OB - 2013-0012 - The Selection of Professional Services Firms for Project Support Services During the Construction of the Public PlazaRESOLUTION NO. 2013-0012
A RESOLUTION OF THE OVERSIGHT BOARD FOR THE SUCCESSOR AGENCY TO
THE ROSEMEAD COMMUNITY DEVELOPMENT COMMISSION CONFIRMING THE
SELECTION OF PROFESSIONAL SERVICES FIRMS FOR PROJECT SUPPORT
SERVICES DURING THE CONSTRUCTION OF THE PUBLIC PLAZA
WHEREAS, THE Rosemead Successor Agency received the Finding of Completion
on April 18, 2013 from the Department of Finance; and
WHEREAS, the Finding of Completion states that the Rosemead Successor Agency
may utilize proceeds derived from bonds issued prior to January 1, 2011 in a manner
consistent with the original bond covenants per Health and Safety Code section
34191.4(c); and
WHEREAS, the Rosemead Successor Agency is holding approximately $7.1 million
in bond proceeds derived from bonds issued prior to January 1, 2011 for Capital
Improvement Projects identified in the bond covenants; and
WHEREAS, the Rosemead Successor Agency will be required to provide oversight
of the completion of the Capital Improvement Projects to ensure compliance with the
bond covenants; and
WHEREAS, the approved Capital Improvement Projects have been included on
each Recognized Obligation Payment Schedule filed by the Rosemead Successor
Agency; and
NOW, THEREFORE, THE OVERSIGHT BOARD FOR THE SUCCESSOR
AGENCY TO ROSEMEAD COMMUNITY DEVELOPMENT COMMISSION HEREBY
RESOLVES:
1. The Rosemead Successor Agency Oversight Board confirms that the
professional services firms listed below are qualified and capable to provide
project support services during the construction of the public plaza.
2. That contracts with the following firms shall not exceed the amounts listed in the
table below. If any contract amendments are required, all such changes shall be
brought back to the Oversight Board for review and approval. Further, that staff
time in direct relation to the construction of the public plaza is authorized and
shall not exceed the amount listed below.
Trade
Firm
Total Budget
Public Works Project Inspection
SCB Inspections
$ 57,000.00
Civil Engineering Project Management
CEJ Engineering
$ 22,000.00
Geotechnical Engineering Inspection
Willdan Engineering
$ 7,855.00
Electrical Engineering Project Inspection
CEJ Engineering
$ 4,500.00
Mechanical and Plumbing Project Inspection
STO Design Group
$ 7,200.00
Design /Landscape Architectural Project Inspection
Lawrence Moss and
Associates
$ 45,075.00
City Staff Project Administration
N/A
$ 52,600.10
Total Cost $ 196,230.10
% of Construction 14.58%
3. Successor Agency staff is directed to submit documents to the Department of
Finance as necessary, including an amended Recognized Obligation Payment
Schedule.
4. Successor Agency staff is directed to provide a copy of this Resolution to the
County Auditor - Controller, the State Controller's Office and the State Department
of Finance.
PASSED, APPROVED AND ADOPTED THIS 16 DAY OF October, 2013
d�� �! (�
Pat Wallach
Chair
ATTEST:
MattheiV Hawke w rth
Successor Agency Staff
I HEREBY CERTIFY that the above foregoing resolution was duly passed and adopted by
the Oversight Board for the Successor Agency to the Rosemead Community Development
Commission at its regular meeting on the 16 day of October 2013, by the following vote, to
wit:
Ayes: Allred, Jones, Lash, Redondo - Churchward, Wallach
Noes: None
Absent: Miller, Sotelo
Abstained: None
Mathellp E. Haw esworth
Successor Agency Staff
Assistant City Manager
ROSEMEAD SUCCESSOR
AGENCY STAFF REPORT
TO: THE HONORABLE CHAIR AND BOARD MEMBERS
FROM: MATTHEW HAWKESWORTH, ASSISTANT CITY MANAGER
DATE: OCTOBER 16, 2013
SUBJECT: CONSTRUCTION ADMINISTRATION AND SUPPORT SERVICES —
DOWNTOWN PLAZA PROJECT
SUMMARY
In June, 2013, the Oversight Board approved Resolution 2013 -0006 which confirmed
the selection of E.C. Construction for the completion of the Downtown Plaza Project.
The Downtown Plaza project includes the construction of a public plaza in the area
between City Hall and the County Library. The project will include new, decorative
hardscape, improved landscape, and multiple water features. The plaza will
complement existing parking lot improvements that were completed in spring 2012. It is
hoped that once the plaza is completed, it will become a valuable community resource
with the addition of seating areas, interactive water features, and space for public
events.
During the construction phase, it is necessary that construction inspection,
administration, and support services be provided to ensure that the new plaza is built in
accordance with project plans and specifications. Typically referred to as "soft costs ",
these services include day -to -day inspection and construction oversight, project
administration, and specialty inspection of specific construction trades, including
landscape architectural services and mechanical, electrical, plumbing, and geotechnical
engineering services. Such costs will not exceed fifteen (15) percent of the total
construction costs and are further detailed in this report.
Staff Recommendation
It is recommended that the Oversight Board approve Resolution 2013 -0012 confirming
the contracts associated with construction support for the Public Plaza Project.
DISCUSSION
In 2010, the City completed the Parks and Facilities Master Plan to help serve as a
guide for future capital improvements. As such, the City, with significant public input,
identified a need to create a "Downtown" public plaza that will create a vibrant public
gathering space for the community. Together with the new Civic Center Parking Lot
and renovated Rosemead Community Recreation Center, this area will serve as an
inviting space for public events and will help complement nearby commercial uses.
