CC - Item 2D - Montebello Boulevard/Towne Center Drive Resurfacing Median and Landscape Enhancements Project - Award of ContractROSEMEAD CITY COUNCIL
STAFF REPORT
TO: THE HONORABLE MAYOR AND CITY COUNCIL
FROM: JEFF ALLRED, CITY MANAGER
DATE: FEBRUARY 24, 2015
SUBJECT: MONTEBELLO BOULEVARD /TOWNE CENTER DRIVE RESURFACING
MEDIAN AND LANDSCAPE ENHANCEMENTS PROJECT —
AWARD OF CONTRACT
SUMMARY
As a part of the City's Fiscal Year 2014 -15 Capital Improvement Program, the City
Council approved the "Montebello Boulevard/Towne Center Drive Resurfacing, Median
and Landscape Enhancements" Project. This project includes the grinding of existing
pavement and the reconstruction of the roadway with new asphalt concrete, the
replacement of damaged sidewalk, and extensive improvements, including the addition
of landscaping, to the medians along Montebello Boulevard, Towne Center Drive, and
San Gabriel Boulevard. This project is funded through Measure R and Prop C funds.
The City received five (5) bids and the lowest bid received was from Tobo Construction
of Los Angeles, CA. Through staff's investigation of the contractor's background it was
concluded that no evidence was provided to demonstrate that this contractor has the
experience necessary to complete the major street reconstruction as required in this
project. It is staff's recommendation that the City Council reject the bid of Tobo
Construction and award the contract to the second lowest bidder, Sully - Miller
Contracting Co.
Staff Recommendation
It is recommended that the City Council:
1. Approve the plans and specifications for the Montebello Boulevard/Towne Center
Drive Resurfacing, Median and Landscape Enhancements Project, and
2. Reject the bid of Tobo Construction, Inc as nonresponsive as the contractor
cannot provide the necessary references for experience in this type of work, and
3. Authorize the City Manager to enter into a contract with Sully - Miller Contracting
Co. in the amount of $624,686.20. In addition, authorize an amount of $62,000
(approximately 10 %) as a contingency to cover the cost of unforeseen
construction expenses.
ITEM NUMBER:
City Council Meeting
February 24, 2015
Page 2 of 4
4. Approve Resolution No. 2015 -13 appropriating $86,700 in additional Measure R
Funds to complete this project
DISCUSSION
The Montebello Boulevard/Towne Center Drive Resurfacing, Median and Landscape
Enhancements project was included in the Fiscal Year 2014 -15 Capital Improvement
Program with funding through Measure R and Prop C funds. The scope of work for this
project includes the grinding of existing pavement and the reconstruction of the roadway
with new asphalt concrete along Montebello Boulevard from the City Limit to Towne
Center Drive and along Towne Center Drive from Montebello Boulevard to San Gabriel
Boulevard. Additional work includes the reconstruction of damaged sidewalk, curb and
gutter, striping improvements, and extensive improvements to the medians. The
medians along Montebello Boulevard, Towne Center Drive, and San Gabriel Boulevard
will be modified by removing the substantial asphalt in the medians and replacing it with
landscaping and river rock, consistent with other medians throughout the city.
Montebello Boulevard and Towne Center Drive are busy arterials that provide access to
the SR -60 freeway, Montebello Towne Center Mall, and several hotels and businesses
in the southern portion of the City. According to the City's Pavement Management
Program, which was updated in 2013, these segments of roadway have Pavement
Conditions Index (PCI) scores of between 21 and 30, which classify the conditions of
these roadways as "Very Poor ". For comparison, the citywide average PCI score is 75.
A Notice Inviting Bids was published in local newspapers and trade publications on
January 22 and January 29 2015. Sealed bids were received in the Office of the City
Clerk until 10:30 a.m. on Wednesday, February 4, 2015. At 11:00 a.m. on February 4,
2015, the City Clerk publicly opened and read five (5) sealed bids with the following
result:
Rank
Bidder
Location
Bid Amount
1
Tobo Construction, Inc.
Los Angeles, CA
$ 591,354.00
2
Sully - Miller Contracting Co.
Brea, CA
$ 624,686.20
3
KASA Construction, Inc.
Chino, CA
$ 708,473.00
4
C.S. Legacy Construction, Inc.
Pomona, CA
$ 816,769.73
5
E.C. Construction
South El Monte, CA
$ 875,391.36
Staff has reviewed the bid documents for completeness and has reviewed the
contractors' backgrounds and recent projects for competency. Staff finds the bid of
Tobo Construction to be nonresponsive as they do not demonstrate experience in road
resurfacing projects. Tobo Construction, Inc. presented a list of projects completed for a
number of public agencies; however, the projects are building projects. These projects
may include a paving component, such as a parking lot or minor road repair from
construction activities; however, none of the projects involve major road reconstruction.
Due to the volume of traffic on these streets and the proximity to SR -60 and busy
City Council Meeting
February 24, 2015
Page 3 of 4
commercial areas, staff believes that Tobo Construction does not have the experience
needed to manage a project of this magnitude. Staff recommends the award of contract
to the second lowest bidder; Sully - Miller Contracting Co. Sully - Miller Contracting Co. is
a well- regarded general engineering contractor that has completed major road
reconstruction projects for many public agencies in Southern California. Sully - Miller has
worked on City of Rosemead Projects before, completing the Walnut Grove Avenue and
Rush Street Resurfacing Project in 2011 and they are currently constructing the Safe
Routes to School Project on Walnut Grove Avenue.
FINANCIAL REVIEW
The Montebello Boulevard/Towne Center Drive Resurfacing, Median and Landscape
Enhancements Project is included in the FY 2014 -15 Capital Improvement Program.
The project has a budget of $600,000 from Measure R and Prop C Funds, Measure R
and Prop C funds are local return funds from Los Angeles County Sales Tax for
transportation projects. The total appropriation needed to award this contract tonight is
approximately $686,700.00. Staff is requesting an additional appropriation of $86,700
from the Measure R fund to complete the construction of this project.
ENVIRONMENTAL REVIEW
This project is categorically exempt from the California Environmental Quality Act
(CEQA) pursuant to Section 15301 (C) of the CEQA Implementing Guidelines.
PUBLIC NOTICE PROCESS
This item has been noticed through the regular agenda notification process.
Prepared By:
Rafael M. Fajardo, P.E.
City Engineer
Prepared By:
Sean Sullivan
Acting Public Works Manager
Submitted By:
Matt Hawked orth
Assistant City Manager /Acting Director of Public Works
City Council Meeting
February 24, 2015
Page 4 of 4
Attachments:
A. Plans and Specifications (Available in the City Clerk's Office)
B. Bid Analysis
C. Bid of Tobo Construction, Inc.
D. Bid of Sully - Miller Contracting Co.
E. Resolution No. 2015 -13
PUBLIC WORKS SERVICE DEPARTMENT/ENGINEERING DIVISION
CITY OF ROSEMEAD
MONTEBELLO BLVDITOWNE CENTER DRIVE RESURFACING PROJECT MEDIAN AND LANDSCAPE IMPROVEMENTS
PROJECT NUMBER: 21018
BID ANALYSIS
BID SUBMITTAL: FEBRUARY4.2015
TOBO CONSTRUCTION
BASE BID PRICE
#1
ITE
DESCRIPTION
CITY
UNIT
UNIT PRICE
TOTAL
1
CLEARING AND GRUBBING PER PLANS /SPECS.
1.00
LS
16,000.00
$ 16,000.00
2
_._.
DISPOSAL OF WASTE MATERIALS
1.00
LS
10 500.00
0.40
$ 10 500.
$ 65,744.00
3
4
COLD MILL 2 EXISTING PAVEMENT
164,360.00
SF
CONSTRUCT L5 "THICK PAVEMENT OVERLAY ARHM -GG -C
CONST 1.0" ASPHALTIC LEVELING COURSE DI
1,545.00
TONS
50.00
$ 77,250.00
5
6
1,030.00
4,800.00
TONS
82.00
$ 84,460.00
REMOVE 6" EXISTING PAVEMENT REPLACE W/ 4" AC B -PG 64 -10 BASE
OVER COMPACTED NATIVE
SF
10.00
$ 48,000.00
7
REMOVE, DISPOSE, CONSTRUCT 4 PCC SIDEWALK
R EMOVE, DISPOSE, CONSTRUCT 8" CURB 124" GUTTER
3,524.00
SF
10.00
$ 35,240.00
$ 30,450.00
e
� 145.00
135.00
LF
LF
210.00
160.00
9
10
OSE, CONSTR
RE MOVE DISPUCT 8 "CURB ONL
$ 21,600.00
REMOVE, DISPOSE, CONSTRUCT PCC C RAMPS
DOUBLEACJUSTSEWER MANHOLE TO GRADE
10.00
! EA
3,200.00
$ 32,000.0
11
5.00
EA
EA
1,050.00
1,150.00
$ 5,250.00
$ 4,600.00
12
13
ADJUST WATER VALVE /GAS VALVE TO GRADE
4.00
INSTALL LANDSCAPE PER PLANS AND SPECIFICATIONS COMPLETE
1.00
LS
37,000.00
52,000.00
$ 37,000.00
$ 52,000.00
14
INSTALL IRRIGATION PER PLAN AND SPECIFICATI COMPLETE
1.00
LS
15
INSTALL SURVEY WELL MONUMENT
3.00
EA
1,100.00
$ 3,300.00
16
INSTALL STRIPING, SIGNAL LOOPS, AND PAVEMENT MAR KERS
1.00
4,89 6.00
LS
SF
19,000.00
$ 19,000.00
17
REMOVE EXISTING AND INSTALL 50 150 MIX OF YOSEMITE AND ARIZONA
COBBLE RIVER ROCK 6" DIAM MIN. TO 12" DIAM MAX. AS INDICATED ON
PLANS AND SPECIFICATIONS COMPLETE
10.00
$ 48,960.00
4,896.00
SF
15.00
$ 73,440.00
TOTAL BASE BID PRICE
TOTAL BASE BID PRICE
$ 591,354.00
SULLY - MILLER CONTRACTING CO.
BASE BID PRICE
#2
ITEM
DESCRIPTION �
QTY
UNIT
UNIT PRICE
M y TOTAL
1
CLEARING AND GRUBBING PER PLAN /SPECS.
1.00
LS
25,000.00
$ 25,000.00
2
DISPOSAL OF WASTE MATERIALS
1.00
LS
20,000.00
$ 20,000.00
3
4
COLD MILL EXISTING PAVEMENT
164,360.00
1545.00
SF
TONS
027
85.00
$ 44,377.20
$ 131,325.00
CONSTRUCT 1.5 "THICK PAVEMENT OVERLAY ARHM -GG -C
_
5
CONSTRUCT 1.0" ASPHALTIC LEVELIN COURSE D1
1,030.00
TONS
75.00
$ 77,250.00
6
REMOVE 6" EXISTING PAVEMENT REPLACE W/ 4" AC B -PG 64 -10 BASE
OVER COMPACTED NATIVE
4,800.00
SF
5.25
$ 25,200.00
7
RE MOVE, DISPOSE, CONSTRUCT 4" PCC SIDEWALK
3,524.00
SF
7.25
$ 25,549.00
e
REMOVE, DISPOSE, CONSTRUCT B " CURB /24 "GU TTER
___.
145.00
___
LF
- _
35.00
$ 5,075.00
9
REMOVE, DISPOSE, CONSTR 8 CURB ONLY
135.00
LF
32.00
$ 4,320.00
1 0
11
REMOVE, DISPOSE, CONSTRUCT PCC CURB RAMPS
10.00
....
5.00
EA
EA
_. 2,000.00
690.00
$ 20,000.00
._.. . _.
$ 4,450.00
DOUBLE ADJUST SEWER MANHOLE TO GRAD
12
ADJUST WATER VALVE / GAS V ALVE TO GRADE
4.00
EA
375.00
$ 1,500.00
13
INSTALL LANDSCAPE PER PLANS AND SPECIFICATIONS COMPLETE
1.00
1.00
LS
LS
68,000.00
$ 68,000.00
14
INSTALL IRRIGATION PER PLANS AND SPECIFICATIONS COMPLETE
INSTALL S URVEY WELL MONUMENT
73,000.00
$ 73,000.00
15
16
3.00
EA
LS
400.00
25,000.00
$ 1,200.00
$.... 25,000.00
INSTALL STRIPING, SIGNAL LOOPS, AND PAVEMENT MARKERS
1.00
17
REMOVE EXISTING AND INSTALL 50/50 MIX OF YOSEMITE AND ARIZONA
COBBLE RIVER ROCK 6" DIAM MIN. TO 12" DIAM MAX. AS INDICATED ON
PLANS AND SPECIFICATIONS COMPLETE
4,896.00
SF
15.00
$ 73,440.00
TOTAL BASE BID PRICE
$ 624,686.20
2/1912015
PAGE
PUBLIC WORKS SERVICE DEPARTMENT/ENGINEERING DIVISION
KASA CONSTRUCTION, INC.
BASE BID PRICE
#3
C.S. LEGACY CONSTRUCTION
BASE BID PRICE
#4
ITEM
DE SCRIPTION
QTY
UNIT
UNIT PRICE
59,000.00
TOTAL
1
_ _
CLEARING AN GRUBBING PER PLANS /SPECS.
1.00
LS
$ 59,000.00
2
DISPOSA OF WASTE MATERIAL
1.00
LS
6200001$
620000
3 _
4
_
COLD MILL 2" EXISTIN PAVEMENT
164,360.00
SF
0.20
100.00
$ 32,872.00
CONSTRUCT 1.5 "THICK PAVEMENT OVERLAY AR HM_GG C
1,545.00
1,030.00
TONS
TONS
$ 154,500.00
5
CON STRUCT 1.0" ASPHALTIC LEVELING COURSE D1
90.00
$ 92,700.00
__._.
6
REMOVE 6" EXISTING PAVEMENT REPLACE W/ 4" AC B -PG 64 -10 BASE
OVE COMPACTED NATIVE
4,800.00
SF
3.501
I
$ 16,800.00
7
_
REMOVE, DISP OSE, CONSTRUCT 4" PCC SIDEWALK
3,524.00
SF
LF
6 00
$ 21,144.00
8
REMOV DISPOSE, CONSTRUCT 8" CURB / 24" GUTTER
145.00
34.001
$ 4,930.00
9
REM OVE DISPOSE, CONSTRUCT 8" CURB ONLY
135.00
LF
25.00
$ 3,375.00
10
REMOVE, DISPO CONSTRUCT PCC CURB RAMPS
10.00
EA
EA
...._. 2,500.00
1,000.00
$ 25,000.00
11
DOUBLE ADJUST SEWER MANHOL TO GRA
_ 5.00
4.00
$ 500000
12
ADJUST WATER VAL / GAS VALVE TO GRADE
EA
400.00
$ 1,600.00
13
IN STALL LANDSCAPE PER PLANS AND SPECIFICATIONS COMPLETE
1.00
LS
110,000.00
$ 110,000.00
14
INSTA IRRIGATION PER PLANS AND SPECIFI COMPLETE
1.00
LS
85,000.00
$ 85,000.00
15
INS TALL SURVEY WELL MO
3.00
EA
1,200.00
$ 3,600.00
16
INSTALL STRIPING, SIGNA LOOPS, AND PAVEMEN MARKERS
1.00
LS
28,00i50
$ 28,000.00
17
REMOVE EXISTINGAND INSTALL 50/50 MIX OF YOSEMITE AND ARIZONA
COBBLE RIVER ROCK 6" DIAM MIN. TO 12" DIAM MAX. AS INDICATED ON
PLANS AND SPECIF ICATIONS COMPLETE
4,896.00
SF
12.00
$ 58,752.00
LS
22,098.00
$ 22,098.00
17
i
4,896.00
SF
TOTAL BASE BID PRICE
$ 91,702.08
_
$ 708,473.00
C.S. LEGACY CONSTRUCTION
BASE BID PRICE
#4
2/192015
PAGE 2
ITEM
JDES CRIPTION
QT_Y
-
UNIT
UNIT PRICE
TOTAL
1
CLEARING AND GRUBBING P PLANS /SPECS.
