Loading...
The URL can be used to link to this page
Your browser does not support the video tag.
CC - Item 4G - Garvey Park Duff Field Renovations - Award of Contract - Lighting Installation
iE s ME ° �° ROSEMEAD CITY COUNCIL STAFF REPORT TO: THE HONORABLE MAYOR AND CITY COUNCIL FROM: JEFF ALLRED, CITY MANAGER e/;' DATE: FEBRUARY 10, 2015 SUBJECT: GARVEY PARK DUFF FIELD RENOVATIONS — AWARD OF CONTRACT - LIGHTING INSTALLATION SUMMARY As a part of the City's Fiscal Year 2014-15 Capital Improvement Program, the City Council approved the "Garvey Park Duff Field Renovations" Project which includes the installation of new lighting, fencing, turf and miscellaneous site improvements at the west ball field at Garvey Park. The project consists of the addition of new sports lighting, replacement of the existing chain link fence and backstop, and improvements to the landscape, irrigation, and adjacent concrete sidewalk. The work at this facility will take place in three phases based on the distinct scopes of work and the specialties of the contractors required to complete the work. This phase of work includes the installation and expansion of lighting on both the ball field and the multipurpose field. The lighting installation will be performed by Musco Lighting who has been the exclusive provider of sports lighting to the City for several decades. Musco's proposal includes installation of twelve ball field light standards on six galvanized poles along the ball field and the multipurpose field. The project will achieve significant energy efficiencies, improved lighting controls, and include an extensive warranty and maintenance program for a period of twenty-five years. Staff Recommendation It is recommended that the City Council: 1. Authorize the City Manager to enter into a professional services agreement with Musco Lighting as a sole source for the installation of sports lighting at Garvey Park Duff Field and multi-purpose field in an amount not to exceed $242,961. In addition, authorize a contingency amount of $24,500 (approximately 10%) to cover the cost of any unforeseen construction expenses. 2. Approve Resolution 2015-10, authorizing an additional appropriation of $92,500 from the Street Lighting District Fund to complete the project as proposed. ITEM NUMBER: AG City Council Meeting February 10,2015 Page 2 of 3 DISCUSSION As a part of the City's Fiscal Year 2014-15 Capital Improvement Program, the City Council approved the "Garvey Park Duff Field Renovations' Project which includes the installation of new lighting, fencing, turf and miscellaneous site improvements at the west ball field at Garvey Park. The project consists of the addition of new sports lighting, replacement of the existing chain link fence and backstop, and improvements to the landscape, irrigation, and adjacent concrete sidewalk. The work at this facility will take place in three phases based on the distinct scopes of work and the specialties of the contractors required to complete the work. This phase of work includes installation and expansion of lighting on both the baseball field and the multipurpose field. Musco Lighting has been the sole provider of Rosemead's sports lighting, including ball field and pool facility lighting, for several decades. Musco is regarded as the worldwide industry standard for sports lighting as they design and manufacture lighting systems for sports fields and stadiums, up to the professional level, all over the world. Additionally, Musco's Green System is rated up to 50% more efficient than standard sports lighting systems. Lastly, Musco's proprietary Control-Link helps users control, monitor, and manage facility lighting on-site or remotely, via the internet, from anywhere. This sole source agreement is authorized pursuant to sections 037.204(E) and 039.204(G) of the Rosemead Municipal Code. Musco's proposal includes installation of twelve ball field light standards on six poles at the west ball field and multipurpose field at Garvey Park. The proposed work includes the installation of 6 galvanized poles and corresponding foundation work, the furnishing of all fixtures