CC - Item 4F - Rosemead Skate Plaza - Award of Contract E M f S 4 r ° ROSEMEAD CITY COUNCIL CIVIC PRIDE STAFF REPORT 71,.M7 NCDRPpRATED.„9 TO: THE HONORABLE MAYOR AND CITY COUNCIL FROM: JEFF ALLRED, CITY MANAGER /4 DATE: MARCH 22, 2016. SUBJECT: ROSEMEAD SKATE PLAZA (PROJECT NO. 41009) — AWARD OF CONTRACT SUMMARY As a part of the adopted Fiscal Year 2015-16 Capital Improvement Project (FY15-16 CI P) Budget, the City Council approved Project No. 41009, which consists of constructing a skate plaza adjacent to the Aquatic Center, inside Rosemead Park. The City has completed the construction documents, and subsequently solicited competitive bids for the Rosemead Skate Plaza Project. On February 24, 2016, the City received and publicly opened 6 bids; and the apparent lowest bidder was PK Construction. The City is now ready to consider awarding a construction contract to the lowest responsive bidder. Staff Recommendation It is recommended that the City Council: 1. Approve the plans and specifications for Project 41009, Rosemead Skate Plaza. 2. Waive the minor irregularities in PK Construction's bid. 3. Award the construction contract to PK Construction in the amount of $381,999, and authorize a construction contingency of$57,301 (15%), for a total of$439,000. 4. Approve Resolution No. 2016-12 allocating an additional $187,000 in Redevelopment Bond Fund for the Project DISCUSSION On November 10, 2014, the City Council directed staff to proceed with developing a skate plaza adjacent to the Aquatic Center, inside the Rosemead Park. On April 28, 2015, the City Council approved a contract with Spohn Ranch Skateparks, for conducting public workshops and preparing design plans. On June 17, 2015 and July 22, 2015, the City conducted public workshops, and subsequently incorporated community inputs into the skate plaza design concept. ITEM NO. 4.F APPROVED FOR CITY COUNCIL AGENDA: City Council Meeting March 22,2016. Page 2 of 5 The Rosemead Skate Plaza is approximately 10,000 square feet in size, located immediately to the east of the Aquatic Center in Rosemead Park. The design capitalizes on the existing natural topography at the site to minimize major earthwork, and includes a variety of street features: steps, handrails, benches, ramps, etc. Exhibits "A" and "B" illustrates the location and the design concept of the Skate Plaza Project. On August 11, 2015, the City Council approved the Skate Plaza design concept, and authorized the City Manager to execute a contract with "Helping Governments Across the County Buy" (HGACBuy) Program in an amount not to exceed $475,000, for construction of the Project. Thereafter, the City Attorney opined that through the cooperative purchasing program, the City is only permitted to purchase the precast (prefabricated) skate plaza elements (e.g. hub ledge, stairs, grind rails, ramps, etc.). The construction portion (e.g. site work, grading, concrete, drainage, etc.) must be competitively bid in accordance with the Public Contract Code. Therefore, the City proceeded with HGACBuy only for purchasing the precast skate plaza elements, in the amount of $166,207. Under the HGACBuy Program, Spohn Ranch is the certified vendor, who is responsible for fabricating and delivering the precast elements to the site for installation. In December 2015, the City completed the bid documents, and subsequently advertised the Project for construction bids. On February 24, 2016, the City publicly received and opened six (6) bids, as summarized below. RANK CONTRACTOR LOCATION Total Bid 1 PK Construction Altadena, CA $381,999 2 Spohn Ranch Inc. Los Angeles, CA $508,609 3 Y. Ko Construction Co. Inc. Woodland Hills, CA $512,000 4 Monet Construction Inc. Glendale, CA $513,942(' 5 Minco Construction