_
1.00
LS
20,217.00
$ 20,217.00
2
:DISP LASO OF WA MATERIALS
1.00
LS
6,579.00
$ 6,579.00
3
_
COLD MILL 2" EXISTING PAVEMENT
164,360.00
SF
__
---
030
$ 49,308.00
$
q
I.S "THICK PAVEMEN OVERLAY ARHM -GG -C
__._
1,545.00
TONS
112.00
$ 173,040.00
_ CONSTRUCT
5
CONSTRUCT 1.0" ASPH ALTIC LEVELING COURSE D1
1,030.00
TONS
105.00
$_ 108,15
6
REMOVE 6 EXISTING PAVEMENT REPLACE W/4 AC B PG 64 -10 BASE
OVER COMPACTED NATIVE
4,800.00
SF
5.39
$ 25,872.00
7
REMOVE, DISPOSE, CONSTRUC 4' PCC SIDEWALK
_ 3,524.00
SF
9.80
$ 34,535_.20
_
8
REMOVE, DIS POSE, CONSTRI T8" CURB /24" GUTTER
145.00
LF
46.40
$ 6,728.00
9
_
R EMOVE DISPOSE, CONSTRU 8" CURB ONLY
135.00
LF_
4367
$ 5,895.45
10
REMOVE, DISPOSE, CONSTR PCC CURB RAMPS
_ _ 10.00
EA
3745.00
$ 37,450.00
11
DOUB LEADJUST SEWER MANHOLE TO GRADE
5.00
EA
2,618
$ 130 9000
12
ADJU WATER VALVE / GAS VALVE T GRADE
4.00
EA
1,089A0
$ 4,356.00
13
INSTALL LANDSCAPE PER PLANS AND SPECIFICATIONS C OMPLETE
1.00
LS
109,139.00
$ 109,139.00
14
IN STALL IRRIGATION PER PLAN AND SPE CIFICATIONS COMPLETE
1.00
LS
103,95tOOI
$ 103,951.00
_
15
INSTALL SURVEY WELL MONUMENT
3.00
EA
1,553.001
$ 4,659.00
16
INSTALL STRIPING, SIGNAL LOOPS, AND PAVEMENT MARK
1.00
LS
22,098.00
$ 22,098.00
17
REMOVE EXISTING AND INSTALL 50/50 MIX OF YOSEMITE AND ARIZONA
COBBLE RIVER ROCK 6" DIAM MIN. TO 12" DIAM MAX. AS INDICATED ON
PLA AND SPECIFICATIONS COMPLET
4,896.00
SF
18.73
$ 91,702.08
_
TOTAL BASE BID PRICE
$ 816,769.73
2/192015
PAGE 2
PUBLIC WORKS SERVICE DEPARTMENT/ENGINEERING DIVISION
E.C. CONSTRUCTION
BASE BID PRICE
#6
ITEM
DES CRIPTION
UNIT
UNIT PRICE
K
TOTAL
1
CLEARING AND GRUBBING PER PLANS /SPECS.
--QTY
1.00
LS
15,000.00
$ 15,000.00
2
DISPOSAL OF WAS MATERIALS
1.00
LS
6,500.00
$ 6,500.00
_
3
COLD MILL 2" EXISTING PAVEMENT
164,360.00
1,545.00 0
__- SF
0.23
T 37,810.00
4
CO NSTRUCT 1.5 "THICK PAVE OVERLAY ARHM -GG -C
TONS
97.08
$ _ 149,985.00
5
CONSTRUCT 1.0" ASPHALTIC LEVELING COURSE DI
1,030.00
TONS
77.28
$ 79,594.00
_
6
REMOVE 6 EXISTING PAVEMENT REPLACE W/ 4 AC B -PG 64 -10 BASE
OVE COMPACTED NATIVE
4,800.00
SF
4.01
$ 19,248.00
7
e
REMOVE, DISPOSE, CONSTRUCT 4" PCC SIDEWALK
REMOVE, DISPOSE, CONSTRUCT 8" CURB / 24" GUTTER
.
3,524.00
SF
6.00
$ 21,144.00
$ 14,500.00
145.00
LF
100.00
9
REMOVE DISPOSE, CONSTRUCT 8" CURB ONLY
135.00
LF
EA
50.00
3,000.001
$ 6,750.00
10
REMOV DISPOSE, CONSTRUCT P CC CURB RAMPS
10.00
$ 30,000.00
11
DOUBLE ADJUST SEWER MANHOL TO GRADE
5.00
EA
1,340.00
$ 6,700.00
12
ADJUST WATER VALVE / GA VALVE TO GRADE
4.00
EA
75.00
145 247.00
$ 300.00
13
14
(INS TALL LANDSCAPE PER PLA AND SPECIFICATIONS COMPLET
1.00
1.00
_.. 3.00
LS
$ _ _ 145,247.00
$ 231,116.00
INST IRRIGATION PER PLANS AND SPECIFI COMPLETE
LS
231,116.00
15
JINSTALL SURVEY WELL MONUMENT
EA
750.00
$ 2,250.00
16
INSTALL STRIPING SIGNAL LOOPS AND PA VEMENT MARKERS
1.00
LS
SF
( _ 21,560.00
$ 21,560.00
17
REMOVE EXISTING AND INSTALL 50/50 MIX OF YOSEMITE AND ARIZONA
COBBLE RIVER ROCK 6" DIAM MIN. TO 12" DIAM MAX. AS INDICATED ON
PLA AND SPECIFICATIONS COMPLET
4,896.00
17.91
$ 87,687.36
TOTALBASEBID PRICE
$ 875,391.36
3
COLD MILL 2" E XISTING PAVEMENT
164,360.00
SF
0.401
$ 65,744.00
4
CON STRUCT 1.5 "THICK PAVEME OVE RLAY ARHM -GG -C
1,54500
TONS
50.00
$ 77,250.00
5
CONSTRUCT 1.0" ASPHALTIC LE VELING COURSE D1
1,030.00
TONS
82.00
$ 84,46
6
_
REMOVE 6" EXISTING PAVEMENT REPLACE W /4" AC B -PG 64 -10 BASE
OVER COMPACTED NATIVE
4,800.00
SF
10.00
$ 48,000.00
13
INSTALL LANDSCAPE PER PLANS A SPECIFICATIONS COMP LETE
1.00
LS
37,000.00
$ 37 000.00
14
IN STALL IRRIGATION PER PLANS AND SPE COMPLETE
i 1 .00
LS
52,000.00
$ 52,000.00
16
INS TALL STRIPING, SIGNAL LO OPS AND PAVEMENT MARKERS
1 00
LS
19,000.00
$ 19,000.00
_
TOTAL BASE BID PRICE
$ 383,464.00
2/19/2015
PAGE 3
BIDDER: �LbE O & Dt(
BID SCHEDULE
SCHEDULE OF PRICES FOR
MONTEBELLO BLVD. / TOWNE CENTER DRIVE RESURFACING
MEDIAN AND LANDSCAPE ENHANCEMENTS
PROJECT No. 21806
BASE BID SCHEDULE
GBF -1
UNIT OF
EST.
UNIT
ITEM
NO.
ITEM DESCRIPTION
MEASURE
QTY.
PRICE
COST
1
Clearing & Grubbing per plans
LS
1
and specificatiohs. See technical
provisions TP -2, TP -3 & TP-4,
t C c
C' o
2
Disposal of Waste Materials.
LS
1
i C'
0 ' C
I c, C7
3
Cold mill 2.0- inches thick existing
SF
164,360
pavement
4
Construct 1.5 inches thick
TONS
1,545
pavement overlay ARHM -GG -C
(PG 64 -16) as indicated on the
7 2 o
plans,
5
Construct 1,0 ihches thick
TONS
1,030
Asphaltic Leveling course D1
(PG 64 -10) as indicated on the
T
plans.
6
Remove 6- 1nches of existing
SF
4,800
pavement and replace it with fl-
inches of AC B -PG 64 -10 Base
i ii'rri
N•,
0 i?
Course over compacted native,
7
Remove, Dispose and Construct
SF
3,524
4- Inches thick PCC Sidewalk per
SPPWC Std, Plan 113 -1.
9
S 2, j o
8
Remove, Dispose and Construct
LF
145
8- inches Curb and 24- inches
Gutter per SPPWC Std, Plan
120 -2.
9
Remove, Dispose and Construct
LF
135
8- 11 PCC Curb Only per
SPPWC Std, Plan 120 -2.
10
Remove, Dispose and Construct
EA,
10
PCC Curb Ramps per SPPWC
Std, Plan 111 -4,
GBF -1
BIDDER: ToL,L� l 1�f 37 c1 :. t( vf�4
NO.
ITEM DESCRIPTION
UNIT OF
MEASURE
EST,
QTY.
UNIT
PRICE
ITEM
COST
11
Double Adjust Sewer Manhole to
EA
5
Grade per APWA Std. Plan 205-
1 and 206 -1.
12
Adjust Water Valve /Gas Valve to
EA
4
Grade.
13
Install Landscape per Plans and
LS
1
Specifications Complete as
Indicated on Sheet No. 3 to 7,
i Uri € =
3� co
14
Install Irrigation per Plans and
LS
1
Specifications Complete as
indicated on Sheet.No, 8 to 11,
2-G o
15
Install Survey Well Monument
EA
3
per City of Rosemead Std, plan
508.001. See Section 2 -9
Surveying of the General
Provislon -7 perdetalis (Cover,
Sleeve & Dome will be provided
by the City at no cost).
16
Install Traffic Striping, Traffic
LS
1
Signal Loops and Pavement
Markers per the Striping Plans
I q ur o
(: j C C'D
and Specifications Complete.
17
Remove Existing and Install
SF
4,896
50150 Mix of Yosemite and
Arizona Cobble River Rock 6"
Die. Min. to 12" pia. Max as
1 0
4 b i 6 C
Indicated on Plans and
Specifications Complete,
TOTAL BASE BID PRICE (SCHEDULE BID PRICE):$ 5q1351 ' o ()
hi� LK'30( J�1 kl
Dollar amount in written form
Note: The City of Rosemead reserves the right to reduce or increase the quantities of any items in
the schedule of bid items above, within the limits define in Section 3- 2.,2,1 of the Standard
Specifications, to stay within the budgeted amount of this project.
If the Bid Documents specify alternate bid items, the following Alternate Bid amounts shall
be added to or deducted from the Total Bid Price entered above. The owner can choose to
include one or more of the alternates in the Total Bid Price of the Project. If any of the
Alternate Bids are utilized by the Owner, the resulting amount shall be considered the Total
Bid Price for the Project.
VO LLA �S'
CBF -2
BIDDER: 4
CONTRACT BID FORMS
TABLE OF CONTENTS
SECTION 1
BID SCHEDULE__ ...........................
SECTION 2
BID DATA FORMS ..... ...............................
2.A
BID BOND. .....................
2.B
LIST OF PROPOSED SUBCONTRACTORS...
SECTION 3
NON - COLLUSION AFFIDAVIT .........................
............................ 5
............................ 6
............................ 7
....... . ...... .... .... ............. ... 10
CBF -12
BIDDER:
SECTION 1 - BID SCHEDULE
CBF -0
BIDDER: T, of Om �Cch 7�j c,
The undersigned agrees that these Contract Bid Forms constitute a firm offer to the Owner which
cannot be withdrawn forthe number of Working Days indicated in the Notice Inviting Bids from and
afterthe bid opening date, or until a Contract forthe Work is fully executed by the Owner and a third
party, whichever is earlier. The undersigned also agrees that If there is a discrepancy between the
written amount of the Bid Price and the numerical amount of the Bid Price, the written amount shall
govern.
Attached hereto is a certified check, a cashier's check or a �id bo d 'in the amount of
X! Dollars ($ 5 i t 3 rrt said amount being not less than ten percent (10 %) of the Total
id Price. The undersigned agrees that said amount shall be retained by the Owner if, upon award,
we fail or refuse to execute the Contract and furnish the required bonds, certificates and
endorsements of insurance and other certifications within the time provided.
If awarded a Contract, the undersigned agrees to execute the formal Contract, which will be
prepared by the Owner for execution, within five (5) Calendar Days following the Letter of Award for
the Contract, and will deliver to the Ownerwithin that same period the necessary original Certificates
of Insurance, Endorsements of Insurance, Performance Bond, Payment Bond and all other
documentation and certification required by the Contract.
The undersigned offers and agrees that if this bid is accepted, it will assign to the purchasing body
all rights, title, and interest in and to all causes of action it may have under Section 4 of the Clayton
Act (15 U.S.C, Section 15) or under the Cartwright Act (Chapter 2 of Part 2 of Division 7 of the
Business and Professional Code), arising from purchases of goods, materials or services by the
Bidder for sale to the purchasing body pursuant to the bid. Such assignment shall be made and
become effective at the time the purchasing body tenders final payment to he Contractor.
Bidder understands and agrees that, when requested by Owner, he shall provide: (1) evidence
satisfactory to the Owner of Bidder's California contractor's license(s) in good standing; (2) evidence
that the person signing this Bid is authorized to bind Bidder to this Bid and to a contract resulting
therefrom; and (3) any other information and documentation, financial or otherwise, needed by
Owner to award a Contract to the lowest responsible and responsive bidder.
The undersigned acknowledges receipt, understanding and full consideration of the following
addenda to the Contract Documents.
Ks Addenda Nos,
The Bidder understands and agrees that the Total Bid Price is inclusive of all labor, materials, and
equipment or supplies necessary to complete the Work as described in the Bid Documents. If this
bid is accepted, the undersigned Bidder agrees to enter into and execute the Contract with the
necessary bonds and accept the Total Bid Price as compensation in full for all Work under the
contract.
CBF -3
Bidder acknowledges that. data submitted with its Contract Bid Forms which it requires to be
incorporated into a Contract arising out of this Submittal has been so identified by Bidder. Bidder
further acknowledges that the Owner may, at its discretion, incorporate any of the remaining data
submitted herewith into a contract arising out of this Bid.
By:
Signature
Mi, d)
Type or Print Name
Title
BIDDER: T C)6 0 a V
Business Street Olddress
City, State and Zip Code
4t�- 1 6u
Telephone Number
Bidder'slContractoes State of Incorporation: C'>'fj .
Partners or Joint Venturers:
Bidder's License Number(s):
q 5 Pv 12-
Department of Industrial Relations
Registered No.
NOTES:
9)
2)
3)
u0 Q o U � 3k.
By its signature on this Bid, the Bidder certifies under penalty of perjury the accuracy of the
representations made on the Contract Bid Forms.
If Bidder is a corporation, enter State of Incorporation in addition to Business Address
If Bidder is a partnership or joint venture, give full names of all partners or joint
venturers.
As further discussed in the Instructions to Bidders, Bidder will be required
to provide evidence that the person signing on behalf of the corporation,
Partnership or .joint venture has the authoritv to do so.
CIS
BIDDER: �4 �7C Its (N J
SECTION 2
BID DATA FORMS
CBF -5
BIDDER: Tobo Construction, Inc.
Bidder shall submit its Bid data in accordance with the format shown on each of the following Bid
Data Forms. Bidders shall prepare and use as many sheets as are necessary to adequately provide
the information required. Bidder shall ensure that every page of its Bid Data Forms are properly
identified with the Bidder's name and page number.
2.A BID BOND
KNOW ALL MEN BY THESE PRESENTS:
THAT Tobo Construction, Inc.
Principal, and Internationa
as
, as Surety, are held firmly bound unto the
CITY OF ROSEMEAD (hereinafter called the OWNER) in the sum of
ten percent of total attached bid amount
($ 10% of bid ) , being not less than ten percent (10 %) of the Total
Bid Price; far the payment of which sum will and truly to be made, we bind ourselves,
our heirs, executors, administrators, successors, and assigns, jointly and severally,
firmly by these presents.
WHEREAS, said Principal has submitted a bid to the OWNER to perform all Work
required for the Montebello Blvd./Towne Center Drive Resurfacing Median and
Landscape Enhancement Project as set forth in the Notice Inviting Bids and
accompanying Bid Documents, dated 02/04/15
NOW, THEREFORE, if said Principal is awarded a Contract for the Work by the
OWNER and, within the time and in the manner required by the above- referenced
Bid Documents, enters into the written form of Contract bound with said Bid
Documents, furnishes the required bonds (one to guarantee faithful performance
and the other to guarantee payment for labor and materials) furnishes the required
insurance certificates and endorsements, and furnishes any other certifications as
may be required by the Contract, then this obligation shall be null and void; otherwise
it shall remain in full force and effect. In the event suit is brought upon this bond by
the OWNER and judgment is recovered, said Surety shall pay all costs incurred by
'the OWNER in such suit, including reasonable attorneys' fees to be fixed by the
court.
SIGNED ANDS ALED, this 28th day of January 2015
Tobo Construc' n, In . (SEAL)Interna Fidelity Insurance Company (SEAL)
Principal Surety
By: N By:
Signat re Signature tephanie ng, Attjrnny -in -Fact
1
f
CALIFORNIA ALL- PURPOSE ACKNOWLEDGMENT CIVIL CODE 1189
A notary public or other offtcor completing this certificate verifies only the identity of the individual who signed the
document to which this certificate is attached and not the truthfulness, accuracy, or validity of that document.