and all necessary electrical and installation work. Furthermore, extensive staff training will be provided by Musco regarding the controls and operations of the lighting system. All Musco lighting systems include a comprehensive warranty and maintenance package for a period of twenty-five (25) years. FINANCIAL REVIEW The Garvey Park Duff Field Renovations Project is included in the FY 2014-15 Capital Improvement Program. The project has a budget of $325,000.00 utilizing General Funds and Street Lighting District Funds. The allotted mount of Street Lighting District Funds for this project is currently $175,000.00 and the total appropriation necessary to award this contract is $267,461.00. An appropriation of $92,500.00 from the Street Lighting District Fund is requested in order to complete this project. The current fund balance for the Street Lighting District Fund is approximately $1,400,000.00. ENVIRONMENTAL REVIEW This project is categorically exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15301 (C) of the CEQA Implementing Guidelines. PUBLIC NOTICE PROCESS This item has been noticed through the regular agenda notification process. City Council Meeting February 10,2015 Page 3 of 3 Prepared cc, Sullivan Acting Public Works Manager Submitted By: David Montgomery-Scott Director of Parks and Recreation Attachments: A. Scope of Work and Proposal of Musco Lighting B. Resolution 2015-10 0 muspo, ltd rStr Light Structure GreenTM Turnkey Scope of Work Garvey Park- Phase II Duff Field Rosemead, CA Project #165103 Revision- January 30, 2015 Owner Responsibilities: I. Total access to the site and pole locations for construction. Must be able to move from location to location on standard rubber tires. 2. Removal of any trees, limbs, shrubs, etc. for total access to pole locations. 3. Removal,replacement, and repair of all fencing necessary for construction. 4. Repair and replacement of any field turf, asphalt, curbs, and concrete damage. Review with city. 5. Locate and mark existing irrigation systems prior to excavation as necessary. 6. Provide on-site area for excavated drilling spoils. 7. Additional mobilization cost if needed for electrical connections to cell tower pole lighting equipment. Musco Responsibilities: 1. Provide required (5)poles, (20) fixtures, (5) foundations, and associated designs. 2. Provide structural design for poles and foundations, certified by a professional engineer licensed in the State as required. Structural Design to he based off Class 5, Standard Soil, CBC-2013 110mph. 3. Provide layout of pole locations and aiming diagram. 4. Provide light test upon owner supplied electrical system. 5. Provide Project Management assistance as needed. 6. Provide review of electrical design as provided by Electrical Contractor or Electrical Engineer. 7. Provide (2) GFCI Lockable Assemblies to be installed at 10' on poles Al, A2. 8. Provide mounting accommodations for a security light fixture to be installed on pole A 1 and A2 at 20'. 9. Control Link Zoning: Zone 1 =Softball Field, Zone 2=Security Lights, Zone 3 =GFCI, Zone 4: Practice Soccer (PI/P2), Zone 5=Sparc, Zone 6=Spare. Alternate#1 Provide (6)new SCG 1500w Light Fixtures to be mounted on existing pole- P I Alternate#2 Provide(1) new 60' pole with (6) LSG 1500w Light Fixtures, and foundation. muSo. Musco Subcontractor Responsibilities: 1. Provide equipment and materials to off load equipment at jobsite per scheduled delivery. 2. Provide storage containers for material as necessary. 3. Provide adequate trash container for cardboard waste and packing debris. 4. Provide adequate security to protect Musco delivered products from theft, vandalism or damage during the installation. 5. Obtain and pay for required permits. 6. Provide equipment and materials to remove, and dispose of(2)existing security light poles. The foundation of security light pole at the Bl location will be removed. 7. Provide electrical design as required. Also provide any as-built drawings as required following the completion of the project. 8. Provide materials and equipment to install or upgrade existing electrical service panels as required or necessary. This needs to be defined in the electrical design. 