SUMMARY
As a part of the City's Fiscal Year 2014-15 Capital Improvement Program, the City
Council approved the "Garvey Park Duff Field Renovations" Project which includes the
installation of new lighting, fencing, turf and miscellaneous site improvements to the
west ball field at Garvey Park. The project consists of the addition of new sports lighting,
replacement of the existing chain link fence and backstop, and improvements to the
landscape, irrigation, and adjacent concrete sidewalk. The work at this facility will take
place in three phases based on the distinct scopes of work and the specialties of the
contractors required to complete the work. Work will begin, at this time, with the
installation of new sports lighting, the fence replacement, and site work.
Staff Recommendation
It is recommended that the City Council:
1. Approve the plans and specifications for the Garvey Park Duff Field Renovations
Project.
2. Authorize the City Manager to enter into a contact with AZ Construction, Inc. in
the amount of $79,361 for the Garvey Park Duff Field Renovations Project and
authorize a contingency amount of $11,900 (approximately 15%) to cover the
cost of any unforeseen construction expenses.
DISCUSSION
The Garvey Park Duff Field Renovations project was included in the Fiscal Year 2014-
15 Capital Improvement Program with funding from the General Fund and the Lighting
Fund totaling $325,000.00. The scope of work includes a comprehensive upgrade to the
facility including lighting replacement, fencing, site work and amenity upgrades, and
substantial landscape and irrigation improvements. This phase of the project includes
replacement of the existing chain link fence, concrete, and various site amenities.
The existing chain link fence will be replaced with new chain link fencing. The height of
the backstop fence will be increased to twenty feet and include an overhang to LW-
ITEM NUMBER. 11
City Council Meeting
February 10, 2015
Page 2 of 3
baseballs and softballs within the playing area. The backstop, perimeter fencing, and
gates will also be replaced. A four feet tall homerun fence will be added in the outfield at
a distance of 200 feet from home plate. The existing dugouts will be removed and
reconstructed behind the new fence, out of the field of play, and will include new
benches. The concrete sidewalk in the spectator area will be replaced and furnished
with new aluminum bleachers.
A Notice Inviting Bids was published in local newspapers and trade publications on
January 22nd and January 29th, 2015. Sealed bids were received in the Office of the City
Clerk until 10:30 a.m. on Wednesday, February 4, 2015. At 11:00 a.m. on February 4,
2015, the City Clerk publicly opened and read six (6) sealed bids with the following
result:
Rank Bidder Location Bid Amount
1 AZ Construction, Inc. La Puente, CA $ 79,361.00
2 CEM Construction Corp. Downey, CA $ 85,120.00
3 E.C. Construction South El Monte, CA $ 85,358.30
4 Concept Consultant, Inc. Los Angeles, CA $ 105,540.00
5 CABD Construction Glendale, CA $ 123,290.00
6 RASA Construction, Inc. Chino, CA $ 133,955.00
Staff has reviewed the bid documents for completeness and finds the bid of AZ
Construction, Inc., to be the lowest responsive bid. Staff has reviewed the contractor's
background and recent projects for competency. AZ Construction, Inc. has successfully
completed similar projects for multiple public agencies including the Cities of Los
Angeles, Pasadena, and Santa Clarita.
FINANCIAL REVIEW
The Garvey Park Duff Field Renovations Project is included in the FY 2014-15 Capital
Improvement Program. The project has a budget of $325,000.00 from the General Fund
and Lighting Fund. The total appropriation needed to award this contract tonight is
approximately $91,261.00.
ENVIRONMENTAL REVIEW
This project is categorically exempt from the California Environmental Quality Act
(CEQA) pursuant to Section 15301 (C) of the CEQA Implementing Guidelines.
PUBLIC NOTICE PROCESS
This item has been noticed through the regular agenda notification process.