Rosemead Successor Agency Oversight Board
October 16, 2013
Paae 2 of 5
The Rosemead Downtown Plaza project includes the construction of a public gathering
space in between City Hall and the County Library and will include multiple water
features, improved landscape and irrigation, and improved hardscape that will
contribute to increased aesthetics and utility in the Civic Center. These features will
replace the existing parking lot at this location that is in a state of disrepair. Existing
conditions in the parking lot include deteriorated paving, little /no site drainage, and a
lack of accessible walkways.
A construction contract was reviewed and confirmed by the Oversight Board in June
2013 with E.C. Construction in the amount of $1,346,205.34. The contract was
subsequently approved by the City Council on September 24, 2013. It is expected that
construction will get underway in mid - November 2013. During the construction phase, it
is necessary that inspection, oversight, and construction management services be
provided to ensure the proper construction of the project. Such services (also known as
"soft costs ") will not exceed 15% of the total construction contract amount. Due to
complexity of this project, several specialty inspection services are needed and are
further described below.
Inspection /Construction Cost Overview
Trade
Firm
Total Budget
Public Works Project Inspection
SCB Inspections
$ 57,000.00
Civil Engineering Project Management
CEJ Engineering
$ 22,000.00
Geotechnical Engineering Inspection
Willdan Engineering
$ 7,855.00
Electrical Engineering Project Inspection
CEG Engineering
$ 4,500.00
Mechanical and Plumbing Project Inspection
STO Design Group
$ 7,200.00
Design /Landscape Architectural Project Inspection
LIMA
$ 45,075.00
Staff Project Administration
N/A
$ 52,600.10
Total Cost $ 196,230.10
% of Construction 14.58%
Rosemead Successor Agency Oversight Board
October 16, 2013
Pape 3 of 5
1. Public Works Proiect Inspection (Demolition, Layout, Paving, Daily Oversiaht)
The City will utilize an existing on -call services agreement with SCB Inspections
to provide regular project inspection services. SCB Inspections will supervise
daily construction activities and ensure that work is completed in accordance with
project plans and specifications. The hourly rate for these services is highly
competitive at $57 per hour, and will not exceed a total of 1,000 hours for this
project. SCB Inspections is experienced in providing inspection services for
public works projects.
Contract Cost: $57,000
2. Engineering Project Management (Civil Engineering Functions)
The City will utilize an existing on -call services agreement with CEJ Engineers to
provide project engineering support services. CEJ completed survey, layout,
grading, and drainage plans for this project and will ensure that construction is
completed in accordance with project plans and specifications. The hourly rate
for these services is highly competitive at $110 per hour for construction
management services, and will not exceed a total of 200 hours for this project.
CEJ Engineers has extensive experience in general engineering and project
management services.
Contract Cost: $22,000
3. Geotechnical Engineering (Compaction Analysis, Soils Enaineerina)
The City will utilize an existing on -call services agreement with Willdan
Geotechnical to provide soils engineering support services. Willdan completed
soils testing and concrete mix requirements for this project and will ensure that
construction is completed in accordance with project plans and specifications.
The hourly rate for regular observation services is highly competitive at $85 per
hour, and will not exceed 56 hours for this project. Additional related laboratory
and review costs are also included. Willdan has extensive experience in public
works geotechnical and observation services.
Contract Cost: $7,855
4.
The City will utilize an existing on -call services agreement with CEG Engineering
to provide electrical engineering support services. CEG completed electrical
design services for this project and will ensure that construction is completed in
accordance with project plans and specifications. The hourly rate for these
services is highly competitive at $100 per hour, and will not exceed 45 hours for
this project. CEG has extensive experience in public works electrical engineering
services.
Contract Cost: $4,500
Rosemead Successor Agency Oversight Board
October 16, 2013
Page 4 of 5
5. Mechanical and Plumbing Inspection (Water Features)
The City will utilize STO Design Group to provide mechanical and plumbing
engineering support services. STO completed mechanical and plumbing design
services for this project and will ensure that construction is completed in
accordance with project plans and specifications. The hourly rate for these
services is highly competitive, ranging from $125 to $165 per hour, and will not
exceed 50 hours for this project. STO has extensive experience in public works
mechanical and plumbing services.
Contract Cost: $7,200
6. Design and Landscape Architectural Inspection
The City will utilize Lawrence Moss and Associates (LMA) to provide overall
design review and landscape architectural support services. LMA completed
overall design services for this project and will serve as the architect -of- record for
the project. The hourly rate for these services is highly competitive, ranging from
$135 to $150 per hour, and will not exceed 329 hours for this project. LMA has
extensive experience in public works landscape architectural services.
Contract Cost: $45,075
7. Project Administration /City Staff Costs
In addition to these contractual services expenses, this project will involve a high
level of interaction between City staff, design consultants, and construction
contractors. As such, an allotment of staff hours is included in the soft cost
estimate for this project. These services will include project administration,
contractor coordination, and regular oversight of the project. The total hours
estimate is detailed in Attachment 3.
Estimated Cost: $52,600
FINANCIAL REVIEW
This project was included in the City's Capital Improvement Program is funded entirely
through tax increment bond proceeds through the former redevelopment agency. The
total budget for this project is $2,250,000. The total estimated for the project
(construction costs and soft costs) including contingencies is $1,747,366.24.
Rosemead Successor Agency Oversight Board
October 16, 2013
Page 5 of 5
Submitted By:
W SIU � yan
Management Analyst
Submitted By:
Chris glarearello
Director of Public Works
Attachments:
(1) Resolution 2013 -0012 (Oversight Board Confirmation of Construction Contract)
(2) Professional Services Inspection /Oversight Proposals
(3) City Staff Hours Estimate