9. Provide materials and equipment to install all underground conduit, wiring, pull boxes, switchgear, etc. and terminate wiring as required per electrical design. This will included conduit and wiring to Musco Light Poles- Al, A2, B I, 132 and C2. Provide sufficient conduit size at pole B I to accommodate pulling the necessary lighting circuit from a future left outfield pole (Future CI) with connection to the Musco Control Link System. 10. Make appropriate contact to ensure utility locates have been done prior to excavation and trenching. Repair any such damage to existing utilities during construction. I 1. Provide materials and equipment to install (5)Light Structure System foundations as specified on Layout- Al, A2, B1, B2, and C2. 12. Connect grounding per requirements 13. Remove augured spoils to off-site location. 14. Provide materials and equipment to assemble and install Light Structure GreenTM fixtures and terminate all necessary wiring. 15. Provide equipment and materials to assemble and erect(5) Light Structure System Poles. 16. Verify aiming points have been located and are correct before sighting in lighting cross-arms. 17. Provide equipment and materials to install the new Controls and Monitoring Cabinet and terminate all necessary wiring. Installation of Musco supplied surge protection required. Subcontractor to commission Control Link once system is energized. 18. Provide(2) Security Lights 19. Install conduit, and wiring for(2) Security Light assemblies mounted on poles Al, and B I. Connect to Musco Control Link. 20. Install conduit, and wiring for(2) GFCI assemblies mounted on poles Al, and Al Connect to Musco Control Link. 21. Keep all heavy equipment off of playing fields and surfaces when possible using due care to minimize damages. 22. Provide startup and aiming as required to provide complete and operating sports lighting system. 23. Provide payment of prevailing wages and certified payroll as required. 0000 mus witty ALTERNATE#1: I. Provide equipment and materials to install (6) SCG 1500w light fixtures on existing P I. and connect to Musco Control Link. ALTERNATE#2: I. Provide equipment and materials to assemble and erect (I) new 60' Pole (P2) with (6)LSG 1500w Light Fixtures on existing P1, and connect to Musco Control Link. Provide materials and equipment to install all underground conduit, wiring, pull boxes and terminate wiring as required per electrical design. Eno, rn , Light Structure GreenTM Turnkey Scope of Work Garvey Park- Phase II Duff Field Rosemead, CA Project#165103 Revision- January 30, 2015 Owner Responsibilities: I. Total access to the site and pole locations for construction. Must be able to move from location to location on standard rubber tires. 2. Removal of any trees, limbs, shrubs, etc. for total access to pole locations. 3. Removal,replacement, and repair of all fencing necessary for construction. 4. Repair and replacement of any field turf, asphalt, curbs, and concrete damage. Review with city. 5. Locate and mark existing irrigation systems prior to excavation as necessary. 6. Provide on-site area for excavated drilling spoils. 7. Additional mobilization cost if needed for electrical connections to cell tower pole lighting equipment. Musco Responsibilities: I. Provide required (5)poles, (20) fixtures, (5) foundations, and associated designs. 2. Provide structural design for poles and foundations, certified by a professional engineer licensed in the State as required. Structural Design to be based off Class 5, Standard Soil,CBC-2013 110mph. 3. Provide layout of pole locations and aiming diagram. 4. Provide light test upon owner supplied electrical system. 5. Provide Project Management assistance as needed. 6. Provide review of electrical design as provided by Electrical Contractor or Electrical Engineer. 7. Provide (2) GFCI Lockable Assemblies to be installed at 10' on poles Al. A2. 8. Provide mounting accommodations for a security light fixture to be installed on pole Al and A2 at 20'. 