State of California )
County of Orange )
On i I �? 1 1 5 before me, Barbara Copeland Notary Public,
personally appeared Stephanie Hoang
Name(s) of Signer(s)
who proved to me on the basis of satisfactory evidence to be the person(a) whose name(s) is /are subscribed to the
within iustnunent and acknowledged to me that ire /she /they executed the same in his/her /their authorized
capacity(ics), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of
which the person(s) acted, executed the instrument,
I certify render PENALTY OF PERJURY under the
BARBARA GOP LAND laws of the State of California that the foregoing
Commission # 2018 348 paragraph is true and correct,
-, Notary public • California a
0 n9 Cbunty n
My Gomm. Expires A r 19.2017 WITNESS my hand and official seal
Place Notary Seat Above
Signature: Y 1 �' 1 'L >� -
Signature OM, taryPablio
OPTIONAL ------------------------------ ----------- ° -------
Though the information below is not required by law, it may prove valuable to persons relying on the document
and could present fraudulent and reattachment of this form to another document.
Description of Attached Document
Type or Title of Document:
Document Date:
Number of Pages:
Signer(s) Other Than Named
Capacity(ies) Claimed by Signer(s)
Signer's Name: Stephanie Hoang
❑ Individual
❑ Corporate Officer -- Titic(s):___
❑ Partner: ❑Limited ❑ General
® Attorney in Fact
❑ Trustee
❑ Guardian or Conservator
❑ Other:
Signer Is Representing:
Capacity(ies) Claimed by Signer(s)
Signer's Name:
❑ Individual
❑ Corporate Officer — Title(s):
❑ Partner: ❑Limited ❑ General
❑ Attorney in Fact
❑ Trustee
❑ Guardian or Conservator
❑ Other:
Signer Is Representing:
Rev. 1 - -15
ACKNOWLEDGMENT
"A Notary Public or other officer completing this certificate verifies only the identity of the individual who
signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of
that document,"
State of California
County of j Los Angeles
On 1/29/2015 before me, Suzie H Na, Notary Public
(Insert name and title of the officer)
personally appeared Jimi Chae
who proved to me on the basis of satisfactory evidence to be the person whose name is
subscribed to the within instrument and acknowledged to me that he executed the same in
his authorized capacity, and that by his signature on the instrument the
person, or the entity upon behalf of which the person acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of Californa that the foregoing
paragraph is true and correct.
WITNESS my hand and official seal.
w
SUZIE H. NA
COMM. # 2022906 M
NOTARY PUBLIC• CALIFORNIA C
(.� LOS ANGELES COUNTY
� Comm. Exp. MAY 2, 2017
(Seal)
BIDDER: Ty,)()�b17C��1 ` /
2.13 LIST OF PROPOSED SUBCONTRACTORS
In compliance with the "Subletting and Subcontracting Fair Practices Act," Sections 4100
through 4114 of the California Public Contract Code, and any amendments thereto, each
Bidder shall provide the information requested below for each subcontractor who will
perform work, labor or render service to Bidder in or about the construction of the Work in an
amount in excess of one -half of one percent (greater than 0.5 %) of the Bidder's Total Bid
Price, or, in the case of bids or offers for the construction of streets or highways, including
bridges, in excess of one -half of 1 percent of the Contractor's total bid or ten thousand
dollars ($10,000), whichever is greater, and shall further set forth the portion of the Work
which will be done by each subcontractor. Bidder shall list only one subcontractor for any
one portion of the Work.
Pursuant to Public Contract Code Section 4104, the Owner has determined that it will allow
Bidders twenty -four (24) additional hours after the deadline for submission of bids to submit
the information requested by the Owner about each subcontractor, otherthan the name and
location of each subcontractor.
If the Bidder fails to specify a subcontractor for any portion of the Work to be performed
under the Contract, it shall be deemed to have agreed to perform such portion itself, and
shall not be permitted to subcontract that portion of the Work except under the conditions
hereinafter set forth below,
Subletting or subcontracting of any portion of the Work in excess of one half of one percent
(greaterthan 0.5 %) of the Total Bid Price or, in the case of bids or offers for the construction
of streets or highways, including bridges, in excess of one -half of 1 percent of the
Contractor's total bid or ten thousand dollars ($10,000), whichever is greater, for which no
subcontractor was designated in the original bid shall only be permitted in cases of public
emergency or necessity, and then only after Owner approval.
CBF -7
BIDDER: 6b
2.13 ' LIST OF PROPOSED SUBCONTRACTORS (continued)
["Duplicate Next 2 Pages if needed for listing additional subcontractors l
Name and Location Description of Work - pAvepjt -- T sJ� Af -Kitt f
of Subcontractor / to be Subcontracted €L w k f [
License No.: _ 3 - 14400
Department of IndustrioI kelation Registration No. i v o ijo (o o
to 'A - z, m f, y
Name and Location Description of Work ,w p EM ,0
of Subcontractor to be Subcontracted [ N!4
Name: Pkile0eli PAC, t (F.th1f 5 Y`Z! € tt;
Address: to2.4f3 �Aij 5 I /Aiije wAy `, f A V>A,t,( -� CA 9f "7 >a
License No.: .5 i s `'t 2 7 S
Department of Industrial Relation Registration No.
fvi>r >cru��3
Name and Location Description of Work [ , €
of Subcontractor to be Subcontracted i nt € ir�t
Name: uWTe.v t t�rr 7St f n �T i f , 4nt
Address: rtufe (tAt,eoA PWp Q�tn , cA 'Ti�z>
License No.: b � 2E o =r a
Department of Industrial Relation Registration No
Name and Location Description of Work - PfNi' a� gACpt
of Subcontractor to be Subcontracted
Name: .J f, S S ?d.i 'fto11,
Address: i54d rtmv Ave, tao - r ALp_(`} LA `f t ? 1
License No.: rs =. =h 2.1
Department of Industrial Relation Registration No. 2
t C3 fY
Name and Location Description of Work
of Subcontractor to be Subcontracted
Name:
Address: , S? r ° ! r� _ A Pte, UcAtP,4 6A -
License No.: r
Department of Indus rd I Relation Registration No
BIDDER: I
2.0 REFERENCES
The following are the names, addresses and telephone numbers for three public agencies for which BIDDER
has performed similar work within the past two (2) years:
Name *d Address of Owner
X31 2-°
Name and telephone Kmber of person familiar with project
Contract amount TvnP of Wnrlr r)� +e P 1-4-
2.
Name and telephone numbe
Contract L am p ount
{�F404`
Name and Address of Owner
4.
person familiar with project
Ty e Wo k
rJ
number of person familiar with
Type
CBF -9
Type of Work Date Completed
Owner
Project Description
Owner Contact
Contact Phone
Total Contract
Amount
UCLA
Tenant Improvement
John D'Amico
310 -683 -1030
$355,000
UCLA
Renovation of Music Center
John D'Amico
310 - 6691030
$16,548,513
City of Santa Clarita
Construction of Transit Center
James Tong
661.510 -2312
$3,635,245
City of Simi Valley
Addition to Simi Valley City Hall
Brian Gabler
B06- 683 -6701
$3;326,326
HACLA
Pipeline Replacement
Darrell Robinson
213- 252 - 4273
$1,650,025
Housing Authority City of Los Angeeles
Ti of Housing Authority Headquarters
Tina Booth
213- 252 -6844
$15,644,764
City of Santa Giants
Construction of Now Library
Rachel Glass
661 -255 -4929
$12,750,000
County of Los Angeles, Department of
Public Works
Job Order Contract
Bill Swindle
562 -869 -1176
$4,200,000
Los Angeles World Airports.
Construction of New Firestation
Robert Falcon
424- 848 -8848
$9,268,996
LACCD
Construction of Outdoor Restroom and bleachers
David Gonzalez
626 - 763.702E
$1,714,530
County of Los Angeles
Dept. of Public Works
Addition of 2 now classrooms and a office building
Marie GiVenz
(826) 39O -3ZZ4
Rio Hondo College
Construction of classroom bldg
Teresa Dreyfuss
(662) 463 -7099
F$1.769,3a4
County of Los Angeles -CDC
Elevator Modernization
Jose Rases
323 - 260 =3464
City of Los Angeles, Departmebt of
Recreation and Parks
Now Construction of Parking Lot and Basketball
Court
Gary Lam
(213) 473.9710
$389,000
County of LOS Angeles -CDC
Improvements 2, Renovations of Senior Center
Verna Lee
323.890. 7001
$3 07,995
County of Los Angeles -CDC
Exterior Improvements
Verna Lee
323 - 890 -7001
$18,000
Too sn�� f1tTw
LACCD
New Construction of animal science center and
Clap Mykhaylov
818 - 610.6563
$3,067,189
equestrian exhibition center
County of Los Angeles, Department of
New Tenant Improvement Construction of 29,000 of
Te-Ung Chou
626 - 300 -3206
$2,579,989
Public Works
City of Los Angeles, Department Of
Renovation of Gym
Gary Lam
(213) 473.9710
$689,926
Recreation and Parks
City of Los Angeles, Department of
New construction of a City operated recreation
Cathie Santo Doming
9
(213) 473 - 5895
$2,379,000
Recreation and Parks
center
City of Les Angeles, Department of
Now construction of a sports activity center
p y
i t
Cathie Santo Domingo
213 )
( 473 -5895
$2
Recreation and Parks
County of Los Angeles, Department of
Weld Shop Improvement
Zaire Khayat
(626) 300.3220
$28,693
Public Works
County of Los Angeles, Department of
Interbasin conduit repair
Youssef Chebabi
(626) 458 -6154
$00,058
Public Works
City of Los Angeles, Department of
Construction of new, restmom facility
Cathie Santo Domingo
(213) 473 -5895
$748,000
Recreation and Parks
County of Los Angeles, Department of
Additional work
Sam Shodab, PM
(626) 306 -2337
$63,675
Public Works
County of Los Angeles, Department of
A/C Work
Cung Nguyen, PM
(626) 458 -2552
$$1,674
Public Works
County of Lcs.Ahgales, Department of
Youssef Chebabi
(626)A5 &0154
$18,723
PublICWorks
City of Los Angeles, Department of
Demolition of roof & installing steel structure with
Cathie Santo Domingo
(21 3) 202 -2668
$6,762;024
Recreation and Parks
skylight systems
County of Los Angeles, [),apartment of
Tower Plugs
Michels Chlmlentl
(626) 458 -6111
$10,488
Public Works
County of Los Angeles, Department of
Headworks repair
Youssef Chebabi
(626) 458 -6184
$68,240
Public Works
Countyo €Los Angeles, Department of
Penstock Repair
Michele Chimienli
(626) 458 -6111
$167,136
Public Works
County of Los Angeles, Department of
Recant the inside of the penstocks
Michele Chimienli
(626) 458-6111
$167,136
Public Works
County of Los Angeles, Department of
Access road repair
Belinda Kwon
(626) A68 -6135
$555,674
Publlo Works
SIDDER: llX , 0
SECTION 3
NON - COLLUSION AFFIDAVIT
CBF -10
BIDDER: oil
NON - COLLUSION AFFIDAVIT
In accordance with Public Contract Code Section 7106, the undersigned, being first duly
sworn, deposes and says that he or she holds the position listed below with the bidder, the
party making the foregoing bid, thatthe bid is not made in the interest of, or on behalf of, any
undisclosed person, partnership, company, association, organization, or corporation; thatthe
bid is genuine and not collusive orsham; thatthe bidder has not directly or indirectly induced
or solicited any other bidder to put in a false or sham bid, and has not directly or indirectly
colluded, conspired, connived, or agreed with any bidder or anyone else to put in a sham
bid, or that anyone shall refrain from bidding; that the bidder has not in any manner, directly
or indirectly, sought by agreement, communication, or conference with anyone to fix the bid
price of the bidder or any other bidder, or to fix any overhead, profit, or cost element of the
bid price, or of that of any other bidder, or to secure any advantage against the public body
awarding the contract of anyone interested in the proposed contract; that all statements
contained in the bid are true; and, further, that the bidder has not, directly or indirectly,
submitted his or her bid price or any breakdown thereof, orthe contents thereof, or divulged
information or data relative thereto, or paid, and will not pay, any fee to any corporation,
partnership, company association, organization, bid depository, orto any member or agent
thereof to effectuate a collusive or sham bid, /1 I.
Signature
Typed or Printed Name
Title
T16 Ao'-M 1 L—
Bidder
Subscribed and sworn before me
This — �– day of IWi_" 20_ CS .
Notary blic in nd for
the Sta e o ifornia
My Commission Expires: 9'
0 S ZIU EH. N.
COMM. #2022906 !
L7' NOTARY PUBLIC •'CALIFORNIA
LOB�ANGELES COUNTY
ca 4q "'It . MAY 2, 2017
CBF - 11
DIDDER: a4v Miller Contracting
SECTION 1- BIb SCHEDULE
r
cer - o
BIDDER: Sully Miller Confiractin�
BID SCHEDULE
SCHEDULE OF PRICES FOR
MONTEBELLO BLVD. I TOWNE CENTER DRIVE RESURPACIN13
MEDIAN AND LANDSCAPE ENHANCEMENTS
PROJECT No. 21806
;i
BASE BID SCHEDULE
NO.
ITEM DESCRIPTION
UNIT OF
MEASURE
qTY.
PRICE
ITEM
COST
1
Clearing & Grubbing per plans
LS
1
and specifications, See technical
provisions TP -2, TP -3 & TP4_
co
a- .
2
Disposal of Waste Materials,
LS
1
ao coo. '
ao o . —
3
Cold milt 2,0- inches thick existing
Pavement.
SF
164,360
4
Construct 1.5 inches thick
TONS
9,545
pavement overlay ARHM -GG -C
(PG 6416} as indicated on the
��•
✓ 3/ 2 S
plans.
5
Construct 1.0 Inches thick
TONS
1,030
Asphaltic Leveling course D1
7 � 0 ,
(PG 64 -10) as indicated on the
So
plans.
.
6
Remove 6- inches of existing
SF
4,800
pavement and replace It with 4-
inches of AC B -PG 64 -10 Base
s. S
as aO(D
Course over compacted native.
7
Remove, Dispose and Construct
SF
3,524
4- inches thick PCC Sidewalk per
9
SPPWC Std. Plan 113 -1.
8
Remove, Dispose and Construct
LF
145
s- inches Curb and 24- inches
Gutter per SPPWC Std. Plan
7 i
J 5 �
5
120.2,
9
ReMOVe, Dispose and Construct
LF
135
8- Inches PCC Curb Only per
SPPWC
Std, Plan 120 -2,
10
Remove, Dispose and Construct
EA
10
PCC Curb Ramps per SPPWC
Std, Plan 111
-4.
/
i
CBF -1
I'
BIDDER: -Sally AAiIIPr C nntrarti
I
TOTAL, BABE BID PRICE (SCHEDULE BID PRICE) -.
amount in wiftteri form
Note: The City of Rosemead reserves the right to reduce or increase the quantities of any items in
the schedule of bid items above, within the limits define in Section 3 -2.2.1 of the Standard
Specifications, to stay within the budgeted amount of this project.
If the Bid Documents specify alternate bid items, the following Alternate Bid amounts shall
be added to or deducted from the Total Bid Price entered above. The owner can choose to
include one or more of the alternates in the Total Bid Price of the Project. If any of the
Alternate Bids are utilized by the Owner, the resulting amountshail be considered the Total
Bid Price for the Project.
CBF -2
I
EDOUble DESCRIPTION
UNIT OF
MEASURE
1ST.
CITY.
UNIT
PRICE
ITEM
COST
ust Sewer Manhole to
EA
5 APWA
S #d. Ptan 205.1.
/
12
Adjust Water Valve /Gas Valve to
EA
4
Grade.
7S,
�/
13
Install Landscape per Plans and
LS
1
Specifications Complete as
indicated
g Doe)
(o p�
on Sheet No, 3 to 7.
14
Install Irrigation per Plans and
LS
1
Specifications Complete as
Indicated
73 aoo. °
7.3 000
on Sheet No. 8 to 11.
15
Install Survey Weil Monument
EA
g
Per City of Rosemead Std. Plan
S08 -001. See Section 2 -9
1
Surveying of the General
Provision -7 per details (Cover,
Sleave & Dome will be provided
by the City at no cost).
1s
Install Traffic Striping, Traffic
LS
Signal Loops and Pavement
Markers per the Striping Plans
and Specifications Complete.
