ Stakeholder Outreach
Building on the SR 710 Conversations, after the start of the SR 710 Study, community outreach efforts
began with two All Communities Convening (ACC) meetings held in March 2012 with the purpose of
gathering communities together in an open house format to discuss the project, share information
about the process, and gather comments. At these meetings, the Community Liaison Councils (CLCs)
were introduced as an option for community members to participate in the councils to generate
interest and participation within the various communities ofthe study area and to invite the public to
the next series of informational meetings. CLC meetings were held throughout the month of April to
notify the community of the upcoming Open House meetings scheduled for the fall.
The Technical Advisory Committee (TAC) was created with the purpose of providing technical input to
Metro, Caltrans, and the project team. Representatives of each jurisdiction in the study area, as well
as representatives of other stakeholder agencies, were invited to participate in the TAC. The TAC
reviewed technical analyses and methodologies and provided feedback on technical materials and
project information. TAC members were also responsible for sharing information with their agencies.
The TAC met eight times during the AA process, in January, February, March, April, May, July, August,
and November, 2012.
The Stakeholder Outreach Advisory Committee (SOAC) was created at the direction of the Metro
Board and consisted of members of planning commissions, transportation commissions, and elected
officials. The SOAC met in May, July, August, and November, 2012, to be briefed on the progress of
the SR 710 Study. SOAC members were responsible for providing updates to their respective
jurisdictions on the progress of the study and in turn recommend items to the project team to place
on the agenda for subsequent SOAC meetings.
Open House Meetings. A series of seven Open House meetings was held in May 2012 at locations
throughout the study area to share the project progress and to gather input from community
members and other stakeholders on the Initial Set of Alternatives and on the screening process. At the
SR 710 Study
December 2012 Page
Alternatives Analysis Report
_QDMetro Chapter 8 — Re
Open Houses, seven stations were set up covering the following topics: welcome and introduction,
study overview, environmental study review process, scoping process review, alternative concepts
overview, feedback, and next steps in the study.
Each station presented information in English and Spanish on large presentation boards, allowing
members of the community to proceed at their own pace. Each station was also staffed by members of
the project team, who were available to answer questions and provide clarifications. Attendees were
encouraged to provide their feedback on "Post-O" notes that could be affixed to the boards. All
feedback was documented and shared with the project team.
ES.6.0 Evaluation Process and Summary
In the secondary screening, the performance of the 12 alternatives in the initial set of alternatives on
the eight project objectives was evaluated using 42 performance measures. Table ES -4 presented
earlier summarizes the performance of each of the alternatives on the five objectives related to the
project need. Table ES -6 presented earlier summarizes the performance of each of the alternatives on
the three objectives related to environmental, planning, and cost concerns.
The No Build Alternative and the TSM/TDM Alternative are required to be evaluated in the PA /ED
phase. Therefore, they should be evaluated further.
Among the BRT alternatives, the measures for the objectives related to transportation system
performance were similar to one another, with Alternative BRT -1 performing slightly better at reducing
transit travel times, but Alternatives BRT -6 and BRT -6A performing slightly better at increasing access
to high- frequency transit service and increasing north -south transit patronage. Therefore, performance
on the transportation objectives does not clearly favor one alternative over the others. However,
Alternatives BRT -6 and BRT -6A could be implemented with no right -of -way acquisition and would also
have a smaller potential impact on sensitive habitat. Therefore, Alternatives BRT -6, along with the
design variation Alternative BRT -6A, should be evaluated further in the PA /ED phase.
Among the IRT alternatives, the measures for the objectives related to transportation system
performance were similar to one another. However, on the measures for the objectives related to
environmental and other concerns, Alternative LRT -6 was clearly inferior to Alternatives LRT -4A,
LRT -413, and LRT -41D. Alternative LRT -6 would require the acquisition of hundreds of properties, impact
more historic period properties, and impact more community facilities. Similarly, compared to
Alternatives LRT -4A and LRT -48, Alternative LRT -4D would have greater property impacts. Therefore,
Alternatives LRT -4A and LRT -46 should be evaluated further in the PA /ED phase.