City Council Meeting
February 10, 2015
Page 3 of 3
Prepared By: Prepared By:
c
/ Rafael M. Fajardo, P.E. Sean Sullivan
City Engineer Acting Public Works Manager
Submitted By:
/
Matt H wkesrw h
Assistant City Manager/Acting Director of Public Works
Attachments:
A. Plans and Specifications (Available in the City Clerk's Office)
B. Bid Analysis for the Garvey Park Duff Field Improvements Project
PUBLIC WORKS SERVICE DEPARTMENT/ENGINEERING DIVISION Y4,2015
CITY OF ROSEMEAD
DUFF PARK IMPROVEMENTS PROJECT
PROJECT NUMBER: 41016
BID ANALYSIS
BID SUBMITTAL:FEBRUARY 4.2015
AZ CONSTRUCTION INC, #1
BASE BID PRICE
I- I
ITEM DESCRIPTION OTT UNIT UNIT PRICE TOTAL
1 CLEARING AND GRUBBING PER PLANS/SPECS. _ 1.00 LS 2.900 00 $ 2.900 00
2 DISPOSAL OF WASTE MATERIALS 1.00 LS 50000 $ 50000
3 REMOVE.DISPOSE,CONSTRUCT 4"PCC SIDEWALK 1225.00 SF 1100 $ 13,47500
REMOVE,DISPOSE,CONSTRUCT 2P HIGH CHAIN LINK FENCE 9 GAUGE
AND 2"MESH.WITH TOP RAIL AND BOTTOM TENSION WIRE,
4 INCLUDING POLES&BASEBALL BACKSTOP COMPLETE 130.00 LF _ 15900 $ 20,670 00
REMOVE,DISPOCE,CONSTRUCTS'HIGH CHAIN LINK FENCE 9 GAUGE
AND 2"MESH WITH TOP RAIL AND BOTTOM TENSION WIRE INCLUDING
5 POLES COMPLETE 434.00 LF 39.00 E 16 926 00
CONSTRUCT 4'HIGH HOMERUN FENCE 9 GAUGE 2"MESH WITH TOP
6 RAIL AND BOTTOM TENSION WIRE INCLUDING POLES COMPLETE 380.00 LF 1800 $ 6,84000
7 CONSTRUCT DUGOUT COMPLETE(30'X 10') 2.00 EA 2250.00 $ 4.50000
8 FURNISH AND INSTALL 3 ROW ALUMINUM BLEACHERS-CAPACITY 15 2.00 EA 1300.00 $ 2,600.00
FURNISH AND INSTALL DUGOUT BENCHES ELITE BENCH PER
9 BASEBALL RACK OR APPROVED EQUAL 4.00 EA 1,50000 $ 6,000.00
_ 10 INSTALL 4'WIDE GATE AS INDICATED ON PLANS 3.00 EA 65000 $ 1,950.00
11 INSTALL 20'WIDE GATE AS INDICATED ON PLANS 2.00 EA 1.50000 $ 3000.00
TOTAL BASE BID PRICE $ 79,361.00
CEM CONSTRUCTION #2
BASE BID PRICE
ITEM DESCRIPTION OTY UNIT UNIT PRICE TOTAL
1 CLEARING AND GRUBBING PER PLANS/SPECS. 1.00 LS 5.000 00 5 500000
2 DISPOSAL OF WASTE MATERIALS 100 LS 1.000 00 $ 100000
3 - REMOVE,DISPOSE,CONSTRUCT 4"PCC SIDEWALK 1225.00 SF 6.00 $ 7,350.00
REMOVE.DISPOSE.CONSTRUCT 20 HIGH CHAIN LINK FENCE 9 GAUGE
AND 2"MESH,WITH TOP RAIL AND BOTTOM TENSION WIRE,
4 INCLUDING POLES&BASEBALL BACKSTOP COMPLETE 130.00 LF 28000 $ 36400.00
REMOVE.DISPOCE.CONSTRUCT 6'HIGH CHAIN LINK FENCE 9 GAUGE
AND 2"MESH WITH TOP RAIL AND BOTTOM TENSION WIRE INCLUDING
5 POLES COMPLETE 434.00 LF 3000 $ 13,020.00
CONSTRUCT 4'HIGH HOMERUN FENCE 9 GAUGE 2"MESH WITH TOP
6 RAIL AND BOTTOM TENSION WIRE INCLUDING POLES COMPLETE 380.00 LF 25.00 $ 9.500.00
7 CONSTRUCT DUGOUT COMPLETE(30'X 10') 2.00 EA 1,B00.00 $ 3,60000
8 FURNISH AND INSTALL 3 ROW ALUMINUM BLEACHERS-CAPACITY IS 2.00 EA 1,500 00. $ 3,00000
FURNISH AND INSTALL DUGOUT BENCHES ELITE BENCH PER
9 BASEBALL RACK OR APPROVED EQUAL 4.00 EA 1,000.00 $ 4,00000
GATE 10 INSTALL 2'WIDE GATE AS INDICATED ON PLANS N 3.00 EA 600.00 $ 1,050 00
11 INSTALL 20'WIDE GATE AS INDICATED ON PLANS 2.00 EA 600.00 $ 1,200 00
TOTAL BASE BID PRICE S. 85,120.00
PAGE
PUBLIC WORKS SERVICE DEPARTMENT/ENGINEERING DIVISION Z'42015
E.O.CONSTRUCTION #3
BASE BID PRICE
..L, I I . ..