17
Remove Existing and Install
SF
4
50/50 Mix of Yosemite and
Arizona Cobble River Rock 8°
1 5 ' ,/
� 3`y /
7
Dia. Min. to 12" Dia. Max as
Indicated on Plans and
Specifications Complete,
I
TOTAL, BABE BID PRICE (SCHEDULE BID PRICE) -.
amount in wiftteri form
Note: The City of Rosemead reserves the right to reduce or increase the quantities of any items in
the schedule of bid items above, within the limits define in Section 3 -2.2.1 of the Standard
Specifications, to stay within the budgeted amount of this project.
If the Bid Documents specify alternate bid items, the following Alternate Bid amounts shall
be added to or deducted from the Total Bid Price entered above. The owner can choose to
include one or more of the alternates in the Total Bid Price of the Project. If any of the
Alternate Bids are utilized by the Owner, the resulting amountshail be considered the Total
Bid Price for the Project.
CBF -2
I
BIDDER: Sully Miller QgrrfTacting_
The undersigned agrees that these Contract Bid f=orms constitute a firm offer to the Owner which
cannot be withdrawn for the number of Working mays indicated in the Notice Inviting Bids from and
after the bid opening date, or until n Contract for the Worl< is fully executed by the Owner and a third
party, whichever is earlier. The undersigned also agrees that if there is a discrepancy between the
written amount of the Bid Price and the numerical amount of the Bid Price, the written amount shall
govern.
Attached hereto is a certified check, a cashier's check or a bid bond in the amount of
Dollars ($ said amount being not less than ten percent (10%) of the Total
Bid Price. The undersigned agrees thatsaid amount shall be retained by the Owner if, upon award,
we fall or refuse to execute the Contract and furnish the required bonds, certificates and
endorsements of insurance and other certifications within the time provided,
If awarded a Contract, the undersigned agrees to execute the formal Contract, which will be
prepared bythe Owner for execution, within five (5) Calendar Days following the Letter of Award for
the Contract, and will deliver to the Owner within that same period the necessary original Certificates
of insurance, Endorsements of Insurance, Performance Bond, Payment Bond and all other
documentation and certification required by the Contract.
The undersigned offers and agrees that if this bid is accepted, it will assign to the purchasing body
all rights, title, and interest in and to all causes of action it may have under Section 4 of the Clayton
Act (15 U.S.C. Section 15) or under the Cartwright Act (Chapter 2 of Part 2 of Division 7 of the
Business and Professional Gode), arising from purchases of goods, materials or services by the
Bidder for sale to the purchasing body pursuant to the bid. Such assignment shalt be made and
become effective at the time the purchasing body tenders final payment to he Contractor,
Bidder understands and agrees that, when requested by Owner, he shall provide: (1) evidence
satisfactory to the Owner of Bidders California contractors license(s) in good standing; (2) evidence
that the person signing this Bid is authorized to bind Bidder to this Bid and to a contract resulting
therefrom; and (3) any other information and documentation, financial or otherwise, needed by
Owner to award a Contract to the lowest responsible and responsive bidder.
The undersigned acknowledges receipt, understanding and full consideration of the foliowing
addenda to the Contract Documents.
Addenda Nos,
The Bidder understands and agrees thatthe Total Bid Price is inclusive of all labor, materials, and
equipment or supplies necessary to complete the Work as described in the Bid Documonts, if this
bid is accepted, the undersigned Bidder agrees to enter into and execute the Contract with the
necessary bonds and accept the Total Bid Price as compensation in full for all Work under the
contract.
CBF - 3
w , a
Bidder acknowledges that data submitted with its Contract Bid Forms which it requires to.•be
incorporated into a Contract arising out of this Submittal has been so identified by Bidder. Bidder
further acknowledges that the Owner may, at its discretion, incorporate any of the remaining data
submitted herewith into a contract arising out of this Bid.
By: L L ��
Ennis Ga nsen
Type or Print Name
Ass istant Secretary
Title
- ..__... ... _.._.._ ........ ........ _.. ..-
BIDDER: Sully Miller Contracting
135 S. State College 81 #400
Business Street Address
Brea CA szszi
City, State and Zip Code
7141578 -9660
Telephone Number
Bidder's /Contractor's State of Incorporation: Delaware
I�
1
s
a
{f
Partners or Joint Venturers:
Bidder's License Number(s): License # 747612 Class A Expiration Date 03/31/16
Department of Industrial Relations
Registered,No.. 1000003664
NOTES.
1) By its signature on this Bid, the Bidder certifies under penalty of perjury the accuracy of the
representations made on the Contract Bid Forms,
2) If Bidder is a corporation, enter State of Incorporation in addition to Business Address
3) If Bidder is a partnership. or joint venture, give full names of all partners or joint
venturers,
As further discussed in theTnstruetions to Bidders, Bidderwill be required
to provide evidence that the person signing on behalf of the corporation,
__p artnership or ,joint venture has the authority to do sn.
CBF -4
a
CALIFORNIA ALL - PURPOSE ACKNOWLEDGEMENT
CIVIL CODE §'1189
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this
certificate is attached, and not the truthfulness, accuracy, or validity of that document
State of California
County of Orange
On February 3, 2015 before me, Addana C. Trejo, Notary Public, personally appeared
Gansen
who proved to me on the basis of satisfactory evidence to be the person whose name is subscribed to the within
instrument and acknowledged to me that he executed the same in his authorized capacity, and that by his
signature on the instrument the person, or the entity upon behalf of which the person acted, executed the
instrument.
I certify under PENALTY OF PERJURY under the
laws of the State of California that the foregoing
paragraph is true and correct.
Place Notary Seal Above
Assistant
ff'�jal seal.
r
Vre of Notary P
C. Trejo, Not e
Though this section is optional, completing this information can deter alteration of the document or fraudulent
reattachment of this form to an unintended document.
Description of Attached Document
Title or Type of Document: Bid Proposal - Signature Page
Document Date: I Fe
Signers) Other Than Named Above:
Capacity Claimed by Signer:
Signer's Name Dennis G
Corporate Officer:
Other:
Signer Represents:
WITNESS my hand s
Signature
A
OPTIONAL
2015 Number of Pages
SULLY - MILLER CONTRACTING COMPANY
ADRIANA C. TREJo
Commission # 1991253
Notat Public - California z
My
Orange County r
Comm. Expires Oct 13, 2016 ~
Place Notary Seal Above
Assistant
ff'�jal seal.
r
Vre of Notary P
C. Trejo, Not e
Though this section is optional, completing this information can deter alteration of the document or fraudulent
reattachment of this form to an unintended document.
Description of Attached Document
Title or Type of Document: Bid Proposal - Signature Page
Document Date: I Fe
Signers) Other Than Named Above:
Capacity Claimed by Signer:
Signer's Name Dennis G
Corporate Officer:
Other:
Signer Represents:
WITNESS my hand s
Signature
A
OPTIONAL
2015 Number of Pages
SULLY - MILLER CONTRACTING COMPANY
Public Work's Contractor Registration Search Page 1 of 1
[Daf p,oi AeRl .ir);S �r� ��r?9_; Jt,(r4�9`r >II� � ; .� C+ °31rG�ri:
Division of Labor Standards Enforcement
Public Works Contractor Registration Search
This is a listing of current and active contractor regithapons pursuant to Divialon 2, Pad 7, Chapter t(commencing with section 1720) of the California Labor Cade.
Enter at least one search calorie to display active registered pu61lc works confractor(s) matching your selections.
Reglstratlon Number: x000003664
Contractor Legal Name: sully - Miller Contracting Company Contractor License Lookuo
License Number: 747Si2
Search Reset
Public Works Contractor Registration Web search Results
No Registered Contractors to display
CopSr'ight r0 2014 Stnte of Califorubt
https:H efiliiig .dir.ca,gov /PWCR/Search.actioia 1/30/2015
CERTIFICATE OF INCUMBENCY AND RESOLUTION
1, Anthony L, Martino, 11, do hereby certify that I am the Secretary of Sully- Miller Contracting
Company, a Delaware corporation, and that as such I have access to and custody of the corporate
records and minute books of said corporation.
And I do hereby further certify that the following persons are duly elected officers of said
corporation.
TITLE NAME
Chairman of the Board
Gordon R. Crawley
President
David Martinez
Vice President, Chief Financial Officer and Treasurer
Timothy P. Orchard
Vice President and Assistant Secretary
Michael Edwards
Vice President
Scott Bottomley
Secretary
Anthony L. Martino 11
Assistant Secretary
Jac Won
Assistant Secretary
Raymond Sanchez
Assistant Secretary
Dennis Gansen
I further certify that the following is a true and correct copy of a resolution duly adopted by the
Board of Directors of said Company at a meeting held on December 12, 2013, and that this
resolution has not been in any way rescinded, annulled, or revoked but the same is still in full
force and effect:
" BID TENDERS: GENERAL
RESOLVED, that any officer of the Corporation be and they hereby are
authorized in the name and on behalf of the Corporation, under its corporate seal
or otherwise (i) to prepare proposals and bids for the supplying of construction
materials and the performance by itself or in joint venture, of work of whatsoever
nature in connection with the construction or paving of highways, roads and
airports and in connection with earthworks and civil engineering projects of all
kinds, together with all work incidental thereto, (ii) to execute and submit any and
all such proposals and bids to any governmental authority, instrumentality, or
agency of the United States, its several states, territories and possessions,
including without limitation, any municipality or other political or corporate
subdivision thereof, and to any corporation, partnership, sole proprietorship, or
other business entity, (iii) in connection with any such submission, to deliver bid
deposits or bonds as may be required and (iv) to execute and deliver definitive
agreements binding the Corporation to perform work in accordance with any
proposals and bids authorized hereby."
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the corporate seal this 7th
day of Fobruary 2014.
(SEAL) Anthony L. IVIao I
Secretary
Sully - Miller Contracting Company
135 S. State College Blvd., Ste, 400
Brea, CA 92821
BIDDER: ,Stilly Miller Contractincl
SECTION 2
BID DATA FORMS
mzwi
kli
BIDDER_ Sully - Miller Contracting Company
Kidder shalt submit I% Bid data in accordance with the format shown on each of the following Bid
Data Forms. Bidders shall prepare and use as many sheets as are necessaryfo adequately provide
the Information required. Bidder ,hall ensure that every page of its Bid Data C'arms are properly.
Identified with the Bidder's name and page number,
2.IA BID BOND
KNOW ALL MEN BY THESE PRESENTS.
THAT Sully - Miller Con tracting Company
as
Principal, and Liberty Mutual Insurance Company
as Surety, are held firmly bound unto the
CITY OF ROSEMEAD (hereinafter called the OWNER) in the sum of
Ten Percent of the total amount bid --------------------------------------------------------------------- •- -- - -•-
t� "° ) , being not less than ten percent (10 %) of the Total
Bid Price; for the payment of which sum wl ll and truly to be made, we bind ourselves,
our heirs, executors, administrators, successors, and assigns, Jointly and severally,
firmly by these presents.
WHERFAS, said Principal has submitted a bid to the OWNER to perform all Work
required forthe Montebello Blvd,lTowno Center Drive Resurfacing Median and
Landscape Enhancement Project as set forth in the Notice Inviting Bids and
accompanying Bid Documents, dated February a 2095
NOW, THEREFORE, if said Principal is awarded a Contract for the Work by the
OWNER and, within the time and in the manner required by the above- referenced
Bid Documents, enters into the written form of Contract bound with said Bid
i Documents, furnishes the required bonds (one to guarantee faithful performance
= and the other tog uarantee payment fur labor and materials) furnishes the required
Insurance certificates and endorsements, and furnishes any other certiflcatfons as
may be required by the Contract, then this obligation shall be null and void; otherwise
a it shall remain in full force and effect. In the event suit is brought upon this bond by
the OWNER andjudgment is recovered, said Surety shall pay all costs incurred by
l the OWNER in such suit, including reasonable attorneys' fees to be fixed by the
r
Qourt.
SIGNED] AND STALED, this 30th day of January y 20 95
Sully - Miller Coutrac_ling Company SQL
Principal ( ) Liberty e MutuallnsuranneCOmpany ($EAL)
Y
By. �/� By
Slppn�lu Signature Victoria . Campbell, A t rney -In -Font
De'hms Tansen, Assistant Secretary
_i
CBF -6
CALIFORNIA ALL - PURPOSE ACKNOWLEDGEMENT
CIVIL CODE § 1189
A notary public or other officer completing this certificate verifies only, the identity of the individual who signed the document to which this
certificate is attached, and not the truthfulness, accuracy, or validity of that document
State of California
County of Orange
On February 3, 2015 before me, Addana C. Trejo, Notary Public, personally appeared
who proved to me on the basis of satisfactory evidence to be the person whose name is subscribed to the within
instrument and acknowledged to me that he executed the same in his authorized capacity, and that by his
signature on the instrument the person, or the entity upon behalf of which the person acted, executed the
instrument.
ADRIANA C. TREJO
Commission # 1991253
Notary Public - California z
Orange County
My Comm. Expires Oct 13, 201 fi
I certify under PENALTY OF PERJURY under the
laws of the State of California that the foregoing
paragraph is true and correct.
WITNESS my hand apfi ial / s t eal.
Signature /
ignature of Not
Id uma C. Trejo, P
Place Notary Seal Above
OPTIONAL
Though this section is optional, completing this information can deter alteration of the document or fraudulent
reattachment of this form to an unintended document.
Description of Attached Document
Title or Type of Document: Rid Bond- Signature Pa ge
Document Date: January 30 2015 Number of Pages 1
Slgner(s) Other Than Named Above:
Capacity Claimed by Signer:
Signer's Name Den Gansen
Corporate Officer: Assistant Secretary
Other:
Signer Represents: SUL - MILLER CONTRACTING COMPANY
CALIF ORNIA c •
�e�.��c.T< e:�<.�ra<.r— ..<A.v....r<r�. �•_.n<.�....e�m .�. .:�. ...ra.o, ... e�<. r....,.e:Kr�_
A notary public or other officerbompleting this certificate verlfles only the Identity of the Individual who signed the
document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.
State of California
County of Orang
On JAN 3 0 241 before me , Magall Melchor Notary Public
Date Here Insert Name and Title of the Officer
personally appeared victoria M.
Name(s) of Signer(s)
who proved to me on the basis of satisfactory evidence to be the persons) whose name(s) is /are
subscribed to the within instrument and acknowledged to me that -he /she /they- executed the same in
his /her /their authorized capacity(les), and that by his /her /their signature(s) on the Instrument the person(s),
or the entity upon behalf of which the person(s) acted, executed the instrument.
M M LC H R�
ADALI [
Commission # 2079392 m
-r' Notary Public - Californla
Orange County
M Comm. Expires Sep 3, 2018
I certify under PENALTY OF PERJURY under the laws
of the State of California that the foregoing paragraph
is true and correct.
WITNESS my hand and official leay
Signature 4 ff
Signature o Notary Public
Place Notary Seal Above
OPTIONAL
Though this section is optional, completing this information can deter alteration of the document or
fraudulent reattachment of this farm to an unintended document.
Description of Attached Document
Title or Type of Document:
Number of Pages:
Capacity(les) Claimed by Signer(s)
Signer's Name:
Corporate Officer — Title(s):
El Partner — 0 Limited ❑ General
• Individual IN Attorney in Fact
• Trustee 0 Guardian or Conservator
❑ Other:
Signer Is Representing:
Liberty Mutual Insurance Compa
Document Date:, JAN 3 0 2015 _
Signer(s) Other.Than Named Above:
Signer's Name:
Corporate Officer — Title(s):
❑ Partner — ❑ Limited ❑ General
• Individual ❑ Attorney in Fact
• Trustee ❑ Guardian or Conservator
❑ Other:
Signer Is Representing:
.......... ..... ........
f
BIDDER: Sully Miller Contracting
2,13 LIST fD 'a1 C^rPflaBD SllE3C[St�TM —CORS
In compliance with tho "Subletting and Subcontracting f=air Practices Act," Soctions 4100
through 4114 of the California Public Contract Code, and any amendments thereto, each
Bidder shall provide the information requested below - for each subcontractor who will
perform work, labor orrenderservice to Bidderin oraboutthe construction of the Workin an
amount in excess of one -half of one percent (greater than 0.5 %) of the Bidder's Total Bid
Price, or, in the case of bids or offers for the construction of streets or highways, including
bridges, in excess of one-half of 1 percent of the Contractor's total bid or ten thousand
dollars ($10,000), whichever is greater, and shall further set forth the portion of the Work
which will be done by each subcontractor. Bidder shall list only one subcontractor for any
one portion of the Work.