9. Control Link Zoning: Zone 1 = Softball Field, Zone 2= Security Lights, Zone 3 =GFCI, Zone 4: Practice Soccer(PI/P2), Zone 5 = Spare, Zone 6=Spare. Alternate#1 Provide(6) new SCG 1500w Light Fixtures to be mounted on existing pole- PI Alternate#2 Provide(1) new 60' pole with (6) LSG 1500w Light Fixtures, and foundation. 0000 Ulf iffir Musco Subcontractor Responsibilities: I. Provide equipment and materials to off load equipment at jobsite per scheduled delivery. 2. Provide storage containers for material as necessary. 3. Provide adequate trash container for cardboard waste and packing debris. 4. Provide adequate security to protect Musco delivered products from theft, vandalism or damage during the installation. 5. Obtain and pay for required permits. 6. Provide equipment and materials to remove, and dispose of(2)existing security light poles. The foundation of security light pole at the B I location will be removed. 7. Provide electrical design as required. Also provide any as-built drawings as required following the completion of the project. 8. Provide materials and equipment to install or upgrade existing electrical service panels as required or necessary. This needs to be defined in the electrical design. 9. Provide materials and equipment to install all underground conduit, wiring, pull boxes, switchgear, etc. and terminate wiring as required per electrical design. This will included conduit and wiring to Musco Light Poles-Al, A2, B I, B2 and C2. Provide sufficient conduit size at pole B to accommodate pulling the necessary lighting circuit from a future left outfield pole(Future Cl) with connection to the Musco Control Link System. 10. Make appropriate contact to ensure utility locates have been done prior to excavation and trenching. Repair any such damage to existing utilities during construction. I1. Provide materials and equipment to install (5) Light Structure System foundations as specified on Layout-A I, A2, B1, B2, and C2. 12. Connect grounding per requirements 13. Remove augured spoils to off-site location. 14. Provide materials and equipment to assemble and install Light Structure Green TM fixtures and terminate all necessary wiring. 15. Provide equipment and materials to assemble and erect (5) Light Structure System Poles. 16. Verify aiming points have been located and are correct before sighting in lighting cross-arms. 17. Provide equipment and materials to install the new Controls and Monitoring Cabinet and terminate all necessary wiring. Installation of Musco supplied surge protection required. Subcontractor to commission Control Link once system is energized. IS. Provide (2) Security Lights 19. Install conduit, and wiring for(2)Security Light assemblies mounted on poles Al, and Bl. Connect to Musco Control Link. 20. Install conduit, and wiring for(2) GFCI assemblies mounted on poles Al, and A2. Connect to Musco Control Link. 21. Keep all heavy equipment off of playing fields and surfaces when possible using due care to minimize damages. 22. Provide startup and aiming as required to provide complete and operating sports lighting system. 23. Provide payment of prevailing wages and certified payroll as required. • m rye i�� r [4. ALTERNATE#1: I. Provide equipment and materials to install (6) SCG 1500w light fixtures on existing P1. and connect to Musco Control Link. ALTERNATE#2: 1. Provide equipment and materials to assemble and erect (1) new 60' Pole(P2) with(6) LSG 1500w Light Fixtures on existing PI, and connect to Musco Control Link. Provide materials and equipment to install all underground conduit, wiring, pull boxes and terminate wiring as required per electrical design. •••• Quote Garvey Park- Duff Field Lighting Project Rosemead,California Date:January 30, 2015 To: David Montgomery Scott The City of Rosemead Quotation Price-Duff Field Lighting Project-Turnkey Musco's Light Structure Green" as described below,and the Duff Field Scope of work document: > Duff Field Softball Poles/Fixtures(Al,A2,Bl,B2,C2): $166,400.00 Estimated Sales Tax at 9%: $14,976.00 Total Project Cost: $181,376.00 Pricing furnished is effective for 90 days unless otherwise noted and is considered confidential. Equipment