Loading...
CC - Item 4E - Traffic Signal Improvements Project - Mission Drive and Walnut Grove AvenueROSEMEAD CITY COUNCIL STAFF REPORT TO: THE HONORABLE MAYOR AND CITY COUNCIL FROM: JEFF ALLRED, CITY MANAGER DATE: MAY 26, 2015 SUBJECT: TRAFFIC SIGNAL IMPROVEMENTS PROJECT- MISSION DRIVE AND WALNUT GROVE AVENUE SUMMARY Included in the proposed Fiscal Year 2015 -16 Capital Improvement Program (CIP) Budget is a project that will undertake improvements to the traffic signal at the intersection of Walnut Grove Avenue and Mission Drive. The existing conduit is undersized causing shorts in the traffic signal wiring, which occasionally results in traffic signal outages. These shorts and outages are unpredictable which has led to signal outages and frequent repair work. It has been determined that the entire conduit needs to be replaced with a larger conduit to ensure proper operation of the signal and plans and specifications have been developed for the project. Although funding will not be available until July 1, 2015 as a part of the 2015 -16 CIP Budget, staff has conducted a public bid for this project and is ready for the contractor to mobilize so that work may begin in early July. Staff Recommendation It is recommended that the City Council: 1. Approved the plans and specifications for the Traffic Signal Improvements Project, Mission Drive and Walnut Grove Avenue; and. 2. Award a contract to California Professional Engineering, Inc. in an amount of $97,887.99 and authorize a contingency amount of $15,000.00 (approximately 15 %) to cover the costs of any unforeseen construction expenses. DISCUSSION Ongoing maintenance issues with the traffic signal at the intersection of Walnut Grove Avenue and Mission Drive have caused staff to determine that the existing conduit is undersized. The undersized conduit causes wiring in the traffic signal to short which results in the traffic signal malfunctioning. It has been determined that in order for the signal to operate properly, the existing conduit must be replaced with a larger conduit. Additionally, while the contractor is performing these upgrades, the project includes the installation of a video detection system and other traffic signal improvements. ITEM NUMBER: �� City Council Meeting • May 26,2015 Page2of2 A Notice Inviting Bids was published in local newspapers and trade publications on April 30th and May 7th, 2015. Sealed bids were received in the Office of the City Clerk until 10:30 a.m. on Wednesday, May 13, 2015. At 11:00 a.m. on May 13, 2015, the City Clerk publicly opened and read two (2) sealed bids with the following result: Rank Bidder Location Bid Amount 1 California Professional La Puente, CA $ 99,887.99 Engineering, Inc. 2 PTM General Engineering Riverside, CA $ 105,999.00 Services, Inc. Staff has reviewed the proposals, backgrounds, and recent projects of California Professional Engineering, Inc. and has found them to be the lowest responsive bidder to complete this project. California Professional Engineering, Inc. .has performed similar projects for a number of public agencies including the Cities of Downey and La Puente and the County of Los Angeles. FINANCIAL REVIEW Funding for this project is included in the proposed Fiscal Year 2015-16 Capital • Improvement Program Budget in the amount of $150,000. The source of the funding is the Street Lighting District Funds. PUBLIC NOTICE PROCESS This item has been noticed through the regular agenda notification process. Prep- ed By: Prepared By: afael M. Fajardo, P.E. Sean Sullivan City Engineer Acting Public Works Manager Submitted By: Matt awkes orth Assistant City Manager/Acting Director of Public Works Attachments: A. Plans and Specifications (Available in the City Clerk's Office) B. Bid Analysis PUBLIC WORKS SERVICE DEPARTMENT/ENGINEERING DIVISION 5/18/2015 CITY OF ROSEMEAD TRAFFIC SIGNAL IMPROVEMENTS PROJECT-WALNUT GROVE AVENUE AND MISS!, BID ANALYSIS BID SUBMITTAL: MAY 13 2015 CALIFORNIA PROFESSIONAL ENGINEERING,INC. #1 BASE BID PRICE ITEM DESCRIPTION QTY UNIT UNIT PRICE TOTAL 1 CLEARING AND GRUBBING PER PLANS/SPECS. 1.00 LS 1,000.00 $ 1,000.00 2 DISPOSAL OF WASTE MATERIALS 1.00 LS 1,000.00 $ 1,000.00 CONSTRUCT TRAFFIC SIGNAL IMPROVEMENTS AT MISSION DRIVE AND 3 WALNUT GROVE AVENUE PER PLANS AND SPECIFICATIONS COMPLETE 1.00 LS 97,887.99 $ 97,887.99 TOTAL BASE BID PRICE $ 99,887.99 PTM GENERAL ENGINEERING SERVICES,INC. #2 BASE BID PRICE ITEM DESCRIPTION QTY UNIT UNIT PRICE TOTAL 1 CLEARING AND GRUBBING PER PLANS/SPECS. 1.00 LS 7,000.00 $ 7,000.00 2 DISPOSAL OF WASTE MATERIALS 1.00 LS 3,000.00 $ 3,000.00 CONSTRUCT TRAFFIC SIGNAL IMPROVEMENTS AT MISSION DRIVE AND 3 WALNUT GROVE AVENUE PER PLANS AND SPECIFICATIONS COMPLETE 1.00 LS 95,999.00 $ 95,999.00 TOTAL BASE BID PRICE $ 105,999.00 PAGE 1