Pursuant to Public Contract Code Section 4104, the Owner has determined that !twill allow
Bidders twenty -four (24) additional hours after the deadline for submission of bids to submit
the information requested by the Owner about each subcontractor, other than the name and
location of each subcontractor.
If the Bidder fails to specify a subcontractor for any portion of the Work to be performed
under the Contract, it shall be deemed to have agreed to perform such portion Itself, and
shall not be permitted to subcontract that portion of the Work except under the conditions
hereinafter set forth below.
Subletting or subcontracting of any portion of the Work h Wass of one half of one percent
(greaterthan 0;5 %) of the Total Bid Price or, in the case of bids or offers forthe construction
of streets or highways, including bridges, In excess of one -half of 1 percent of the
Contractor's total bid or ten thousand dollars ($10,000), whichever is greater, for which no
subcontractor was designated in the original bid shall only be permitted in cases of public
emergency or necessity, and then only after Owner approval.
i
J
I
CBF -7
BIDDER: Su lly Miller Contracting
2.? LIST f JF PR4P6S D 5t ®R5 (continued)
(* Duplicate NeM2 Paget ii needed 5or Ilsting addlBonal subeoniractars.�]
Name and Location Description of Work
of Subcontractor n to be Subcontracted f Address;
License No.. & yo
Depafent of industrial Relation Registration No.
Name and LOe, tion Description of Work
of Subcont // to be Subcontwtod
Name: na > Z5. 6 1 u L
Address S
License Ne.:
Department of Industrial Relation Registration No
Name and Location Description of Work
of S�r to be Subcontracted
Name: ZO
Address: lJ it ni Tip
License No.: -7�� 310 --
Department of Industrial Relation Registration No
No and Locatjon
r� of Subcontractor
Description of Work
to ba Subcontracted
Nama
Address
License Ne -:
Department of Industrial Relation Reglstration No._
tz
Name and LoCation
of Subcontractor
"a
f
,a
Description of Work
/ to be Subcontract
Name: CsSz L. ✓ S
Address: � - V �e�/ � -M-m4 -f
/v 1 L( f
License No.: I-
Dopartment of Industrial Relation Reglstration No.
GBF,B
:.. - -
2.
3.
2.c
The following are the names, addresses and telephone numbers for throe) public agencies for which BIDDER
has performed similar work within the past two (2) yearn
* *Please see attached **
1,
Name and Address of Owner
Name and telephone number of person familiar with project
Contract amount Type of Work Date Completed
Name and Address of owner
Name and telephone numberof person familiar wifh project
Contract amount Typa of Work Date Completed
Name and Address of Owner
Name and telephone numberof person familierwith project
Contract amount Typa of Work Date Completed
4.
Name and Address of Owner
Name and telephone number of person famillarwith project
Contract amount Type of Work Date Completed
i
1
o�
�j
CBF -9
SULI-YMII_LER
CONTIRAC;TINCr Ca.
BIDDER`S EXPERIENCE AND QUALIFICATIONS
Project Name /Number:
Start and Finish Dates:
Project Description:
Agency Name:
Contact Person:
2011 ROADWAY MAINTENANCE & SLURRY SEAL PROGRAM/ 10150602
8/2013- 12/2014
SWPPP, AC GRIND & OVERLAY, CRACK SEAL, SLURRY SEAL, STRIPING & MARKING
PORT OF LONG BEACH
92S HARBOR PLAZA DRIVE
LONG BEACH, CA 90802
ALT VATANSHENAG
Telephone: 562/437 -0041
Original Contract Amount: $434,380 Final Contract Amount: $455,300
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Project Name /Number: KIOWA RANCH ROAD TO DEL ORO ROAD/ 10149809
Start and Finish Dates: 9/2013- 11/2013
Project Description: AC GRIND & OVERLAY, PCC IMPRV., STRIPING & MARKING, SURVEY, TREE
REMOVAL, CMB, ADJUST UTILITIES, SLURRY SEAL
Agency Name: TOWN OF APPLE VALLEY
14975 DALE EVANS PARKWAY
APPLE VALLEY, CA 92307
Contact Person:, BRETT MORGAN Telephone: 7601240 -7000
Orlginal Contract Amount. $ 662,781 Final Contract Amount: $663,811
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Project Name /Number: ARTESIA BLVD. & WESTERN AVE. STREET IMPRV. /10147379
Start and Finish Dates:
7/2013- 10/2013
Project Description:
SIGNS, SWPPP, TRAFFIC CONTROL, TREE REMOVAL, STRIPING & MARKING, COLD
MILL, ELECTRICAL, PCC, AC, ARHM, SURVEY, ADJUST MANGLES & WATER VALVES;
LOOPS
Agency Name:
CITY OF GARDENA
1700 W. 162 STREET
GARDENA, CA 90247
Contact Person:
JOHN FELIX Telephone: 310/217 -9500
Original Contract Amount:
$645,472 Final Contract Amount: $605,644
Change in contract amount is due to items of work heing deleted by the agency.
Updated JULY 2014
CaLm
SULLY - MILLER
CONTRACTING CO.
BIDDER'S
AND QUALIFICATIONS
Project Name /Number.
BROOKSHIRE AVENUE PAVEMENT REHABILITATION PROJECT/ 10147171
Start and Finish Dates:
6/2013 - 1112013
Project Description:
SURVEY, TRAFFIC CONTROL, COLD MILL, ARHM, AC, PCC, CATCH BASIN,
ELECTRICAL, ADJUST MANHOLES & WATER VALVES, STRIPING & MARKING, TRAFFIC
SIGNAL LOOP DETECTORS
Agency Name:
CITY OF DOWNEY
11111 BROOKSHIRE AVENUE
DOWNEY, CA 90241 .
Contact Person:
DESI GUTIERREZ Telephone; 562/622 -3468
Original Contract Amount:
$1,366,800 Final Contract Amount: $1,446,784
Change in original contract
amount is due to extra work and /or contract change orders adding
work.
Project Name /Number;
TILDEN TERRENCE/ 10146479
Start and Finish Dates;
4/2013- 9/2013
Project Description;
ON -SITE, OFF -SITE, ALLEY IMPRV.
Agency Name;
DREYFUSS CONSTRUCTION -
5855 GREEN VALLEY CIRCLE, STE. 300
CULVER, CA 90230
Contact Person;
DAVID SANCHEZ Telephone: 310 /645 -9565
Original Contract Amount;
$748,082 Final Contract Amount. $835,884
Change in original contract
amount is due to extra work and /or contract change orders adding
work
Project Name /Number:
LA LOGISTICS CENTER/ 10144825
Start and Finish Dates:
3/2013 - 6/2013
Project Description:
B- PERMIT
Agency Name:
XEBEC BUILDING COMPANY, INC.
3010 OLD RANCH PARKWAY, STE. 480
SEAT_ BEACH, CA 90740
Contact Person:
SIOBHAN SHARPLES Telephone: 562/795 -0270
Original Contract Amount:
$373,756 Final ContractArrnount; $383,456
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Updated JULY 2014
S LI I,LY M ILL ER
CONTRACTING CO.
BIDDER'S EXPERIENCE AND QUALIFICATIONS
Project Name /Number; SHAY ROAD & BALDWIN LAKE ROAD/ 10144777
Start and Finish Dates: 5/2013- 7/2013
Project Description: AC GRIND & OVERLAY, COLD IN PLACE RECYCLING, CRACK SEAL, CEMENT TREATED
BASE, SIGNS & STRIPING & MARKING
Agency Name: COUNTY OF SAN BERNARDINO DEPARTMENT OF PUBLIC WORKS
825 EAST THIRD STREET
SAN BERNARDINO, CA 92415 -0835
Contact Person: FRANK LUNA Telephone: 909/387 -8104
Original Contract Amount: $1,998,888 Final Contract Amount; $1,892,276
Change in contract amount is due to items of work being deleted by the agency,
Project Name /Number:
Start and Finish Dates:
Project Description:
Agency Name:
Contact Person:
AGOURA ROAD WIDENING PHASE 1 /CANWOOD STREET IMPRV./ 10144581
4/2013- 10/2013
AC /ARHM GRIND & OVERLAY, CAB, PCC IMPRV., COLD -IN -PLACE RECYCLING,
ADJUST UTILITIES, SIGNING & STRIPING, TREE PROTECTION /REMOVAL,
LANDSCAPE &IRRIGATION
CITY OF AGOURA HILLS
30001 LADYFACE COURT
AGOURA HILLS, CA 91301 -1335
CHARMAINE YAMBAO
Telephone: 8181597 -7300
Original Contract Amount. $ 1,058,551 Final ContractAmount: $1,273,120
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Project Name /Number: CEDARS -SINAI MEDICAL CENTER-ADVANCES HEALTH SCIENCES PAVILION PROJECT/
10143403
Start and Finish Dates: 2/2013- 4/2013
Project Description: CMB, AC GRIND & OVERLAY, STRIPING, DOUBLE ADJUST MANHOLES
Agency Name: HATHAWAY DINWIDDIE CONSTRUCTION COMPANY
811 WILSHIRE BLVD„ STE, 1500
LOS ANGELES, CA 90017 -2632
Contact Person: STEPHEN DUHM Telephone. 2131236 -0500
Original Contract Amount: $229,000 Final Contract Amount: $234,671
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Updated JULY 2014
SULLY- .MILLER
CONTRAC,TTNG CO.
BIDDER "S EXPERIENCE AND QUALIFICATIONS
Project Name /Number:
BEAR VALLEY CUTOFF/ 10143018
Start and Finish Dates:
5/2013 - 6/2013
Project Description:
ARHM /AC GRIND & OVERLAY, CRACK SEAL, SIGNS & STRIPING & MARKING
Agency Name:
SAN BERNARDINO COUNTY DEPARTMENT OF PUBLIC WORKS
825 FAST 3R STREET
SAN BERNARDINO, CA 92415
Contact Person:
SUNDARAMOORTHY Telephone: 909/387 -8104
SRIRAJAN
Original Contract Amount:
$928,725 Final Contract Amount: $802,793
Change in contract amount is due to items of work being deleted by the agency.
Project Name /Number:
DALE EVANS PARKWAY OVERLAY PROJECT INTERSTATE. 15 TO JOHNSON ROAD &
JOSHUA ROAD OVERLAY PROJECT/ 10141551
Start and Finish Dates:
1/2013- 4/2013
Project Description:
AC GRIND & OVERLAY, STRIPING & MARKING, GRADING, SWPPP
Agency Name:
TOWN OF APPLE VALLEY
14955 DALE EVANS PARKWAY
APPLE VALLEY, CA 92307
Contact Person:
BRENT MORGAN - Telephone: 7601240 -7000
Original Contract Amount:
$720,677 Final ContractAmount: $743,789
Change in original contract
amount is due to extra work and /or contract change orders adding
work.
Project Name/Number:
FY 2012/13 STREET MAINTENANCE PROJECT,( 10140019
Start and Finish Dates:
1012012 - 12/2013
Project Description:
ARHM GRIND & OVERLAY, ADJUST UTILITIES, SURVEY, CRACK SEALING
Agency Name:
CITY OF MALIBU
23825 STUART RANCH ROAD
MALIBU, CA 90265
Contact Person:
ROBERT DUBOUX Telephone: 310/456 -2489
Original Contract Amount.
$652,716 Final Contract Amount: $929,630
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Project Name /Number: THE ICIS APARTMENTS/ 10139570
Start and Finish Dares: 9/2012- 11/2012
Project Description: B- PERMIT
Agency Name: ALLIANCE RESIDENTIAL BUILDERS II G.P., INC.
450 NEWPORT CENTER DR., #550
NEWPORT, CA 92660
Contact Person: SCOTT CRIGGS
Telephone: 9491706 -8460
Original Contract Amount. $ 299,701 Final Contract Amount: $335,741
Change in original contract amount is due to extra work: and /or contract change orders adding work.
Updated JULY 2014
7
SULLY MILT.ER
CONTRACTING CO.
BIDDER'S EXPERIENCE AND QUALIFICATIONS
Project Name /Number: 2012 VARIOUS STREE S RESURFACING 11, PROP 1 B & LACMTA/ 10137709
Start and Finish Dates: 10/2012 -2013
Project Description:
AC /ARHM GRIND & OVERLAY, PCC IMPRV., ADJUST UTILITIES, LOOPS, STRIPING &
MARKING, CONSTRUCTION AREA SIGNS
Agency Name:
CITY OF MONTEREY PARK
320 WEST NEWMARK AVENUE
MONTEREY PARK, CA 91754
Contact Person:
ROYALEONSO Telephone: 626 - 307 -1458
Original Contract Amount:
$996,500 Final Contract Amount: $1,082,247
Change in original contract
amount is due to extra work and /or contract change orders adding
work.
Project Name /Number:
CITYWIDE ANNUAL OVERLAY PROGRAM & CONCRETE REPLACEMENT PROGRAM/
10137355
Start and Finish Dates:
912012- 312013
Project Description:
AC /ARHMGRIND & OVERLAY, AC DIKE, LOOPS, ADJUST UTILITIES, CAB, STRIPING &
MARKING, PCC IMPRV., SURVEY .
Agency Name:
CITY OF CARSON
701 EAST CARSON STREET
CARSON, CA 90745
Contact Person:
RICK BOUTROS Telephone: 3101830 -7600
original Contract Amount:
$1,295,000 Final Contract Amount. $1,504,633
Change in original contract
amount is due to extra work and /or contract change orders adding
work.
Project Name /Number:
Start and Finish Dates:
Project Description:
Agency Name:
Contact Person:
PREVENTIVE MAINTENANCE OF STREETS-2012,110137154
11/2012- 3/2013
COLD MILL, ARHM, AC ADJUST SEWER MANHOLES, CLEAR & GRUB, STRIPING &
MARKING, LOOP DETECTORS, SURVEY
CITY OF PASADENA
100 N. GARFIELD AVE.
PASADENA, CA 91101
MORLEY swiYA
Telephone: 626/744 -4000
original Contract Amount: $1,138,208 Final ContractAmount $1,273,343
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Updated JULY NA
STJLLX .MILLER
CONTRACTING CO.
BIDDER'S EXPERIENCE AND QUALIFICATIONS
Project Nameftmber:
IMPRV. OF LINCOLN AVENUE/ 10136832
Start and Finish Dates:
10/201.2- 3/2013
Project Description:
CONCRETE, AC, CRACK SEAL, COLD MILL; ARHM, ELECTRICAL, MANHOLES, STORM
DRAIN, MARKERS, LOOPS
Agency Name;
CITY OF PASADENA
100 N. GARFIELD AVE.
PASADENA, CA 91101
Contact Person:
SEAN SINGLETARY Telephone: 626 - 744-4000
Original Contract Amount;
$1,348,474 Final Contract Amount $1,641,677
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Project Name /Number:
2012 OVERLAY PROGRAM/ 10136566
Start and Finish Dates:.
10/2012 - 4/2013
Project Description:
AC /ARHM GRIND & OVERLAY, ADJUST MANHOLES, ROOT PRUNE, STRIPING,
SIGNING, MARKERS, LEGENDS
Agency Name:
CITY OF THOUSAND OAKS
2100 THOUSAND OAKS BLVD,
THOUSAND OAKS, CA 91362
Contact Person:
MIKETOHIDIAN Telephone: 8051449 -2400'
Original Contract Amount:
$3,795,547 Final Contract Amount. $3,972,046
Change in original contract
amount is due to extra work and /or contract change orders adding
work.
Project Name /Number:
RTE. 247, SNB CO (08- OP9304)/ 10131719
Start and Finish Dates:
7/207.2- 8/2012
Project Description:
SWPPP, SIGNS, TRAFFIC CONTROL, COLD PLANE, CRACKTREATMENT, AC, ARHM,
STRIPING & MARKING
Agency Name:
CALTRANS
1727 30 STREET
SACRAMENTO, CA 95816
Contact Person:
EHAB MINA Telephone; 916/227 -6300
original Contract Amount:
$4,865,508 Final Contract Amount. $4,988,720
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Updated JULY 2014
SULLY-MILLER
CON'T'RACTING Co.