Gardena, CA $557,200 6 E C Construction S. El Monte, CA $606,580 Notes: (1' Bid price of $514,942 was adjusted to S513,942, to correct arithmetic error. The apparent low bidder was PK Construction ("PK") of Altadena California, with a bid of $318,999; that is approximately $126,610 lower than the next lowest bid. The bid price also includes an alternate bid item for wrought iron fencing in the amount of $2,475. If awarded by the City Council, construction is anticipated to begin in April 2016, with sufficient progress in August 2016 ready for the delivery of the precast skate plaza elements. Ordering the precast elements in advance is expected to result in significant time and cost savings (e.g. no mark up from general contractor). City Council Meeting March 22,2016. Page 3 of 5 BID SUBMITAL ANALYSIS On March 1, 2016, the City received a letter from Spohn Ranch (2nd Lowest Bidder) protesting that the lowest bid submitted by PK Construction is either non-responsive or non-responsible. The specifics of the protest, along with the City's responses on March 8, 2016, are summarized below. 1. Not Responsive. A. Protest: PK did not adequately respond to Section 3.1 ("List categories of work that your organization normally performs with its own forces."). City Response: PK provided information as requested by Section 3.1, namely "Concrete, forming, placing, grading". This is a minor irregularity which may be waived by the City Council because it does not impact the amount of the PK bid and does not give PK a competitive advantage over other bidders. B. Protest: PK did not respond to Section 3.6 which asks for a separate sheet listing the construction experience and present commitments of the key individuals of your organization. City Response: While this information was requested by Section 3.6, the lack of this information is a minor irregularity which may be waived because this omission does not impact the amount of the bid or give the bidder a competitive advantage over other bidders. 2. Lack of Experience. Protest: PK did not provide references for similar work as sought by Section 5. City Response: PK provided 4 references sufficient to satisfy Section 5. 3. Lack of Responsibility. Protest: PK is not a responsible contractor pursuant to Paragraph 30 "Responsibility Criteria" of the Bid Document. City Response: PK is a "Responsible Bidder" as defined by Public Contract Code Section 1103. 4. Sham Bid. Protest: The bid by PK is a sham bid because it is 75% of the next lowest bid. City Response: There is often a wide range of bids and a low bid being 75% of the next lowest bid does not make the low bid a sham bid. City Council Meeting March 22,2016. Page 4 of 5 The City has reviewed PK Construction's bid submittal, and confirmed that it has the necessary construction license(s) (A-General Engineering Construction, B-General Building Construction, and C8-Concrete), which are in good standing and relevant to the required work. Based on reference checks, PK has satisfactorily completed projects for the Cities of Pasadena, Alhambra, and Manhattan Beach. PK's bid is also $166,207 below the 2nd lowest bid. For the foregoing reasons, City staff recommends that the City Council waive these minor irregularities in the bid of PK Construction and award the contract to PK Construction. FINANCIAL REVIEW The FY 15-16 CIP Budget contains $500,000 in Redevelopment Bond Funds for Project No. 41009. Of this amount, a total of $188,207 has been expended ($22,000 for design, and $166,207 for precast skate plaza elements), with a balance of $311,793 available for the construction phase. The total estimated cost for the construction phase (including contingencies, contract administration, design support, and inspection) is $498,793, as