Loading...
OB - Item 3B - Review of Expenditures - Rosemead Park Improvements ProjectROSEMEAD OVERSIGHT BOARD STAFF REPORT TO: THE HONORABLE CHAIR AND BOARD MEMBERS FROM: MATTHEW HAWKESWORTH, ASSISTANT CITY MANAGER DATE: FEBRUARY 9, 2015 SUBJECT: REVIEW OF EXPENDITURES — ROSEMEAD PARK IMPROVEMENTS PROJECT SUMMARY As a part of July 2010 tax increment bond issuance by the former Redevelopment Agency, the City included funding for a project to renovate and improve the facilities at Rosemead Park. The bond issuance included approximately $280,000.00 for miscellaneous park improvements and $750,000.00 for turf improvements, for a total of $1,030,000.00. Extensive improvements have been completed at the park at this time, including the replacement of the playground equipment on the north playground, construction of the new basketball courts, and miscellaneous work and improvements to the surrounding areas. As is common with construction projects, additional elements and expenses have been added to this project as it was in progress. Included in this report is a summary of all project expenses to date and a request for confirmation of the expenses that were not previously presented to the Oversight Board. Staff Recommendation It is recommended that the Oversight Board approve Resolution 2015 -0002 confirming the expenses associated with the Rosemead Park Improvements Project. DISCUSSION Included for the review of the Oversight Board is a review of expenditures related to the Rosemead Park Improvements Project that have not previously been reviewed by the Oversight Board. All of these products and services were procured consistent with the City's purchasing guidelines and have been completed to the satisfaction of staff. Basketball Court Improvement Project A contract for the removal and replacement of the existing basketball courts was issued to PK Construction in February 2014 in the amount of $117,227.50. Throughout the course of construction, several unforeseen conditions were encountered that resulted in increased costs. These items included the demolition and removal of concrete that was far greater, in some areas, than the 4" that was included in the plans. This required the utilization of specialized equipment and additional labor. Also, based on the conditions, more dirt and base was removed TfBM NO. Rosemead Successor Agency Oversight Board February 9, 2015 Page 2 of 3 than initially anticipated, resulting in a higher cost. At the time of approval, the Oversight Board approved the contract and a contingency amount of ten percent for additional or unforeseen construction expenses. The change order amount for this contract totaled $29,000.00 (24.74 %) which is within the signatory authority of the City Manager; however, the additional expense requires the confirmation of the Oversight Board. • Original Contract Cost: $117,227.50 • Additional Expenditures: $ 29,000.00 • Total Contract Amount: $146,227.50 Basketball Court Surface Issues Upon completion of the basketball court project, it was determined that the playing surface, as specified and constructed, was slippery and not suitable for safe play. Staff determined that the best remedy for this situation was to sandblast the playing surface to dull the concrete finish and improve the grip for players. This process, which was conducted utilizing two vendors, has a cost of $ $30,600. Since both phases of the work were completed, safety on the courts has improved significantly and user satisfaction has increased. Additionally, as the playing surface of the courts was sandblasted, the striping and logos that were placed on the original surface was damaged and needed to be repainted. The firm that painted the striping originally was contacted and completed a repainting of the courts for a cost of $3,850. Confirmation of expenditures with the following firms is requested: • Painting and Decor, Inc. Sandblasting $ 21,900.00 • Active Sandblasting, Inc. Sandblasting $ 8,700.00 • Mike Panzarello Striping /Painting $ 3,850.00 2. Landscaping Improvements Upon completion of the Basketball Courts, staff and the City's landscape contractor, TruGreen Landcare, undertook extensive efforts to improve the landscaping in the vicinity of the basketball courts. These efforts included the installation of a new irrigation system, the preparation, leveling and amending of existing soil, and the installation of approximately 8,000 square feet of hybrid Bermuda sod. The expense incurred with TruGreen Landcare was $21,640.00 • TruGreen Landcare Landscaping $ 21,640.00 3. Tree Plantings In conjunction with the landscaping improvements that took place around the basketball courts, the north parking lot, and along the fence between the park and Rosemead High School, staff procured and oversaw the planting of more than fifty (50) trees. These trees