@,IDDEWS EXPERIENCE AND QUALIFICATIONS
Project Name /Number: MANHATTAN BEACH BOULEVARD RESURFACING/ 10130442
Start and Finish Dates: 8/2012- 11/2012
Project Description: UTILITIES, TRAFFIC CONTROL, SIGNS, SURVEY, MANHOLES, PCC, AC, LANDSCAPE &
IRRIGATION, COLD MILL, EXCAVATION, STRIPING & MARKING
Agency Name: CITY OF REDONDO BEACH
415 DIAMOND STREET
REDONDO BEACH, CA 90277
Contact Person: JEFFTOWNSEND Telephone: 3101318 -0661
Original Contract Amount: $862,900 Final Contract Amount: $945,951
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Project Name /Number: PUBLIC WORKS YARD (BID SET NO. 2)/ 10130370 (11148C)
Start and Finish Dates: 11/2012 - 11/2012
Project Description: AC PAVING, PCC IMPROVEMENTS, ELECTRICAL, FENCING
Agency Name: CITY OF EL MONTE
1,133 VALLEY BLVD,
EL MONTE, CA 91731
Contact Person: TOM EARL Telephone: 626/580 -2001
Original Contract Amount: $462,370 Final Contract Amount: $462,370
NO CHANGE
Project Name /Number: SAFE ROUTES TO SCHOOL -CYCLE 7 BULB -OUTS, SIDEWALK &TRAFFIC SIGNAL
MODIFICATIONS/ 10130359
Start and Finish Dates. 5/2012- 11/2012
Project Description: CLEAR & GRUB, AC OVERLAY, PCC IMPRV., ADJUST U TILITIES, SURVEY, TRAFFIC
SIGNAL MODIFICATIONS, SIGNS, STRIPING & MARKING
Agency Name: CITY OF BURBANK
301 EAST OLIVE AVENUE, RM 320
BURBANK, CA 91502
Contact Person: MIKE SILVANI Telephone: 818/238 -5457
Original Contract Amount: $342,560 Final Contract Amount: $408,978
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Updated JULY 2014 7
SULLY - MILLER
CONTRACTING CO.
BIDDER'S EXPERIENCE AND QUALIFICATIONS
Project Name /Number: RTE. 39, (07- 3Y3204)/ 10130355
Start and Finish Dates: 7/2012 - 11/2012
Project Description.'
SWPPP, SIGNS, TRAFFIC CONTROL, COLD PLANE, CRACK TREATMENT, AC, ARIA,
Start and Finish Dates:
STRIPING & MARKING
Agency Name:
CALTRANS
1727 3D STREET
Agency Name:
SACRAMENTO, CA 95816
Contact Person:
REDA KAROUT Telephone: 916/227 -6300
Original Contract Amount.
$1,197,700 Final Contract Amount. $1,265,654
Change in original contract
amount is due to extra work and /or contract change orders adding
work.
$1,019,450 Final Contract Amount: $896,448
Project Name /Number: SLAUSON AVENUE/ 10130289
Start and Finish Dates: 10/2012- 3/2013
Project Description. CLEAR & GRUB, TREE REMOVAL /PLANTING, AC GRIND & OVERLAY, PCC IMPRV.,
STRUCTURES, STRIPING & MARKING
Agency Name: LOS ANGELES COUNTY DEPARTMENT OF PUBLIC WORKS
900 S. FREMONT AVENUE
ALHAMBRA, CA 91803
Contact Person: JOSE POU Telephoner 626/458 -5100
Original Contract Amount: $884,688 Final Contract Amount: $955,09.5
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Project Name /Number:
2011 -2012 STREET RESURFACING - VARIOUS LOCATIONS/ 10130260
Start and Finish Dates:
5/2012- 12/2012
Project Description:
AC OVERLAY, COLD MILL, CRACK SEAL, CMB, ADJUST VALVE COVER & MANHOLE,
LOOPS, STRIPING & MARKING
Agency Name:
CITY OF BEVERLY HILLS
455 N. REXFORD DR,, RM 290
BEVERLY HILLS, CA 90210
Contact Person:
JUAN MARTINEZ Telephone: 310/285 -2489
Original Contract Amount:
$1,019,450 Final Contract Amount: $896,448
Change in contract amount
is due to items of work being deleted by the agency.
Updated 3UL Y 2014
CKM
SULLY - MILLER
CONTRACTING CO.
BIDDER'S EXPERIENCE AND QUALIFICATIONS
Project Name /Number:
Start and Finish Dates:
Project Description:
Agency Name:
Contact Person:
STREET RECONSTRUCTION -HELEN RUNYON DR. & E. MOUNTAIN VIEW ST./
10130241
3/2012- 7/2012
AC PAVING, PCC, FABRIC, LOOPS, SIGNS & STRIPING & MARKING
CITY OF BARSTOW
220 E. MOUNTAIN VIEW STREET, STE. A
BARSTOW, CA 92311
� � Tit • • �/ /3I
Telephone: 760/255 -5156
Original Contract Amount:. $1,027,886 Final Contract Amount; $1,138,746
Change in original contract amount is due to extra work and /or contract change orders adding
work.
project Name /Number:
2012 LOCAL STREET REHABILITATION PROJECT/ 10130069
Start and Finish Dates:
5/2012-812012
Project Description:
AC GRIND & OVELRAY, COLD CENTRAL PLANT RECYCLING, LOOPS, ADJUST
UTILITIES
Agency
CITY OF GARDEN GROVE
11222 ACACIA PARKWAY
GARDEN GROVE, CA 92840
Contact Person:
ROBERT MOUNGEY Telephone: 714/741 -5000
Original Contract Amount:
$2,917,670 Final Contract Amount: $2,846,871
Change in contract amount is due to items of work being deleted by the agency.
Project Name /Number;
RECONSTRUCTION OF CASTAIC POWER PLANT ACCESS ROAD/ 10129951
Start and Finish Dates:
8/2012- 10/2012
Project Description:
AC, COLD MILL, STRIPING & MARKING
Agency Name:
LOS ANGELES DEPARTMENT OF WATER & POWER
111 N. HOPE STREET
LOS ANGELES, CA 90012
Contact Person:
JOSH FONG Telephone: 213/364 -3464
original Contract Amount:
$602,466 Final Contract Amount: $556,923
Change in contract amount is due to items of work being deleted by the agency.
Project Name /Number:
CACTUS AVENUE, FREDERICK STREET & RESOURCE WAY/ 10129926
Start and Finish Dates:
5/2012 - 512013
Project Description:
STREET, STORM DRAIN, SEWER, & WATER, SIGNING & STRIPING, TRAFFIC SIGNAL,
LOOPS, STREET LANDSCAPE & IRRIGATION, ELECTRICAL, COLD PLANE, PCC, AC,
CATCH BASIN
Agency Name:
US REAL EST AT E LIMITED PARTNERSHIP, A TEXAS LTMI t ED PARTNERSHIP, 19300
19300 HAMILTON AVE., STE. 200
GARDENA, CA 90248
Contact Person:
FLOYDYOUNKIN Telephone: 310/323 -9100
Original Contract Amount:
$2,753,919 Final ContractArnount: $3,212,557
Change in original contract amount is due to extra work and /or contract change orders adding work.
Updated JULY 201:
S ULLY-M ILLER
CONTRACTING CC).
BIDDER'S EXPERIENCE AND QUALIFICA`fIONS
Project Name /Number: NATIONAL TRAILS HIGHWAY/ 10128949 (121,850
Start and Finish Dates: 5/2012 — 6/2012
Project Description: CRACK SEAL COLD PLANE, PAV, STRIPING
Agency Name: SAN BERNARDINO COUNTY, DEPARTMENT OF PUBLIC WORKS
825 EAST THIRD STREET
SAN BERNARDINO,CA 92415 -0835
Contact Person:
NIDHAMAL -REYES Telephone: 909/387 -8104
Original Contract Amount:
$1,040,950 Final Contract $931,795
Change in contract amount is due to items of work being deleted by the agency.
Project Name /Number:
TAXILANE D -10 RECONSTRUCTION / 10128948 (121740)
Start and Finish Dates:
5/2012- 12/2012
Project Description:
SURVEY, AC, REMOVE PCC, FENCING, ADJUSTING WATER UTILITY, SWPPP,CAB,
COLD PLANE, PCC, FABRIC, STRIPING & MARKING & SIGNS
Agency Name:
LOS ANGELES WORLD AIRPORTS, AIRPORT DEVELOPMENT GROUP
7301 WORLD WAY WEST, 9 7H FLOOR
LOS ANGELES, CA 90045
Contact Person:
GORAN LAZAREVIC, P.E. Telephone: 310/957 -7149
Original Contract Amount:
$6,383,321 Final ContractAmount: $5,939,022
Change in contract amount
is due to items of work being deleted by the agency.
Project Name /Number:
Start and Finish Dates:
Project Description:
Agency Name:
Contact Person.'
CAMPBELL HALL COMMUNITY ARTS AND EDUCATION CENTER / 10128947 (11153C)
312012 - 4/2012
B — PERMIT: REMOVAL /REPLACEMENT OF CURB & GUTTER, SIDEWALK & SIDEWAY,
SIGNAL, STREET LIGHTING, STRIPING /SIGNING
MATT CONSTRUCTION CORPORATION
9814 NORWALK BLVD., SUITE 100
SANTA FE SPRINGS, CA 90670
KRISTOPHER BARR
Telephone: 562/903 -2277
Original Contract Amount. $ 473,542 Final Contract Amount: $539,471
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Updated JULY 2014 10
MUD
SULLY .MILLER
CONTRACTING CO_
BIDDER'S EXPERIENCE AND QUALIFICATIONS
Project Name /Number:
Start and Finish Dates:
Project Description:
Agency Name:
Contact Person:
RESIDENTIAL STREET REHABILITATION FY2011 -2012 & ANNUAL WATER MAIN
REPLACEMENT PROGRAM FY 2011 -2012 / 10128945 (121710)
3/2012 - 4/2013
AC GRIND & OVERLAY, SLURRY SEAL, PCC IMPROVEMENTS, ADJUST MANHOLES,
TREE R00T PRUNE, STRIPING /MARKING, LOOPS, SURVEY, CMB, WATER
LINE/WATER MAIN
CITY 0 F LA HABRA
201 E. LA, HABRA BLVD.
LA HABRA, CA 90631
CHUCK STEPHANS
Telephone: 9491262 -9379
Original Contract Amount: $4,887,619 Final Contract Amount: $6,081,745
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Project Name /Number:
Start and Finish Dates:
Project Description:
Agency Name:
Contact Person:
NEWPORT BLVD. DOMESTIC WATER RELOCATION PROJECT/ 10128919 (11167C)
2/2012- 4/2013
AC PAVING, WATERLINE, PCC IMPROVEMENTS, & REMOVE METERS
IRVINE RANCH WATER DISTRICT
15600 SAND CANYON AVE,
IRVINE CA, 92619 -7000
TOM BONKOWSKI
Telephone: 949/453 -5692
Original Contract Amount: $3,657,815 Final Contract AmoUnt: $3,936,118
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Project Name /Number:
Start and Finish Dates:
Project Description:
Agency Name:
Contact Person:
LONG BEACH ANNUAL 2012 — GAS & ENGINEERING 10128849/(100710
10128917/(111630
312012 - 1/2013
EMERGENCY REPAIRS
CITY OF LONG BEACH
333 WEST OCEAN BLVD.
LONG BEACH, CA 90802
CHARLES RAMEY
Telephone: 562/570 -5176
Original Contract Amount. $ 2,000,000 Final ContractAmount: $2,210,831
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Updated JULY 2014 11
S1.JLLY- MILLER
CONTRACTING CO.
BIDDERS EXPERIENCE AND QUALIFICATIONS
Project Name /Number:
Start and Finish Dates:
Project Description;
Agency Name:
Contact Person:
PASADENA AVENUE STREET IMPROVEMENT PROJECT /10128916 (11161C)
2/2012 - 6/2012
AC PAVING, ADJUST MANHOLE, COLD MILLING, PCC IMPRV„ SIGNS,
LAN DSCAPING/IRRIGATION & STRIPING /MARKING
CITY OF PASADENA
1414 MISSION STREET
SOUTH PASADENA, CA 91030
GABRIEL B. NEVAREZ Telephone: 626/403 -7248
Original ContractAmount: $499,995 Final Contract Amount: $535,714
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Project Name /Number: STREET RECONSTRUCTION SECTION — I, AGNES AVE., ELM AVE., FRANCES AVE.,
Updated JULY 2014 L2
NORTH MURIEL DR., ADELE AVE„ KATHLEEN. /10128914(11159C)
Start and Finish Dates:
2/2012 - 5/2012
Project Description:
AC PAVING, PCC IMPRV, FABRIC, LOOPS, SIGNS, & STRIPING & MARKING
Agency Name:
CITY OF BARSTOW
220 E. MOUNTAIN VIEW ST., SUITE A
BARSTOW, CA 92311
Contact Person:
DOMINGO GONZALEZ Telephone: 760/255 -5156
Original Contract Amount:
$947,275 Final Contract Amount: $977,541
Change in original contract
amount is due to extra work and /or contract change orders adding
Work.
Project Name /Number:
ROBSON AVE. & MARTIN ST., STPL- 5107(027) /10128913(11154U)
Start and Finish Dates:
2/2012- 5/2012
Project Description:
RECONSTRUCTION PROJECT
Agency Name;
CITY OF SANTA MONICA
1685 MAIN STREET
SANT A MONICA, CA 90401
Contact Person:
ALLAN SHETH Telephone: 310/458 -2201
Original Contract Amount:
$383,000 Final Contract Anount; $380,911
Change in contract amount is due to items of work being deleted by the agency.
Project Name /Number:
MERVYN'S BLDG. RENOVATION CONSTRUCTION CONTP.ACi /10128912(11151C)
Start and Finish Dates:
10/2011- 11/2012
Project Description:
SITE UTILITIES, PAVING, AND SITE IMPROVEMENTS
Agency Name:
WESTFIELD, LLC
2753 E. EASTLAND CTR DR,
WEST COVINA, CA 91791
Contact Person:
ROBERTALLEN Telephone: 626/967 -3399
Original Contract Amount.
$980,902 Final Contract Amount: $1,284,834
Change in original contract amount is due to extra work and /or contract change orders adding work.
Updated JULY 2014 L2
S U LLYM ILLER
CONTRACTIN<s CCU.
BIDDER'S EXPERIENCE AND QUALIFICATIONS
Project Name /Number:
Start and Finish Dates:
Project Description:
Agency Name:
Contact Person:
RUNWAY 15 RUNWAY SAFETY AREA IMPROVEMENTS /1.0128907(11143C)
1/2012 - 4/2012
AC GRIND & OVERLAY, BASE, MARKINGS, FENCING, ELECTRICAL
BURBANK - GLENDALE - PASADENA AIRPORT AUTHORITY
2627 HOLLYWOOD WAY
BURBANK, CA 91505
PEDRO BARRAGON
Telephone: 818/840 -8840
Original Contract Amount: $1,249,277 Final Contract Amount: $1,313,842
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Project Name /Number:
DEEP CREEK ROAD OVERLAY /10128904(11140C)
Start and Finish Dates:
3/01/2012- 3/30/2012
Project Description;
CRUB SEAL, COLD PLANE, AC OVERLAY, STRIPING
Agency Name: COUNTY OF SAN BERNARDINO DEPARTMENT OF PUBLIC WORKS
825 EAST 3 R0 STREET
SAN BERNARDINO, CA 92415
Contact Person; NIDHAM AL -REYES Telephone; 909- 387 -1831
Original Contract Amount: $778,000 Final Contract Amount: $605,995
Change in contract amount is due to items of work being deleted by the agency.
Project Name /Number: WILSHIRE / WESTERN FINAL PHASE /10128903(111390)
Start and Finish Dates 8/2011- 7/2012
Project Description: CITY OF LA, B- PERMIT
Agency Name: SOLAIR MARKETING, LLC
175 WEST JACKSON, SUITE 540
CHICAGO, IL 60604
Contact Person: JIM O'BRIEN
Telephone: 8051310 -8270
Original Contract Amount: $849,532 Final Contract Amount: $863,853
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Project Name /Number:
Start and Finish Dates:
Project Description:
Agency Name:
Contact Person:
MOVEMENT AREAS /10128902(11136C)
ONGOING— 12/2013
MAINTENANCE & REPAIR WORK ON T &M IN AIRCRAFT MOVEMENT AREAS
BURBANK- GLENDALE- PASADENA AIRPORT AUTHORITY
2800 CLYBOURN AVENUE
BURBANK, CA 91505
KAREN SEPULVEDA
Telephone: 8IB /565 -1305
Original Contract Amount: $250,000 Final ContractAmouni; $36,059
Change in contract amount is due to items of work being deleted by the agency.
Updated IULY 2014 13
STJI.LY- MILLER
CONTRAGTINC, CO.