ITEM DESCRIPTION CITY UNIT UNIT PRICE TOTAL
2 CLEARING AND GRUBBING PER SLANS/SPECS. 1.00 LS t,000.00 $ 1.000 00
2 DISPOSAL OF WASTE 5.00 LS 511.54 $ 13050
3 REMOVE DISPOOSE,.CONSTRUCT CONSTRUCT 2"
HG SIDEWALK
1,225.00 ,. SF 115•. 5 14,13650
REMOVE DISPOSE CONSTRUCT 20 HIGH CHAIN LINK FENCE 9 GAUGE
AND 2' MESH WITH TOP RAIL AND BOTTOM TENSION WI RE
4 DING POLES&BASEBALL B KS CCOMPLETE 130.00 LF 128.20 $ 16,666.00
REMOVE,DIH TH CONSTRUCT LINK FENCE 9 GAUGE
AND 2"MESH WITH TOP RAIL AND BOTT OM TENSION WIRE INCLUDING
5 POLES
COMPLETE 434.00 LF 5150 $ 22351 00
CONSTRUCT 4 HIGH HOMERUN FENCE 9 GAUGE 2'MESH WITH TOP
6 RAIL AND BOTTOM TENSION WIRE INCLUDING POLES COMPLETE 380.00 LF 2546 $ 9,674.80
7 CONSTRUCT DUGOUT COMPLETE 130'X 10) 2.00 EA 3505.00 $ 7010.00
8 FURNISH AND INSTALL 3 ROW ALUMINUM BLEACHERS-CAPACITY IS 2.00 EA 145000 $ 290000
FURNISH AND INSTALL DUGOUT BENCHES ELITE BENCH PER
9 BASEBALL RACK OR APPROVED EQUAL 4.00 EA 1,150.00 $ 4600.00
10 INSTALL 4'WIDE GATE AS INDICATED ON PLANS 3.00 EA 51500 $ 154500
11 'INSTALL 20 WIDE GATE AS INDICATED ON PLANS 2.00 EA 248].50 $ 49]5 00
TOTAL BASE BID PRICE $ 88,358.30
CONCEPT CONSULTANT,INC. #4
BASE BID PRICE
1 _- 9 I
ITEM_!DESCRIPTION OTY UNIT UNIT PRICE TOTAL
1 CLEARING AND GRUBBING PER PLANS/SPECS. 1 00_ LS 3.80000 $ 3,800.00
2 DISPOSAL OF WASTE 1.00 LS 2,014.00 $ 7,150.00
3 REMEMOVE,DISPOOSE,,CONSTRUCT CONSTRUCT
20PGSIDEWALK
1,225.00 SF 1400 $ P,150.00
REMOVE DISPOSE CONSTRUCT 20'HIGH CHAIN LI NK FENCE 9 GAUGE
AND 2 S P WITH TOP RAIL AND BOTTOM TENSION WI RE
• INCLUDING POLES B BASEBALL BACKSTOP COMPLETE 13000 LF 22].00 $ 2951000
REMOVE DISPOCE CONSTRUCT 8'OH CHAIN LINK FENCE 9 GAUGE
AND 2"MESH W ITH TOP RAIL AND BOTT OM TENSION W IRE INCLUDING
5 POLES
COMPLETE 43400 LF 45.00 $ 1953000
CONSTRUCT 4'HIGH HOMERUN FENCE 9 GAUGE 2"MESH WITH TOP
6 RAIL AND BOTTOM TENSION WIRE INCLUDING POLES COMPLETE 380.00 LF 40.00 S 1520000
7 CONSTRUCT DUGOUT COMPLETE(30'X 10) 2.00 EA 2600.00 $ 5.200 00
8 FURNISH AND INSTALL 3 ROW ALUMINUM BLEACHERS-CAPACITY 15 2.00 EA 225000 S 4 500 00
FURNISH AND INSTALL DUGOUT BENCHES ELITE BENCH PER
9 BASEBALL RACK OR APPROVED EQUAL 4.00 EA 70000 $ 2,80000
10 INSTALL 4'WIDE GATE AS INDICATED ON PLANS 3.00 EA 65000 5 195000
11 INSTALL 2P WIDE GATE AS INDICATED ON PLANS 2.00 EA 1950.00 $ 3.90000
TOTAL BASE BID PRICE $ 105,540.00
PAGE 2
PUBLIC WORKS SERVICE DEPARTMENT/ENGINEERING DIVISION 2/4/2015
CABO CONSTRUCTION #5
BASE BID PRICE
t. .
