TO: HONORABLE CHAIRMAN AND COMMISSION MEMBERS
FROM: OLIVER CHI, EXECUTIVE DIRECTOR/,.J~:rtu;
DATE: JULY 8, 2008 vv
SUBJECT: ROSEMEAD PARK TRAIL ENHANCEMENT PROJECT -
AWARD OF CONTRACT
SUMMARY
At its June 10th meeting, the City Council approved plans and specifications and
authorized staff to solicit bids for the completion of a fitness trail and recreational
enhancements at Rosemead Park. This project will include the addition of a jogging
trail, recreational equipment, and a tai-chi exercise pad. On June 30, 2008, bids were
received and reviewed for the project.
Staff Recommendation
Staff recommends that the Community Development Commission award a contract to
lowest responsive bidder, The Nazerian Group, and authorize the Chairman and the
City Clerk to execute the contract.
DISCUSSION
Rosemead Park is the City's largest and, arguably, most used park. The Park is located
on the northwest corner of Mission Drive and Encinita Avenue. It abuts a neighborhood
to the east and is bordered by Rosemead High School on the west and Encinita
Elementary School on the north. Rosemead Park houses City preschool classes and
swim programs, youth and adult sports activities, numerous picnic shelters, basketball
courts, and three playgrounds - all of which are heavily used by the community.
The proposed Park enhancements included as part of this project will include the
creation of a'/ mile jogging/walking trail, the addition of a rubberized asphalt concrete
pad for tai-chi and volleyball participants, and the addition of new stationary exercise
units. If approved, staff will authorize the contractor to begin construction on July 14th
At 2:00 PM on June 30, 2008, the City Clerk opened and read the following total base
bid prices for this project:
APPROVED FOR CITY COUNCIL AGENDA:
•
Community Development Commission Meeting
July 8, 2008
Page 2 of 3
Bidder
Low Horizons Construction
2 The Nazerian Group
3 Y&M Construction
Total Base Bid Price
$264,000
$317,450
$339,985
* Denotes Irregularity Contained in Bid Proposal Documents
The low bidder Horizons Construction possesses a Building Contractors Class B license
as specified in the contract documents. In reviewing their bid, staff found that Horizons
did not acknowledge addenda issued by staff. Further, Horizons did not provide a list of
subcontractors as required in the bid specifications.
The second bidder, The Nazerian Group, possesses a Building Contractors Class B
license as specified in the contract documents. The Nazerian Group is a 7 year old firm
that has satisfactorily completed construction projects for other agencies, including
Pasadena Unified School District, the City of Glendale, and Alhambra Unified School
District.
The Contractor must complete all work within 35 consecutive working days. Liquidated
damages are $250 per calendar day.
FINANCIAL REVIEW
The total appropriation needed to award this project is $428,557, which includes
project/construction management fees and a contingency amount for unforeseen
construction expenses. Funding for this project was approved by your City Council as
part of the City's FY 2008-09 Capital Improvement Program Budget.
ENVIRONMENTAL REVIEW
The project is categorically exempt from the California Environmental Quality Act
(CEQA) pursuant to Section 15301 (a) of the CEQA Implementing Guidelines. This
exemption covers building alterations involving partitions, plumbing, electrical, etc.
Prepared by:
Chris Marcarello
Deputy Public Works Director
! •
Community Development Commission Meeting
July 8, 2008
Page 3 of 3
Sub ed by:
Bri aeki
Assistant City Manager
Attachments:
(1) Bid Summary/Comments
(2) Bid Proposals
(3) Contract
(4) Dunn and Bradstreet Reports for The Nazerian Group and Y&M Construction
(5) City Council Agenda Report June 10, 2008