BIDDER'S EXPERIENCE AND QUALIFICATIONS
Project Name /Number:
NON-MOVEMENT AREA (10128901(11135C)
Start and Finish Dates:
ONGOING — 12/2013
Project Description:
MAINTENANCE & REPAIR WORK ON T &M IN NON - MOVEMENT AREA
Agency Name:
BURBANK- GLENDALE- PASADENA AIRPORT AUTHORITY
2800 CLYBOURN AVENUE
BURBANK, CA 91505
Contact Person:
KAREN SEPULVEDA Telephone: 818/565 -1308
Original Contract Amount:
$200,000 Final Contract Amount: $5,724
Change In contract amount is due to items of work being deleted by the agency.
Project Name /Number: 2010 -11 FEDERAL OVERLAY PROGRAM /10128896(11127U)
Start and Finish Dates: 10/2011 - 1/2012
Project Description: AC GRIND AND OVERLAY
Agency Name: CITY OF SANTA CLARITA
23920 VALENCIA BOULEVARD, STE 300
SANTA CLARITA, CA 91355 -2196
Contact Person: 661/259 -2489
Telephone: 661/259 -2489
Original Contract Amount: $2,069,962 Final ContractAmount: $2,047,482
Change in contract amount is due to items of work being deleted by the agency.
Project Name /Number:
WHITEMAN AIRPORT AIRCRAFT RAMP /10128893(111230)
Start and Finish Dates:
2/2012- 9/2013
Project Description:
RECONSTRUCTION OF AIRCRAFT RAMP
Agency Name:
LOS ANGELES COUNTY DEPARTMENT OF PUBLIC WORKS
900 S. FREMOUNT AVENUE
ALHAMBRA, CA 91803
Contact Person: JOSEPH NGUYEN
Telephone: 626/458 -3166
Original Contract Amount: $944,698 Final Contract Amount: $1,038,210
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Project Name/Number:
Start and Finish Dates:
Project Description:
Agency Name:
Contact Person:
2011 ANNUAL CITYWIDE STREET RESURFACING PROJECT /10128890(11119U)
8/2011 - 212012
STREET RESURFACING
CITY OF CALABASAS
100 CIVIC CENTER WAY
CALABASAS, CA 91302 -3172
TATIANA HOLDEN
Telephone: 818/224 -1600
Original Contract Amoun t: $1,146,363 Final Contact Amount: $1,276,123
Change in original contract amount is due to extra work and /or contract change orders adding
work. .
Updated JULY 2014 14
SLJLI.X MILLER
CONTRACTINCi CO.
BIDDER'S EXPERIENCE AND QUALIFICATIONS
Project Name /Number: EAST AVENUE MASTER PLAN STORM DRAIN LINE 8 PROJECT /10128888(11117C)
Start and Finish Dates:
11/2011- 10/2012
Project Description:
AC GRIND & OVERLAY, PCC IMPRV., STORM DRAIN STRUCTURES, CONSTRUCT
Agency Name:
MANHOLES, RCP, FABRIC, LOOPS, STRIPING & MARKING, SWPPP
Agency Name:
CITY OF RANCHO CUCAMONGA
10500 CIVIL CENTER DRIVE
Contact Person:
RANCHO CUCAMONGA, CA 91729 -0807
Contact Person:
KENNETH FUNG Telephone: 909/477 -2700
Ortglnal Contract Amount.
$5,214,750 Final ContractAmount: $6,104,138
Change in original contract
amount is due to extra work and /or contract change orders adding
work.
ROADWAY AND WATERLINE IMPROVEMENT /10128884 (11112C)
Project Name /Number:
Start and Finish Dates:
Project Description:
Agency Name:
Contact Person:
SOUTHERN PACIFIC SLIP /10128887(11116C)
10/2011 - 5/2014
AC & PCC PAVEMENTS, PCC IMPRV., LANDSCAPE & IRRIGATION, SITE FURNISHINGS,
RETAINING WALLS, GUARDRAILS /RAILINGS, SIGNS
PORT OF LOS ANGELES
425 S. PALOS VERDES STREET
SAN PEDRO, CA 90731
MARLYS WHITE
Telephone: 310/732 -7690
Original Contract Amount: $5,694,700 Final Contract Amount. $6,160,508
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Project Name /Number: WEST OAK PARK AREA / 11115C
Start and Finish Dates:
7/2011- 3/2012
Project Description:
AC /ARHM GRIND & OVERLAY, CONCRETE IMPROVEMENTS, CRACK SEAL, LOOPS
Agency Name:
COUNTY OF VENTURA
800 SOUTH VICTORIA AVENUE
VENTURA, CA 92821
Contact Person:
PHIL NELSON I DOLORES Telephone: 805/654 -3984
MURPHY
Original Contract Amount.
$2,470,417 Final Contract Amount: $2,373,097
Change in contract amount
is due to items of work being deleted by the agency.
Project Name /Number:
ROADWAY AND WATERLINE IMPROVEMENT /10128884 (11112C)
Start and Finish Dates:
712011- 912012
Project Description:
ROADWAY AND WATERLINE
Agency Name:
CITY OF LOMITA
24300 NARBONNE AVENUE
LOMITA, CA 90717
Contact Person:
TOM SHAHBAZI Telephone: 310/325 -7110
Original ContractAmount:
$1,412,907 Final ConhactAmount $1,396,657
Change in contract amount
is due to !terns of work being deleted by the agency.
Updated JULY 2014
Is
SULLY-MILLER
CONTRACTING CO.
BIDDER'S EXPERIENCE AND QUALIFICATIONS
Project Name /Number:
FY 2010 -2011 RESIDENTAIL AREA 7 AND ARTERIAL ZONE AREA 5
Start and Finish Dates:
/10128880(11108C)
Start and Finish Dates:
7/2011 - 2/2012
Project Description:
AC PATCHING, GRIND AND OVERLAY, CAPE SEAL, SLURRY SEAL, MANHOLE
ADJUSTING
Agency Name;
CITY OF DIAMOND BAR
Contact Person;
21825 COPLEY DR.
Original Contract Amount:
DIAMOND BAR, CA 91765
Contact Person:
DAVID SLOAN Telephone: 9091839 -7000
Original Contract Amount: $1,8 -19,990 Final ContractAmount: $1,823,184
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Project Name /Number:
Start and Finish Dates:
Project Description;
Agency Name:
Contact Person;
BNSFAGS PROJECT- HOBARTYARD /10128878(11105C)
61MI- 8/2012
CONSTRUCTION OF CIVIL AND ELECTRICAL FEATURESIN SUPPORT OF THE AGS
HARDWARE, SITE DEMOLITION CIVIL, ELECTRICAL, STRUCTURAL, PAVING WORK
ASSOCIATED WITH AGS -
BNSF
2500 LOU MENK DR.,
FORT WORTH, TEXAS, 76131
CHRISTOPHER HARD
Telephone: . 817/352 -4114
Original Contract Amount: $10,036,878 Final Contract Amount: $10,466,761
Change in original contract amount is due to extra work and /or contract change orders add_ ing
work.
Project Name /Number;
WALN UT GROVE AVEN UE TO TUSH STREET/ 11111C
Start and Finish Dates:
07/2011. — 9/2011
Project Description:
STREET RESURFACING
Agency Name;
CITY OF ROSEMEAD
8838 E. VALLEY BOULEVARD
ROSEMEAD,CA 91770
Contact Person;
RAFAEL FAJARDO Telephone: 626/569 -2100
Original Contract Amount:
$1,109,950 Final Contract Amount.' $1,083,687
Change in contract amount
is due to items of work being deleted by the agency.
Updated JULY 2014 16
SULLY - MILLER
CONTRAC,TINC, CO.
BIDDER'S EXPERIENCE AND QUALIFICATIONS
Project Name /Number:
Start and Finish Dates:
Project Description:
Agency Name:
Contact Person.
STREET REHABILITATION PROJECT- REBID /10128881(11109C)
612011 - 1/2012
TRAFFIC CONTROL, GRINDING, AC, PCC, ADJUST MANHOLES & VALVES,
SIGNING /STRIPING /MARKING, LOOPS, UNDERGROUND, FABRIC DISPOSAL, FENCE
RELOCATION
CITY OF CHINO
1322 CENTRAL AVENUE
CHINO, CA 91710
NAGHMEHIMANI
Telephone: 909/464 -8367
Original Contract Amount: $1,813,849 Final Contract Amount: $1,868,794
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Project Name /Number: SAN BERNARDINO COUNTY NEAR NEEDLES FROM 0.4 MILE WEST OF WHALE
Updated JULY 2014 17
MOUNTAIN WASH BRIDGE TO 0.1 MILE WEST OF PARK MOABI ROAD
OVERCROSSING /10128874(11099U)
Start and Finish Dates:
5/2011- 3/2012
Project Description:
WIDEN FREEWAY, INSTALL PERMEABLE SUB BASE, EDGE DRAIN, GRIND &OVERLAY
FREEWAY -1.9 MILES IN LENGTH
Agency Name:
STATE OF CALIFORNIA, DEPARTMENT OF TRANSPORTATION
1727 30'" STREET
SACRAMENTO CA 95816
Contact Person:
DARCY DAVIS Telephone: 951/232 -6000
Original ContractAmount;
$7,193,800 Final Contract Amount: $8,262,201
Change in original contract
amount is due to extra work and /or contract change orders adding
work.
Project Name /Number:
RESIDENTIAL STREET REHABILITATION FY2010 -2011 & ANNUAL WATER MAIN
REPLACEMENT PROGRAM PROJECT /10128866(11090C)
Start and Finish Dates:
4/2011- 12/2011
Project Description;
SURVEY, SWPPP, PCC, AC, CRACK SEAL, ADJUST MANHOLES TO GRADE, TREE ROOT
PRUNE, STRIPING & MARKING, SLURRY SEAL
Agency Name:
CITY OF LA HABRA
201 E. LA HABRA BOULEVARD
LA HABRA, CA 90631
Contact Person:
SAM MAKAR, RE, SR. Telephone: 562/905 -9720
CIVIL ENGINEER
Original Contract Amount:
$3,535,885 Final Contract Amount: $4,029,145
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Updated JULY 2014 17
.._ V
SULLY - MILLER
CONTRACTINCY CO.
BIDDER'S EXPERIENCE AND QUALIFICATIONS
Project Name /Number, "G" AVENUE RAIL LEAD TRACK & CHANNEL PROJECT: PHASE II -LEAD TRACK
Project Name /Number:
Start and Finish Dates:
Project Description:
Agency Name:
Contact Person:
ELM ST. RESURFACING & WATERLINE REPLACEMENT /10128864(11087C)
03/2011- 0712011
CLEARING & GRUBBING, ADJUSTING MANHOLE & WATER VALVE & WATER METER,
SURVEY MONUMENT, PCC, CATCH BASIN, COLD MILLING, ARHM, AC, STRIPING &
MARKING & SIGNING, LOOP DETECTORS
CITY OF BREA
ONE CIVIC CENTER CIRCLE
BREA, CA 92821
BRIAN INGALLINEREA
Telephone.' 714/671 -4450
Original Contract Amount: $945,999 Final Contract Amount: $1,096,259 '
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Project Name /Number: FLORENCE AVENUE STREET REHABILITATION PROJECT/ 10085C
Start and Finish Dates:
CONSTRUCTION & DRAINAGE CHANNEL CONSTRUCTION /10I28865(11088C)
Start and Finish Dates:
0312011— 0212012
Project Description:
TRACK IMPRV., AC, FENCING, STRUCTURES, CAB, PCC, SWPPP, TREE, CLEAR &
Agency Name:
GRUB, EROSION CONTROL
Agency Name:
CITY OF HESPERIA
9700 SEVENTH AVENUE
Contact Person:
HESPERIA, CA 92345
Contact Person:
TINA SOUZA Telephone: 760/947 -1474
Original Contract Amount:
$4,622,722 Final Contract Amount.' $4,988,909
Change iri.original contract
amount is due to extra work and /or contract change orders adding
work.
Project Name /Number:
Start and Finish Dates:
Project Description:
Agency Name:
Contact Person:
ELM ST. RESURFACING & WATERLINE REPLACEMENT /10128864(11087C)
03/2011- 0712011
CLEARING & GRUBBING, ADJUSTING MANHOLE & WATER VALVE & WATER METER,
SURVEY MONUMENT, PCC, CATCH BASIN, COLD MILLING, ARHM, AC, STRIPING &
MARKING & SIGNING, LOOP DETECTORS
CITY OF BREA
ONE CIVIC CENTER CIRCLE
BREA, CA 92821
BRIAN INGALLINEREA
Telephone.' 714/671 -4450
Original Contract Amount: $945,999 Final Contract Amount: $1,096,259 '
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Project Name /Number: FLORENCE AVENUE STREET REHABILITATION PROJECT/ 10085C
Start and Finish Dates:
0612011- 07/2011
Project Description:
CLEARING & GRUBBING, EXCAVATION, COLD'MLL, ARHM, AC, MANHOLE
ADJUSTING, VALVE. /GAS ADJUSTMENT, STRIPING & MARKING, TRAFFIC LOOPS
Agency Name:
CITY OF BELL
6330 PINE AVENUE
BELL, CA 90201
Contact Person:
CARLOS ALVARADO Telephone: 626/960 -1889
Original Contract Amount.
$294,536 Final ContractAmount: $271,478
Change in contract amount
is due to items of work being deleted by the agency.
Updated JULY 2014 13
Eaali
SULLY- MILLER
CONTRAC-TINC, CO.
BIDDER`S EXPERIENCE AND QUALIFICATI ®NS
Project Name/Number:
Start and Finish Dates:
Project Description:
Agency Name;
LAV COLLEGE /10084C
02/2011 — 08/2011
RECONSTRUCT PARKING LOT
C�EVFRON ENERGY SOLUTIONS
150 E. COLORADO BLVD., STE: 360
PASADENA, CA 91105
Contact Person: WAYNE GRAHAM Telephone: 415/773 -4748
Original ContractAmountr $878,000 Final ContractAmount: $783,082
Change in contract amount is due to items of work being deleted by the agency.
Project Name /Number:
Start and Finish Dates:
Project Description:
Agency Name:
Contact Person:
2010 /11 OVERLAY PROJECT /10083C
02/2011 — 0712011
MOBILIZATION, TRAFFIC CONTROL, CRACK SEALING, AC, ARHM, MANHOLES,
LOOPS, THERMOPLASTIC STRIPING, PAVEMENT MARKERS, SIGNS, TREE WELL,
CROSS GUTTER, DETECTABLE WARNING SURFACE, TREES, WATERVALVE, PULL BOX
CITY OF CYPRESS
5275 ORANGE AVENUE
CYPRESS, CA 90630
NICK MANGKALAKIRI
Telephone: 714/229 -6729
Original Contract Amount: $2,198,000 Final Contract Amount: $1,790,853
Change in contract amount is due to items of work being deleted by the agency.
Project Name /Number: INNOV. VILLAGE /10079C
Start and Finish Dates: 01/2011 -- 05/2011
Project Description: AC PAVING, COLD MILL, CRACK FILL, ADJUST MANHOLE, LOOPS & PCC
Agency Name: CAL POLY -- POMONA FOUNDATION
3801 W. TEMPLE AVE
POMONA CA 901768
Contact Person: BRUYN BAVANS Telephone: 909/869 -6842
Original Contract Amount: $653,600 Final CcntractAmount: $693,203
Change in original contract amount is due to extra work and /or contract: change orders adding
work.
Updated JULY 2014 19
SULLY-MILLER
CONTRACTING CO.
BIDDER'S EXPERIENCE AND QUALIFICATI ®NS
Project Name /Number;
Start and Finish Dates:
Project Description:
Agency Name:
Contact Person:
26 STREET IMPROVEMENTS /10074U
02/2011 — 07/2011
EXCAVATION, CUT & DISPOSAL OF AC, GUTTER, COLD PLANE, COLD RECYCLING,
CMB, MANHOLES, STRIPING & MARKING, TRAFFIC SIGNAL, LOOPS, CONSTRUCTION
SIGNS
CITY OF VERNON
4305 SANTA FE AVENUE
VERNON, CA 90058
RAFAEL CONTRERAS
Telephone: 323/583 -8811
Original Contract Amount $ 873,212 Final Contract Amount: $899,429
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Project Name /Number: EMERALD AVENUE STREET IMPROVEMENTS / 100770
Start and Finish Dates. 2/2011- 3/2011
Project Descrlptlon:
AC OVER BASE, STRIPING & MARKING, CURBS, RAMPS, EXCAVATION TRAFFIC
CONTROL, COLD PLANE, CMB, MANHOLE ADJUSTING, LOOPS, SLOUGH WALLS
Agency Name:
CITY OF LA VERNE
3660 "D" STREET
LA VERNE CA 91750
Contact Person:
JASON WELDAY Telephone: 909/594 -9702
Original Contract Amount.