ITEM DESCRIPTION OTY UNIT UNIT PRICE TOTAL
1 CLEARING AND GRUBBING PER PLANS/SPECS. 1.00 LS 10,000.00 $ 10,000.00
2 DISPOSAL OF WASTE MATERIALS 100 LS 12000.00 $ 12,00000
3 REMOVE,DISPOSE.CONSTRUCT 4"PCC SIDEWALK 1225.00 SF 1000 $ 1225000
REMOVE,DISPOSE.CONSTRUCT 20 HIGH CHAIN LINK FENCE 9 GAUGE
AND 2"MESH,WITH TOP RAIL AND BOTTOM TENSION WIRE.
4 INCLUDING POLES&BASEBALL BACKSTOP COMPLETE 130.00 LF 20000 $ 26,000 00
REMOVE, E CONSTRUCT 8'HIGH CHAIN LINK FENCE 9 GAUGE
AND 2"MESH SH WITH TOP RAIL AND BOTTOM TENSION WIRE INCLUDING
5 POLES COMPLETE 434.00 LF 6000 $ 26040.00
CONSTRUCT 4'HIGH N FENCE 9 GAUGE 2"MESH WITH TOP
6 RAIL AND BOTTOM TENSION WIRE INCLUDING POLES COMPLETE 380 00 LF 2500 $ 9,50000
7 CONSTRUCT DUGOUT COMPLETE(30'X 10) 2.00 EA 5.000.00 $ 10,000.00
6 FURNISH AND INSTALL 3 ROW ALUMINUM BLEACHERS-CAPACITY 15 2.00 EA 1,50000 $ 300000
FURNISH AND INSTALL DUGOUT BENCHES ELITE BENCH PER
9 BASEBALL RACK OR APPROVED EQUAL 4.00 EA 1000.00 $ 4000.00
10 INSTALL 20'WIDE GATAAI INDICATE ON PLANS 300 EA 1000.00 $ 400000
11 INSTALL 20'WIDE GATE AS INDICATED ON PLANS 2.00 EA 3,000.00 $ 6,000.00
TOTAL BASE BID PRICE $ 123,290.00
RASA CONSTRUCTION,INC. 09
BASE BID PRICE
UI - 1 1 . .
ITEM DESCRIPTION QTY UNIT UNIT 5 PRICE 00 0 TOTAL
400
2 CLEARING L OFOASTE MATERIALS RIASLANS/SPECS. 1.00 LS 42.50000 $ 4550000
2 DISPOSAL IS WASTE 5.00 LS 2,50000 $ 250500
] REMOVE.DISPOSE,CONSTRUCT 20PIGHC SIDEWALK I 1,225.00 SF Z00 S 69500
REMOVE M.DISPOSE WITH CONSTRUCT RAIL 20'BOTTOM CHAIN N LINK FENCE 9 GAUGE
AND U"INCLUDING P.WITH TOP RAIL AND BOTTOM COMPLETE WIRE,
4 REMOVE DPOLE38BANSTRUCBACKSTOP 8 HIGH AIN LNKF 130.00 LF 175 00 S 22]50-00
REMOVE M.SIH WITH CONSTRUCT AND 8'HIGH CHAIN LINK WIRE INCLUDING
GAUGE
AND 2"MESH WITH TOP RAIL ANO BOTTOM TENSION WIRE INCLUDING
5 POLES COMPLETE 434.00 LF 4500 S 19530.00
CONSTRUCT 4'HIGH HOMERUN FENCE 9 GAUGE 2"MESH WITH TOP
6 RAIL AND BOTTOM TENSION WIRE INCLUDING POLES COMPLETE 380.00 LF 2000 3 ]600.00
0 0 _
7 CONSTRUCT DUGOUT COMPLETE(30'X 10) 2.00 EA 400000 $ 8 p00.00
B FURNISH AND INSTALL 3 ROW ALUMINUM BLEACHERS-CAPACITY 15 2.00 EA 350000 $ ]000.00
FURNISH AND INSTALL DUGOUT BENCHES ELITE BENCH PER
9 BASEBALL RACK OR APPROVED EQUAL 4.00 EA 150000 $ 600000
10 INSTALL 4'WIDE GATE AS INDICATED ON PLANS 3.00 EA 100000 $ 3000.00
11 INSTALL 20'WIDE GATE AS INDICATED ON PLANS 2.00 EA 2,00000 $ 4,000.00
TOTAL BASE BID PRICE $ 131,965.00