tabulated below. Therefore, an additional allocation of $187,000 from the Redevelopment Bond Fund is required to complete the Project. The City has previously set aside a total of $1,878,500 in Redevelopment Bond Fund for the Rosemead Community Recreation Center (RCRC) Project. This Project is substantially complete, and a net savings of S678,500 in Redevelopment Bond Fund can be expected from not constructing a new building next to the RCRC. A portion of this savings can be reallocated to the Rosemead Park Project (for the Skate Plaza). ESTIMATED PROJECT COST Bid Amount $381,999 Contingencies (15%): $57,301 Total Contract Work: $439,300 Contract Administration $59,493 (Inspection, Testing, Design Support, and Staff) Total Project Cost: $498,793 PROJECT FUNDING FY 15-16 CIP Budget Balance (Redevelopment Bond Fund) $311,793 Additional Appropriation (Redevelopment Bond Fund) $187,000 Total Project Funding: $498,793 City Council Meeting March 22,2016. Page 5 of 5 PUBLIC NOTICE PROCESS This item has been noticed through the regular agenda notification process. Prepared by: Submitted by: Rafael M. Fajardo Anthony a Fajardo Y City Engineer Interim Public Works Director Or ilk 1 / Curtis Cannon Special Projects Manager Attachments: (1) Exhibit "A" - Vicinity Map (2) Exhibit "B" - Skate Plaza Rendering (3) Resolution 2016-12 (4) Bid Summary (5) Project Specifications (Available in City Clerk's Office) I- 0 1.1.1 CL cz. LJ-1 0 t2 LL1 H / CO a < ;,. - ,la . „ , ,47--.;IA- - . •,,, ,N , . . . . „ - , LL1 \,',,. .".i104, - • • ' - ._ :..- !,. - . 2 „.-- , .c, ,.L. ,,,....■ . ' . .._ , . LL1 , r 7, 6 * 4 0 '• ----, .. - I I 1 't' 'T .•. ' ,11- .. \ • .1 .. • . . • •... . . . . , ....., il ... .,.....: . : ,... ., u..1 1.,....,., = ... _.. ..„ . . fx .L • ., .10e: rz o 'fittli ._. 14. . ,.. , I >< '. ---- - .*. . . •.. . ,---- --1, . .....n, .,. LLI ,-- ......t.; 3AV VIA101 -LI', -" ' ' •".:4, mi:us, tm.nai 1 mi - rip . ' , ,..-.,..-,,,.: !. : •,...: . - , . . , ' ---, • , . 4 i I i . , . _. -.,. . . '..• -4, . . . 1 ,C4.1 1 - ' ''!; ,o•re - ELI alliii 11111 ‘ I- Nod, 0 -ex I- o LL1 'AC,. ■ --__ a , .,_ . .. - -; ' j,,•:, 14_ -- X -f, u_ 0 < • 3- '9• . , . . it 4 ..- 1 C./) ,4,1 0.. i CO) ; ' .,'■ .i. ■,:. -`. IC. ' _ l . ____-1 , ..... • z „ . . •$ 0 < 4 A - . . ' i■ fa■ . . .•'el / 11 1"t: ... ,1 +41" '-`,,.'Al 1114 1.-"N . i i ___/ ... , vi t . ' , I CI_ ___ , . . „ ,. 1 !: • .' 1— ' i ` 1 . < • i; ' •.. Cf) V .0. . : -.• k, 1 . . ...' :.4.....Ar :# ‘, t. • ..,7 < t • td ' U..1 V. • ''- : Cf) -7 • ', 0 , . I . , . .. . ; / it . ) , \ , . I , . . . . I I , . I' i . i . . el ■I . . . . I., i 1 li 1 i,, ______ i": 1 : _ I • , .e.....:,. - .. . ....., n 0 , . . t .r> . , 'f • rc' 4 .I LW RESOLUTION NO. 2016-12 A RESOLUTION OF THE ROSEMEAD, CALIFORNIA CITY COUNCIL APPROPRIATING ADDITIONAL FUNDS FROM THE REDEVELOPMENT BOND FUNDS FOR THE ROSEMEAD SKATE PLAZA PROJECT WHEREAS, appropriations are the legal authority for a City to spend its funds; and WHEREAS, from time to time it is necessary to amend the budget with additional appropriations; and WHEREAS, the City desires the construction of Rosemead Skate Plaza at Rosemead Park; and WHEREAS, the Rosemead Skate Plaza Project is funded through proceeds from Redevelopment Bond funds and currently has a budget amount of $311,793; and WHEREAS, the total cost for the construction of this project, as proposed, will not exceed $498,793, which is $187,000 more than currently budgeted; and NOW THEREFORE, $187,000 is appropriated in the Capital Improvement Programs for Expenditures related to the Rosemead Skate Plaza Project as defined below: Fund Organization Account Project Description Amount Appropriation 301 6005 5395 Construction $ 187,000 Transfer (Memo) 315 0000 