Among the freeway alternatives, Alternatives F -6 and F -7 are superior to Alternatives F -2 and F -5 on
the measures for the objectives related to the transportation system performance. Alternatives F -6 and
F -7 each performed best on either minimizing travel times or improving connectivity and mobility, and
they both performed best on the objective of reducing congestion on local streets. The performance on
the objectives related to environmental and other concerns distinguished Alternatives F -6 and F -7
from one another. Alternative F -7 would require only a small number of property acquisitions (fewer
than 10), compared to the over 400 required for Alternative F -6 in addition to properties that Caltrans
already owns. Alternative F -7 would also impact fewer historic period properties and community
facilities. Therefore, Alternative F -7 should be evaluated further in the PA /ED phase.
None of the highway alternatives perform well on the measures for objectives related to transportation
system performance. They also performed poorly on the measures for objectives related to
SR 710 Study
December 2012 Page 15
Alternatives Analysis Report
0 Metro Chapter S — References
environmental and other concerns, especially Alternative H -2. Therefore, neither of the highway
alternatives should be evaluated further in the PA /ED phase.
Thus, the alternatives recommended for further evaluation in the PA /ED phase are as follows:
• The No Build Alternative
• The TSM /TDM Alternative
• Alternative BRT -6, with possible refinements as described below
• Alternative LRT -4A /B, with possible refinements as described below
• Alternative F -7, with possible refinements, as described below
Recommended Refinements of Alternatives
No single alternative performs most favorably on all eight project objectives. Therefore, as the
alternatives are further evaluated in the PA /ED phase, refinements of these alternatives that improve
their performance and reduce their impacts should be developed and considered, as well as
alternatives that combine elements of alternatives whose performance complements each other.
Recommended Refinements of Alternatives
In the PA /ED phase, alternatives will be refined first to avoid and then to minimize potential impacts
to the extent possible. Where impacts cannot be avoided or minimized, feasible mitigation measures
will be identified to reduce impacts. Additional refinements of alternatives that should be investigated
in the PA /ED phase include the following:
• The No Build Alternative should be updated to reflect the financially constrained project list in
the 2012 Regional Transportation Plan /Sustainable Communities Strategy (RTP /SCS). This
plan was adopted by SCAG after the initiation of the AA, but it would be appropriate to update
the No Build Alternative in the PA /ED phase to be consistent with the newly adopted plan. The
ridership and travel demand forecasting in the PA /ED phase will be based on the 2012
RTP /SCS.
• The TSM/TDMAltemative was found to have potential right -of -way impacts, primarily
resulting from the spot intersection and roadway segment improvements included in the
alternative. These spot improvements should be refined in coordination with the local
jurisdictions to maximize the alternative's benefits and to minimize its impacts. In addition,
these improvements should be refined to identify opportunities to create "complete streets"
that enhance the pedestrian and bicycle environment and to ensure that they do not detract
from it. The other components of the TSM /TDM Alternative should also be reviewed and
refined to look for additional opportunities to improve the performance of the alternative.
• Alternative BRT-6, like all of the BRT alternatives, would displace a large amount of on- street
parking. Therefore, refinements should be considered to its design, alignment, and /or
operational characteristics to minimize their impact to on- street parking. Refinements should
also be considered to maximize ridership and productivity (passengers per bus).
• Alternative IRT4A/B station locations should be refined to maximize ridership, minimize
property impacts, and to facilitate transfers to the Metro Gold line at its northern and southern
termini.
SR 710 Study
December 2012 Page 16
Alternatives Analysis Report
-QDMetro Chapter 8— References
Alternative LRT -4A /B could be combined with enhanced bus service, including feeder routes to
its stations. By making Alternative LRT -4A /B the spine of a transit network that serves
destinations to its east and west, and not solely along its alignment, it may be possible to
attract additional transit ridership and improve the performance of this alternative.
Alternative F -7 should incorporate refinements to its design and alignment to minimize its
impact. Potential tolled operations to improve its financial feasibility should also be evaluated.
Restriction on use by trucks should be evaluated to determine if they are effective at reducing
impacts.
Alternative F -7 could be combined with a BRT or other enhanced bus service to improve the
performance ofthis alternative on the performance measures related to the transit system.
Alternative F -7 was found to not increase transit ridership or transit mode share. By
introducing a well- designed BRT or other enhanced bus service into Alternative F -7, it may be
possible to diminish north -south transit travel times through the study area and attract
additional transit ridership.
SR710 Study
December 2012 Page 17