Description-Duff Field Softball Lighting Project Light Structure Green"'System delivered to your site in Five Easy Pieces" • (5)Pre-cast concrete bases with integrated grounding • (5)Galvanized steel poles-Al,A2,Bl,82,C2 • UL Listed remote electrical component enclosures with pole length wire harnesses • (20)Factory-aimed and assembled luminaires[stadium]-1500 watt metal halide • Musco Constant 25'"product assurance and warranty program that eliminates 100%of your maintenance costs for 25 years,including labor and materials • Energy savings of more than 50%over a standard lighting system • 50%less spill and glare light than Musco's prior industry leading technology • Guaranteed lighting 50/30 on Softball Field for 25 years • Two(2)group re-lamps at the end of the lamps'rated life,5000 hours;based on SOD annual usage hours for the Softball Field. • Control Linkw Control&Monitoring System for Flexible control and solid management of your lighting system • (2)GFCI assemhlies mounted in the hand hole of poles Al/A2 Lighting Control: Garvey Park-(1)24"x 72"Control Cabinet. Six lighting zones: Duff Field Softball,Soccer Practice,Security Lights.GFCI,Spare I,and Spare 2. *Connect 120v to Musco Controller Project Pole Attachment In formation: Duff Field Softball Security Lighting Fixture Brackets: (2x) 1p Tenon Mount Bracket at 20'on poles Al/81-rear facing. ©2009,2010 Musco Sports Lighting, LLC 40•410 Quote k Quotation Price—Additive Alternate#1-Replace Six existing non-Musco Light Fixtures with Six new Musco SCG Fixtures(1500w) Musco's Light Structure Green' as described below and per Duff Field scope of work: • Additive Alternate#1-Six new Musco SCG Fixtures to be installed on P1 822,000.00 Estimated Sales Tax at 9%: $1,980.00 Add Alt#1 Total Cost: 823,980.00 Pricing furnished is effective for 90 days unless otherwise noted and is considered confidential. Equipment Description-Additive Alternate#1-Provide and install Six new SCG Fixtures(1500w) Light Structure Green"System delivered to your site in Five Fasy Pieces" • (6)Factory aimed and assembled pole top luminaire assemblies • UL Listed remote electrical component enclosures • Mounting hardware for the pole top units and electrical component enclosures • Pole length wire harness,with Disconnects • Musco Constant 25-product assurance and warrunty program that eliminates 100%of your maintenance costs for 25 years,including labor and materials • Two(2)group re-lamps at the end of the lamps'rated life,5000 hours, Based on 500 annual usage hours for the practice soccer area. Quotation Price—Additive Alternate#2-Provide and install Practice Soccer Pole(P2)with Six new Musco LSG Fixtures(1500w) Musco's Light Structure Green"'as described below and per Additive Alternate#1 scope of work document: • Additive Alternate#2-New Practice Soccer Pole P2 and six new Musco LSG Fixtures: 834,500.00 Estimated Sales Tax at 9%: 83,105.00 Add Alt#1 Total Cost: 837,605.00 Pricing furnished is effective for 90 days unless otherwise noted and is considered confidential. Equipment Description-Additive Alternate#2-Provide and install Practice Soccer Pole(P2)with Six new Masco LSG Fixtures (1500w) Light Structure Green"System delivered to your site in Five Easy Pieces" • (1)Pre-cast concrete bases with integrated grounding • (1)Galvanized steel poles-PI • UL Listed remote electrical component enclosures with pole length wire harnesses • (6)Factory-aimed and assembled luminaires[stadium]-1500 watt metal halide • Musco Constant 25"product assurance and warranty program that eliminates 100%of your maintenance costs for 25 years,including labor and materials • 'two(2)group re-lamps at the end of the lamps'rated life,5000 hours. Based on 500 annual usage hours for the practice soccer area. ®2009,2010 Musco Sports Lighting,LLG 9 •000 Quote . era, • Notes Quote is based on: • Shipment of entire project together to one location • Structural code and wind speed=2013 CBC,110 MPH Exposure C. • Confirmation of pole locations prior to production • Revise Musco Design#165103A;Dated January 29,2015 Payment Terms • Payment of 25%of the contract price