were selected by the City's arborist for quality and aesthetics and purchased from A.Y. Nursery, Inc., a frequent supplier of trees for the City, at a cost of $ 15,107.40. • A.Y. Nursery, Inc. Tree Purchases $ 15,107.40 Rosemead Successor Agency Oversight Board February 9, 2015 Page 3 of 3 4. Turf Improvements The Public Works Department has begun the task of repairing and rehabilitating the turf at Rosemead Park. City staff, aided by staff from TruGreen Landcare, began work on the playing fields, which are the most severely impacted areas on the park. The areas were fenced off so that surface could be leveled with soil and over seeded with new grass seed. This work will continue in phases to minimize impacts to park patrons, with each phase or section being fenced off for 8 -10 weeks. The costs to this time include the rental of a fence and the purchase of seed. • So Cal Industries Fence Rental $ 2,602.20 • Stover Seed Company Seed Purchase $ 2,651.98 5. Park Fixtures Staff has identified new trash cans to be ordered and installed in the vicinity of the basketball courts and northern parking lot. These trash cans, which have been used throughout Rosemead and other parks in the City, are durable and coated to prevent graffiti and vandalism. The trash cans will be purchased from Dave Bang and Associates, at a cost of $830.00 each, and staff would like to purchase 6. • Dave Bang and Associates Trash Cans /Fixtures $ 4,980.00 FINANCIAL REVIEW This project is being funded entirely through tax increment bond proceeds from the former Redevelopment Agency. Included in the bond issuance, there is funding of $280,000.00 for park improvements and $750,000.00 for turf improvements. Submitted By: 9 00"" Sean Sullivan Acting Public Works Manager Attachments: 1. Resolution 2015 -0002 2. Project Summary Worksheet RESOLUTION NO. 2015 -0002 A RESOLUTION OF THE OVERSIGHT BOARD FOR THE SUCCESSOR AGENCY TO THE ROSEMEAD COMMUNITY DEVELOPMENT COMMISSION CONFIRMING THE AWARD OF CONTRACTS AND RELATED SUPPORT COSTS FOR THE ROSEMEAD PARK IMPROVEMENTS PROJECT — BASKETBALL COURTS WHEREAS, THE Rosemead Successor Agency received the Finding of Completion on April 18, 2013 from the Department of Finance; and WHEREAS, the Finding of Completion states that the Rosemead Successor Agency may utilize proceeds derived from bonds issued prior to January 1, 2011 in a manner consistent with the original bond covenants per Health and Safety Code section 34191 A(c); and WHEREAS, the Rosemead Successor Agency is holding approximately $7.1 million in bond proceeds derived from bonds issued prior to January 1, 2011 for Capital Improvement Projects identified in the bond covenants; and WHEREAS, the Rosemead Successor Agency will be required to provide oversight of the completion of the Capital Improvement Projects to ensure compliance with the bond covenants; and WHEREAS, the approved Capital Improvement Projects have been included on each Recognized Obligation Payment Schedule filed by the Rosemead Successor Agency; and WHEREAS, the Oversight Board of the Rosemead Successor Agency previously adopted Resolution 2014 -0002 on February 19, 2014 confirming the project and a contract with P.K. Construction, related project management, and staffing. NOW, THEREFORE, THE OVERSIGHT BOARD FOR THE SUCCESSOR AGENCY TO ROSEMEAD COMMUNITY DEVELOPMENT COMMISSION HEREBY RESOLVES: The Rosemead Successor Agency Oversight Board confirms the additional use of $110,431.58 of 2010 Tax Increment Bonds for change orders and related expenditures related to the Rosemead Park Basketball and Turf Improvement Projects. Basketball Court Change Orders $29,000.00 Sandblasting $30,500.00 Painting $3,850.00 Landscaping $21,640.00 Tree Planting $15,107.40 Turf Improvements $5,254.18 Trash Cans $4,980.00 Total $110,431.58 2. Successor Agency staff is directed to submit documents to the Department of Finance as necessary. 3. Successor Agency staff is directed to provide a copy of this Resolution to the County Auditor - Controller, the State Controller's Office and the State Department of Finance. PASSED, APPROVED AND ADOPTED this 9th day of February, 2015. Pat Wallach Chair ATTEST: Matthew Hawkesworth Successor Agency Staff 00 m a O N N M, 0 0 0 0 0 0 0 0 O O d m O O O O O O h N c4 O O 0 0 01 rl W l tD l 0 0 m rl 00 m N L!1 N N OI N N N H v a o c m U bD Y 0 U U H m '° a o4 a m — G O a N v- 00 m n al m U x U bA O E m m m L W 0 a m ai t C U m C @ O U0 4 O °c O U a a v a .a. ai v a > c a v c v z O N N VI J H li V) d' T �n c v U0 L C O m y O � OU E O U O m w O "? O Q a m a m c m u c a v c C'^ d N C N m U c> '++ v C7 z m> > ai _ Y O } V > N VI 4 tio y C > N m 0 o u a m N _ m a U m m L N J Y C r N C N m N O O �n ` i O H H O U m m Q a O O N U U bA V U 6 — " 0 — o o O is n m N m z O_ O=A ..O a D_ L -0 (U N N E U _C C m m w m n m m ¢ H a 00 m a O N N M,