5960 Transfer Out <$ 187,000> 301 0000 4860 Transfer In $ 187,000 The additional appropriation is made a part of the approved FY 2015-16 budgets as though it were a part of the initial budget fully set forth. PASSED, APPROVED and ADOPTED this 22nd day of March 2016. Margaret Clark, Mayor ATTEST: Carol Cowley, City Clerk PUBLIC WORKS SERVICE DEPARTMENT/ENGINEERING DIVISION CITY OF ROSEMEAD ROSEMEAD SKATE PARK PROJECT PROJECT No.41009 BID ANALYSIS BID OPENING:FEBRUARY 24,2016 AT 11:00 AM PK Construction #1 BASE BID PRICE ITEM DESCRIPTION 1 CLEARING AND GRUBBING. 1.00 LS $ 45,000.00 $ 45,000.00 2 DISPOSAL OF WASTE MATERIALS. 1.00 LS $ 12,360.00 $ 12,360.00 CONSTRUCTROSEMEAD SKATE-PARK PER PLANS AND 3 SPECIFICATIONS COMPLETE. 1.00 LS $ 322,164.00 $ 322,164.00 TOTAL BASE BID PRICE $ 379,524.00 ALTERNATE BID ITEM No.1 ,.... TOTAL 4 INSTALL GUARD RAIL AS INDICATED ON THE PLANS 150.00 LF $ 16 50 S 2,475.00 TOTAL ALTERNATE BID PRICE $ 2,476.00 TOTAL BASE&ALTERNATE BID PRICE $ 381,999.00 Spohn Ranch,Inc. #2 BASE BID PRICE 1I3i[I1,g 1 'CLEARING AND GRUBBING. 1.00 LS $ 4,384.00 S 4,384.00 2 DISPOSAL OF WASTE MATERIALS. 1.00 LS $ 7,000.00 $ 7,000.00 CONSTRUCT ROSEMEAD SKATE PARK PER PLANS AND 3 SPECIFICATIONS COMPLETE. 1.00 LS $ 478,475.00 $ 478,475.00 TOTAL BASE BID PRICE $ 489,859.00 ALTERNATE BID ITEM No.1 ITEM ;DESCRIPTION QTY UNIT UNIT PRICE TOTAL • Ir 4 INSTALL GUARD RAIL AS INDICATED ON THE PLANS 150.00 LF $ 125.00 S 18,750.00 TOTAL ALTERNATE BID PRICE S 18,750.00 TOTAL BASE&ALTERNATE BID PRICE $ 508,609.00 Y.Ko.Construction Co. #3 BASE BID PRICE ITEM DESCRIPTION QTY UNIT UNIT PRO;. TOTAL 1 CLEARING AND GRUBBING. 1.00 LS $ 9,000.00 $ 9,000.00 2 DISPOSAL OF WASTE MATERIALS. 1.00 LS S 10,000.00 S 10,000.00 CONSTRUCT ROSEMEAD SKATE PARK PER PLANS AND 3 SPECIFICATIONS COMPLETE. 1.00 LS S 479,000.00 S 479,000.00 TOTAL BASE BID PRICE $ 498,000.00 ALTERNATE BID ITEM No.1 4 INSTALL GUARD RAIL AS INDICATED ON THE PLANS 150.00 LF S 93.34 $ 14,001.00 TOTAL ALTERNATE BID PRICE $ 14,001.00 TOTAL BASE&ALTERNATE BID PRICE $ 612,001.00 Monet Construction,Inc. #4 BASE BID PRICE ITEM DESCRIPTION TY UNIT UNIT.IE. 1 CLEARING AND GRUBBING. 1.00 LS S 4,200.00 S 4,200.00 2 DISPOSAL OF WASTE MATERIALS. 1.00 LS $ 10,0.00.00 $ 10,000.00 CONSTRUCT ROSEMEAD SKATE PARK PER PLANS AND — Ir 3 SPECIFICATIONS COMPLETE. 1.00 LS ' $ 483,242.00 • $ 483,242.00 TOTAL BASE BID PRICE $ 497,442.00 ALTERNATE BID ITEM No.1 ITEM ;DESCRIPTION _4 INSTALL GUARD RAIL AS INDICATED ON THE PLANS 150.00 LF $ 110 00 $ 16.500 00 TOTAL ALTERNATE BID PRICE $ 16.500.00 TOTAL BASE&ALTERNATE BID PRICE $ 513,942.00 PUBLIC WORKS SERVICE DEPARTMENT/ENGINEERING DIVISION ' Minako America Corp DBA Minco Corportation #6 BASE BID PRICE QTY UNIT UNIT PRICE 1 CLEARING AND GRUBBING. 1.00 LS $ 7.000.00 $ 7,000.00 ' 2 DISPOSAL OF WASTE MATERIALS. 1.00 LS $ 3,000.00 5 3,000.00 CONSTRUCT ROSEMEAD SKATE PARK PER PLANS AND ' 3 SPECIFICATIONS COMPLETE. 1.00 LS $ 527,700.00 $ 527,700.00 ' TOTAL BASE BID PRICE $ 537,700.00 ALTERNATE BID ITEM No.1 ITEM - — QTY UNIT UNIT PRICE TOTAL 4 INSTALL GUARD RAIL AS INDICATED ON THE PLANS 150.00 LF S 130 00 S 19,500 00 TOTAL ALTERNATE BID PRICE $ 19,500.00 TOTAL BASE&ALTERNATE BID PRICE $ 557,200.00 EC Construction #6 BASE BID PRICE RII��E r _ 4F UNIT UNIT PRICE TOTAL 1 CLEARINGANDGRUBBING. 1.00 LS S 13,600.00 S 13.600.00 2 DISPOSAL OF WASTE MATERIALS. 1.00 , LS $ 10,355.00 $ 10.355.00 CONSTRUCT ROSEMEAD SKATE PARK PER PLANS AND 3 SPECIFICATIONS COMPLETE. 1.00 LS $ 568,420.00, $ 568.420.00 TOTAL BASE BID PRICE $ 592,375.00 ALTERNATE BID ITEM No.1 ITEM .DESCRIPTION lEEMOIy _ OT ;. 4 INSTALL GUARD RAIL AS INDICATED ON THE PLANS 150.00 LF $ 94.70 $ 14.205 00 TOTAL ALTERNATE BID PRICE I $ 14.205.00 TOTAL BASE&ALTERNATE BID PRICE S 606.580.00 PAGE 2