is required with order.The contract balance is due within 30 days. • Late payment will be subject to service charges of 1 Y%per month(18%APR). Thank you for considering Musco for your sports-lighting needs.Please contact me with any questions. Mike Higgins Project Manager Musco Sports Lighting,LLC 4 Jenner.Suite 100 Irvine,CA 92618 Phone: 800-659-0117 x6121 E-mail: mike.higgins @musco.com Fax: 949-754-0637 ©2009,2010 Musco Sports Lighting,LLC 3 R Q ce • E dE my - p r . _ _ E d > i Z S E ° z v 9 C p ? Y V D • H Q t C E c £ F F F E G = k E - E O V 41 w '^ 6a " n _ Ea Yp E y E _ n 13 -e & uS _ - EpiE F3 - > 3 i Co. o i C E i ° 9 y a C E c q In K 3 P z F J ° '^ - C s= “ 2 H U' p' u .1. mLJ V _ b w ° _ - c _ zm N O i • N. n n - n `ai ("i tear tear tear n n r N- CD C) c CO N !- n tear f tear n tear n N- O N- N L() CO Q CO C) V n n Cl- CI- tear tear tear tear (Nr;z -I m V N- O) C) CO 0) p N 0 1*F n n n �ar tear tear tear n- 0 n a s °°° n n �i N i far i a i n- EE- i CO n N i CO 0 04 F n °"i °i i a N CO '4 n CO n F F Tv Es iFar 31113.1 CO N C) )O I4 N CO 0) 0 V 0) N. tear S c2 tear `2 4 S 4 S , • . . . n n 0 01 cl- tear w. `4 a4 '4 4 i €■_Ib bb er' r' s M 0 O tear tear 0 V 0 0 CO O) CO V n tear n S 4 4 S g 9 j r n noj n n n n tear m I".«, Cr, z ill 0 x < w m w . I# p . rN ) \ is ! } - 2 � / \ \ k • « ! b ; / { / d - 2 « y = , . s , z � , a , . . - - $� . , ya « es , a9la £ s g : . . e . \ 2 E «: 2 \ % . _ , . , . 1 Eel . . !! • . . = ; : , t . : . , . , <,, , 1 : : : , ; , I : , == . , . _ � - w 96 R G Q 8 dr / � » / « 3 - \ \ ' ) / ^ \ < \ \ \\ \ } /\ L \ \. 2 J0 0 CV N co [ii:ii4 ° » i '6 74 i & & k i § ; § } . a & N ; } § \ & § & k ; ; % ,' i # « ~ ® ®ƒ * k 7 & q ,LI \« § _w w z \ !! ¥ ` }_{ \ . {\ k • ` _ _ \ - § ¢ . , , ! ; , . . « , . 2z , , . < • a . a g y : 2 \ ! z p; . e „ aa , . o , o . . . ,, _ e � c J /9 ` a . cl9 8I , z > » e u 1 \ ` - :: _ , : - - � \ - ag 4 2s So _ ~^ \ E5 g LL\ *cal \ , y \ > #5 \a r'73 ,+ 22 : /H $ m ©/ | . . . . | H La Li } \ . \. .. � ° .m . - : } \ - -I St - \\ : ®D w / \\ \e • ° \ <. • - , : , : C : R . ; = g ; : s -, , a g . g 3 z • q_ } . : 0 ©cc Fg _ \\ \ -S� � � / /}CI \\.10 at 4. 0 6 (-----fre on ;l 2? ~ +~ {i\\ :+ �+ .. . . § // I ~` \ t \ \ \ \ 0-• / z F \j )\ W. i ? »C 2 ! § !,F} ) ) ){ 3 {} } ` 2 •! i - � . . / y ■ptt . - . : | C ) • S � 2 . . \ § o • - k :_ . . ° _ - e x - < { !Ec\ . /) \ \ / ' \\ \\ . \ } / � \ CI 61 \ 32 `{ In\ ,, . n \\ t \t 23-2- ; `I z : � ` 0 ° ~: \ , § . W RESOLUTION NO. 2015-10 A RESOLUTION OF THE ROSEMEAD, CALIFORNIA CITY COUNCIL AMENDING APPROPRIATING ADDITIONAL FUNDS FROM THE CITY'S STREET LIGHTING DISTRICT FUND FOR THE GARVEY PARK DUFF FIELD IMPROVEMENTS PROJECT — REPLACEMENT OF SPORTS LIGHTING WHEREAS, appropriations are the legal authority for a City to spend its funds; and WHEREAS, from time to time it is necessary to amend the budget with additional appropriations; and WHEREAS,the City desires to improve the sports field lighting at Duff Field and the multipurpose field at Garvey Park; and WHEREAS, the lighting replacement project is funded through proceeds from the Street Lighting District Fund and currently has a budget amount of$175,000.00; and WHEREAS, the total cost for the lighting components of this project, as proposed, will not exceed $267,461.00, which is $92,500.00 more than currently budgeted; and WHEREAS, the Street Lighting District Fund has a balance of approximately $1,400,000.00 of which the additional funding could be made available for this project. NOW THEREFORE, $92,500.00 is appropriated in the Capital Improvement Programs for Expenditures related to the Garvey Park Duff Field Renovation Project as defined below: Fund Organization Account Project Description Amount Appropriation 301 6005 5395 41016 Construction $ 92,500.00 Transfer (Memo) 245 0000 5960 Transfer Out <$ 92,500.00> 301 0000 4860 Transfer In $ 92,500.00 The additional appropriation is made a part of the approved FY 2014-15 budget as though it were a part of the initial budget fully set forth. PASSED, APPROVED and ADOPTED this 10th day of February 2015. William Alarcon, Mayor ATTEST: Gloria Molleda, City Clerk