$226,000 Final Contract Amount: $487,575
Change in original contract
amount is due to extra work and /or contract change orders adding
work.
Project Name / Number:
ROSECRANS AVENUE & VALLEYVIEW AVENUE STREET IMPROVEMENTS /10072C
Start and Finish Dates:
0112011 - 03/2011
Project Description:
MOBILIZATION, EXCAVATION, CMB, COLD MILL, ARHM, AC, CURB & GUTTER,
ADJUST WATER VALVE & MANHOLES, STORM DRAIN, LOOPS, TRAFFIC CONTROL,
PAVEMENT MARKERS, SURVEY MONUMENTS
Agency Name:
CITY of SANTA FE SPRINGS
11710 TELEGRAPH ROAD
SANTA FE SPRINGS,. CA 90670
Contact Person:
RAFAEL CASILLAS Telephone: 562/868 -0511
Original Contract Amount:
$668,149 Final Contract Amount: $559,031
Change in contract amount is due to items of work being deleted by the agency.
Updaied JULY 2014 - 20
S T ILLY- .MILLER
CONTRACTING CO.
BIDDERS EXPERIENCE AND QUALIFICATIONS
Project Name /Number:
he .
LB ANNUAL 2010 /10128849(10071C)
Start and Finish Dates:
01./2011 - 11/2012
Project Description:
EMERGENCY REPAIRS
Agency Name:
CITY OF LONG BEACH
33 WEST OCEAN BLVD
LONG BEACH, CA 90802
Contact Person:
ROBERTSOLIS Telephone: 562/570 -5176
Original Contract Amount:
$2,000,000 Final Contract Amount: $2,210,831
Change in original contract
amount is due to extra work and /or contract change orders adding
work.
ProjectName/Number:
RAMPS A&B REHAB /10070C
Start and Finish Dates:
01/2011 — 07/2011
Project Description:
AC PAVING, PCC IMPRV., ELECTRICAL, FENCING, WHEEL STOPS, STRIPING /MARKING
Agency Name:
BURBANK- GLENDALE- PASADENA AIRPORT AUTHORITY
2800 N. CLYBOURN
BURBANK, CA 95105
Contact Person;
SAFA KAMAGAR Telephone; 818/565 -1305
Original Contract Amount:
$6,595,968 Final Contract Amount: $6,713,133
Change in original contract
amount is due to extra work and /or contract change orders adding
work.
Project Name /Number:
VALLEY BLVD. REHABILITATION PROJECT /10069U
Start and Finish Dates:
01/2011— 07/2011
Project Description;
SURVEY, AC GRIND & OVERLAY, CMB, PCC IMPRV., RCB CULVERT, ADJUST
UTILITIES, SIGNS /STRIPING /MARKING, LANDSCAPE & IRRIGATION
Agency Name:
CITY OF ALHAMBRA
111 SOUTH FIRST STREET
ALHAMBRA, CA 91801
Contact Person:
MELISSA RAMOS Telephone: 626/282 -5833
Original Contract Amount:
$1,851,617 Final Contract Amount, $1,871,827
Change in original contract
amount is due to extra work and /or contract change orders adding
Work.
Project Name /Number;
LAKE- ALAMEDA /10128845(7.0067U)
start and Finish Dates;
01/2011 - 12/2011
Project Description;
ACCESS PATH CONSTRUCTION
Agency Name:
LACDPW
900 SOUTH FREMOUNT AVE 8 T " FLOOR
ALHAMBRA CA 91802
Contact Person;
MARIO RODRIGUEZ Telephone: 6261458-5100
Original Contract Amount: $1,449,940 Final Contract Amount: $1,551,239
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Updated JULY 2014 21
SJJLLY- MILLER
CONTRACTING CO.
BIDDER'S EXPERIENCE AND QUALIFICATIONS
Project Name /Number. LAKEWOOD BOULEVARD IMPROVEMENTS - PHASE 3A 110128841(10063U)
start and Finish Dates;
10/2010 - 11/2011
Project Description:
AC PAVING, PCC IMPROVEMENT, CLEAR /GRUBBING, ELECTRICAL, IRRIGATION,
MANHOLE ADJUSTING, SIGNING, STRIPING & UNDERGROUND
Agency Name:
CITY OFDOWNEY
11111 BROOKSHIRE AVE., DOWNEY,CA 90241
Contact Person;
DESI GUTIERREZ Telephone; 562/622 -3468
Original Contract Amount:
$3,233,203 Final Contract Amount; $3,547,058
Change in original contract
amount is due to extra work and /or contract change orders adding
work.
Project Name /Number:
MAIN STREET - 2 N° STREET TO "H" AVE /10057C
Start and Finish Dates:
04/2011- 10/2011
Project Descriptions
COLD PLANE, AC, PCC, ADJUST UTILITY MANHOLES, REMOVE CATCH BASIN, CMB,
LOOPS, TRAFFIC SIGNAL, STRIPING & MARKING, SWPPP, SURVEY
Agency Name:
CITY OF BARSTOW
220 E. MOUNATAIN VIEW ST.
BARSTOW, CA 92311
Contact Person:
MARK ROWAN Telephone; 760/241 -6146
Original Contract Amount:
$1,645,609 Final Contract Amount: $1,869,560
Change in original contract
amount is due to extra work and /or contract change orders adding
work.
Project Name /Number:
RESIDENTIAL STREETS IMPROVEMENTS PROJECT %10128832(10053C)
Start and Finish Dates;
08/2010 - 04/2011
Project Description:
SURVEY /MONUMENTS, PCC, CMB, TRUNCATED DOMES, CAPE SESAL, CHIP SEAL,
SLURRY SEAL TYPE I1, AC, CRACK ROUTING & SEALING, ADJUST MANHOLES &
VALVES, ROOT PRUNE, STRIPING & MARKING & SIGNS
Agency Name:
CITY OF RANCHO PALOS VERDES
30940 HAWTHORNE BLD.
RANCHO PALOS VERDES, CA 90275 -5391
Contact Person:
CHUCK STEPHAN Telephone: 310/544 -5252
Original Contract Amount.
$1,218,105 Final Contract Amount: $1,275,338
Change in original contract
amount is due to extra work and /or contract change orders adding
work.
Updated JULY 2014 22
S ILLY -M II.I,ER
CONTRACTING CO.
BIDDER`S EXPERIENCE AND QUALIFICATIONS
Project Name /Number: AVE H, MOUNTAIN VIEW, 2ND AVE, COUNTY CLUB /10051C
Start and Finish Dates: 0912010 — 04/2011
Project Description:
AC, UTILITY MANHOLES, CMB, PCC TRAFFIC SIGNAL, LOOPS, STRIPING &
Project Description:
MARKING, SIGNAGE, ADJUST WATER VALVES & GAS VALVES, REPAIR EXISTING
SEWER LINE
Agency Name:
CITY OF BARSTOW
220 E. MOUNTAAN VIEW ST
Agency Name:
BARSTOW, CA 92311
Contact Person:
MARK ROWAN Telephone: 760/241 -6146
original Contract Amount.
$1,523,000 Final Contract Amount: $1,803,836
Change in original contract
amount is due to extra work and /or contract change orders adding
work.
$3,445,395 Final Contract Amount: $3,910,596
Project Name/Number:
Start and Finish Dates:
Project Description:
Agency Name:
Contact Person:
VARIOUS STREETS, VIRGINIA WAY ETC /10048C
02/2011 - 12/2011
AC, PCC, CATCH BASIN, UTILITY MANHOLES, LOOPS, STRIPING & MARKING,
SIGNAGE
CITY OF BARSTOW
220 E. MOUNTAIN VIEW ST
BARSTOW, CA 92311
MARK ROWAN .
Telephone: 760/241 -6146
Original Contract Amount: $1,124,134 Final Contract Amount: $1,365,121
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Project Name /Number: MEADOWPASS ROAD IMPROVEMENTS /1o047C
Start and Finish Dates:
09/2010 — 03/2011
Project Description:
CLEARING & GRUBBING, CAB, AC, PCC,.ADJUST VALVE & MANHOLE TO GRADE,
STRIPING /MARKING /SIGNS, STREET LIGHTING, RETAINING WALL, MASONRY WALL,
PIPE LANDSCAPE & IRRIGATION, LOOP DETECTORS, STROM DRAIN, CATCH BASIN,
STRUCTURES, RCP
Agency Name:
CITY OF WALNUT
21201 LA PUENTE ROAD
WALNUT, CA 91789
Contact Person:
JASON WELDAY Telephone: 909/595 -6095
Orlgina/ContractAmount:
$3,445,395 Final Contract Amount: $3,910,596
Change in original contract
amount is due to extra work and /or contract change orders adding
Work.
Updated JULY 2014 33
SULLY- MILLFR
CONTRACTING CO.
BIDDER'S EXPERIENCE AND QUALIEICATI®NS
Project Name /Number:
Start and Finish Dates:
Project Description:
Agency Name:
Contact Person:
ARMORY ROAD /10046C
09/2010 — 01/2011
AC EMULSION, ADJUST MANHOLE, SURVEY, STRIPING /MARKING /SIGNS, PCC, LOOPS
CITY OF BARSTDW
220 E. MOUNTAIN VIEW ST
BARSTOW, CA 92311
WILLIAM HENDERSON
Telephone; 760/255 -5157
Original Contract Amount: $782,765 Final Contract Amount: $786,834
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Project Name /Number:
Start and Finish Dates:
Project Description:
Agency Name:
Contact Person:
ABBOTT ROAD STREET IMPROVEMENTS / 10043U
0912010 12/2010
AC GRIND & OVERLAY, PCC IMPRV., ADJUST UTILITIES, ELECTRICAL, ROOT
PRUNING /TREE TRIMMING/TREE REMOVAL, STRIPING & MARKING, STORM DRAIN
STRUCTURES
CITY OF LYNWOOD
11330 BULLIS ROAD
LYNWOOD, CA 90262
PAUL NGUYEN
Telephone: 310/603 -0220
Original Contract Amount: $1,267,754 Final Contract Amount: $1,601,267
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Project Name /Number: DAISY AVENUE /10042C
Start and Rnlsh Dates: 09/2010 — 0312011
Project Description: PULVERIZE, CLEAR & GRUB, BOLLARDS REMOVAL, REFURBISH BOLLARDS, TREE &
STUMP REMOVAL, TREE PRUNE, ADJUST MANHOLES & VALVES, ELECTRICAL,
ADJUST SURVEY MONUMENTS, CONCRETE IMPRV., GRANITE, AC, FIREHYDRANT
MARKERS, STRIPING &. MARKING, LANDSCAPE, UNDERGROUND
Agency Name: CITY OF LONG BEACH
333 WEST OCEAN BLVD
LONG BEACH, CA 90802
Contact Person: ERIC LOWE Telephone: 562/570 -5176
Original Contract Amount: $1,312,217 Final Contract Amount: $1,362,406
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Updated JULY 2014 21t
SULLY - MILLER
CONTRACTING CO.
BIDDERS EXPERIENCE AND QUALIFICATIONS
Project Name /Number:
STATE STREET /10037U
Start and Finish Dates:
08/2010 — 03/2011
Project Descrlptlon:
REPAIR OF PCC PAVEMENT AND SW /RAMPS /DW
Agency Name:
CITY OF SOUTH GATE
8650 CALIFORNIA AVENUE
SOUTH GATE, CA 90280
Contact Person: DANIEL GRUEZO Telephone: 323/357 -9657
Original Contract Amount: $1,299,973 Final Contract Amount: $1,546,185
Change in original contract amount is due to extra work and /or contract change orders adding
work.
Updated ]ULY 2011 25
ImMul
SECTION 3
NON-COLLUSION AFFIDAVIT
Ell
CBF-10
BIDDER: Sully Miller ContractincL
NON-COLLUSION AFFIDAVIT
In accordance with Public Contract Code Section 7405, the undersigned, being first duly
sworn, deposes and says that he or she holds the posiiion listed belowwi,th the bidder, `the
party making the foregoing bid, that the bid is not made in the interest of, or on behalf of, any
undisclosed person, partnership, company, association, organization, or corporation; that the
bid is geriuine and not collusive or sham; that the bidder has not directly or indirectly induced
or solicited any other bidder to put in a false or sham bid, and has not directly or indirectly
colluded, conspired, connived, or agreed with any bidder or anyone else to put in a sham
bid, orthat anyone shall refrain from bidding; thatthe bidderhas not in any manner, directly
or indirectly, sought by agreement, communication, or conference with anyone to fixthe bid
price of the bidder or any other bidder, or to fix any overhead, profit, or cost element of the
bid price, or of that of any other bidder, or to secure any advantage against the public body
awarding the contract of anyone interested in the proposed contract; that all statements
contained In the bid are true; and, further, that the bidder has not, directly or indirectly,
submitted his or herbid price or anybreakdown thereof, orthe contents thereof, ordivulged
Information or data relative thereto, or paid, and will not pay, any fee to any corporation,
partnership, company association, organization, bid depository, orto any member or agent
thereof to effectuate a collusive or sham bid.
Signature
d�nnis Gansen
Typed or Printed Name
Assistant Secretary
Title
Sully Miller Contracting
Bidder
Subscribed and sworn before me
This 4th day of February 1 2015
Please see attached Jurat (Seal)
Notary Public In and for
the State of California
My Commission Expires:
CBF -44
CALIFORNIA JURAT WITH AFFIANT STATEMENT
CIVIL CODE § 8202
® See Attached Document (Notary to cross out lines 1 -6 below
See Statement Below (Lines 1 -6 to be completed only by document signer, not Notary
Signature of Document Signer No. 1 Signature of Document Signer No, 2
A notarypublic or other officer completing this certificate verifies only the identity of the Individual who signed the document to which this
certificate is attached, and not the truthfulness, accuracy, or validity of that document
State of California Subscribed and sworn to (or affirmed) before me
On this 3rd day of February, 2015 by:
County of Orange Dennis Gansen
1.
2.
ADRIANA 0. TREJO
Commission # 1%1263 Proved to me on the basjs of satisfactory evidence to be
O Notary Public - California z the person who appea ik Yore me.
Orange county My Comm. Expires Oct 13, 2D16
Signature
C. Trejo,
Place Notary Seal Above
OPTIONAL
Though this sectlon is optional, completing this information can deter alteration of the document or fraudulent reattachment of this form to an
unintended document.
Description of Attached Document
Title or Type of Document: Non- Collusion Affidavit - Si Page
Document Date: February 3 2 015 Number of Pages 1
Signer(s) Other Than Named Above:
Signer Represents: SULLY - MILLER CONTRACTING COM PANY
RESOLUTION NO. 2015 -13
A RESOLUTION OF THE ROSEMEAD, CALIFORNIA CITY COUNCIL
APPROPRIATING ADDITIONAL FUNDS FROM THE
CITY'S MEASURE R FUND FOR THE
MONTEBELLO BOULEVARD /TOWNE CENTER DRIVE RESURFACING
MEDIAN AND LANDSCAPE ENHANCEMENTS PROJECT
WHEREAS, appropriations are the legal authority for a City to spend its funds; and
WHEREAS, from time to time it is necessary to amend the budget with additional
appropriations; and
WHEREAS, the City desires rehabilitate and improve the roadways of Montebello
Boulevard and Town Center Drive and the adjacent medians in this area; and
WHEREAS, the roadway rehabilitation project is funded through proceeds from
Measure R and Prop C funds and currently has a budget amount of $600,000; and
WHEREAS, the total cost for the construction of this project, as proposed, will not
exceed $686,700, which is $86,700.00 more than currently budgeted; and
WHEREAS, the Measure R Fund has a balance of approximately $200,000 of which
the additional funding could be made available for this project.
NOW THEREFORE, $86,700 is appropriated in the Capital Improvement Programs
for Expenditures related to the Montebello Boulevard/Towne Center Drive Resurfacing,
Median and Landscape Enhancements Project as defined below:
Fund
Organization
Account Project Description
Amount
Appropriation
301
6005
5395 21018 Construction
$ 86,700.00
Transfer (Memo)
225
0000
5960 Transfer Out
<$ 86,700.00>
301
0000
4860 Transfer In
$ 86,700.00
The additional appropriation is made a part of the approved FY 2014 -15 budget as though
it were a part of the initial budget fully set forth.
PASSED, APPROVED and ADOPTED this 24 day of February 2015.
William Alarcon, Mayor
ATTEST:
Gloria Molleda, City Clerk