OB - Item 3C - Zapopan Park Improvement ProjectROSEMEAD OVERSIGHT BOARD STAFF REPORT TO: THE HONORABLE CHAIR AND BOARD MEMBERS FROM: CURTIS CANNON, SPECIAL PROJECTS MANAGER DATE: APRIL 18, 2016. SUBJECT: ZAPOPAN PARK IMPROVEMENTS PROJECT— PROJECT No. 41008 SUMMARY Included in the July 2010 bond issuance by the former Redevelopment Agency (RDA) was a project to complete a number of improvements and upgrades to facilities at Zapopan Park, including basketball courts, turf and landscape, and restrooms. The action recommended for this agenda item will construct Zapopan Park Improvements Project. On April 12, 2016, the City Council awarded the construction contract to Green Giant Landscape, Inc. for the Zapopan Park Improvements Project for $1,230,000, plus 14% contingencies of $170,000, for a total of $1,400,000. Staff Recommendation It is recommended that the Oversight Board: Approve Resolution 2016 -003 confirming the contracts and expenditures related to the Zapopan Park Improvements Project — Project No. 41008. DISCUSSION Zapopan Park is approximately 7 acres of open park space located below an existing Southern California Edison (SCE) transmission corridor adjacent to Garvey Avenue, between San Gabriel Boulevard and Walnut Grove Avenue. Project No. 41008 ( Zapopan Park Improvement) includes the following: a new 1/3 -mile rubberized surface pedestrian trail, security lighting, landscaping, irrigation, new restroom facilities, parking lot renovation and expansion, repainting existing picnic shelters and furnishings, renovation of existing basketball court and the northerly playground, relocation of existing volleyball court, and Garvey Avenue entryway beautification and access enhancement. On January 6, 2016, the City conducted a community workshop at the Public Safety Center, for which nearby residents were invited to attend and provide input on the Project. On February 9, 2016, after Council directed staff to proceed advertise Project No. 41008 for bids. opened 9 bids, as summarized below. receiving a design and schedule update, the City with finalizing the construction documents and On March 30, 2016, the City publicly received and ITEM NO. IC Oversight Board Meeting April 18, 2016. Peas 2 of 3 RANK CONTRACTOR LOCATION Total Bid 1 CEM Construction Corp. Downey, CA Non-Responsive 2 Green Giant Landscape, Inc. La Habra, CA $1,230,000.00 3 PUB Construction Diamond Bar, CA $1,243,299.00 4 Kasa Construction Chino, CA Non-Responsive 5 California Landscape & Design Inc. Upland, CA $1,378,248.00 6 C.S. Legacy Construction, Inc. Pomona, CA $1,581,628.00 7 Am co Contracting, Inc. Anaheim, CA $1,622,145.30 8 A and Y Construction Glendale, CA Non-Responsive 9 Ian Thomas Group, Inc. Glendale, CA $1,895,245.00 Notes: ( Non - Responsive, proposal read $1,176,555. (2) Corrected bid amount, proposal read $1,243,249. ( Non - Responsive, proposal read $1,249,790. ( Corrected bid amount, proposal read $1,388,348. ( Non - Responsive, proposal read $1,652,477. ( (2) (3) (4) S) Of the 9 bids received, three were non - responsive due to not submitting the required Addendum No. 01. Specifically, Addendum No. 1 states "Failure to acknowledge receipt of addendum will disqualify the Bidder." Of the remaining 6 bids, Green Giant Landscape, Inc. (GGLI) of La Habra, California was the lowest responsive bidder with a bid of $1,230,000. The anticipated construction will commence in May 2016, and be substantially complete by November 2016. CONSTRUCTION MANAGEMENT /INSPECTION /STAFF TIME Construction management and inspection services for this project will be completed utilizing City staff and existing on -call contractors as follows: ITEM ? CONTRACTOR DESCRIPTION AMOUNT (Not to exceed) 1 Spectrum Management Services Special Inspection $25,000 2 SCB Inspection Inspection $25,000 3 CEJ Engineers Construction Support $10,000 4 City Staff /Miscellaneous N/A $10,000 Total $70,000 Oversight Board Meeting April 18, 2016. Page 3 of 3 FINANCIAL REVIEW Funding for the construction of the Zapopan Park Improvements Project is included in the bond proceeds from the former RDA. The total appropriation of bond proceeds necessary to award this project is approximately $1,470,000 as describe below: Green Giant Landscape, Inc. $1,230,000 Contingencies (14 %) $170,000 Special Inspection $25,000 Construction Support $10,000 Inspection $25,000 City Staff /Miscellaneous $10,000 Total $1,470,000 PUBLIC NOTICE PROCESS This item publicly noticed through the regular agenda notification process. Submitted by: Curtis Cannon Special Projects Manager Attachments: (1) Resolution 2016 -003 (2) Bid Analysis RESOLUTION NO. 2016-003 A RESOLUTION OF THE OVERSIGHT BOARD FOR THE SUCCESSOR AGENCY TO THE ROSEMEAD COMMUNITY DEVELOPMENT COMMISSION CONFIRMING THE CONTRACTS AND EXPENDITURES RELATED TO THE ZAPOPAN PARK IMPROVEMENTS PROJECT. WHEREAS, the Rosemead Successor Agency received the Finding of Completion on April 18, 2013 from the Department of Finance; and WHEREAS, the Finding of Completion states that the Rosemead Successor Agency may utilize proceeds derived from bonds issued prior to January 1, 2011 in a manner consistent with the original bond covenants per Health and Safety Code Section 34191.4 (c); and WHEREAS, the Rosemead Successor Agency is holding approximately $7.1 million in bond proceeds derived from bonds issued prior to January 1, 2011 for Capital Improvement Projects identified in the bond covenants; and WHEREAS, the Rosemead Successor Agency will be required to provide oversight of the completion of the Capital Improvement Projects to ensure compliance with the bond covenants; and WHEREAS, the approved Capital Improvement Projects have been included on each Recognized Obligation Payment Schedule filed by the Rosemead Successor Agency; NOW, THEREFORE, THE OVERSIGHT BOARD FOR THE SUCCESSOR AGENCY TO THE ROSEMEAD COMMUNITY DEVELOPMENT COMMISSION HEREBY RESOLVES: SECTION 1 . The Rosemead Successor Agency Oversight Board confirms that the vendors and professional firms listed below are qualified and capable to provide materials and construction services necessary to complete the Zapopan Parks Improvements Project. SECTION 2. That the contract with the following firms shall not exceed the amounts listed in the table below. If any contract amendments are required, all such changes shall be brought back to the Oversight Board for review and approval. TRADE FIRM TOTAL BUDGET Construction Green Giant Landscape, Inc. $1,400,000 Special Inspection Spectrum Management Services $ 25,000 Construction Support CEJ Engineers, Inc. $10,000 Project Inspection SCB Inspection $ 25,000 Project Administration /Staff Time N/A $10,000 TOTAL COST: $1,470,000 SECTION 3. Successor Agency staff is directed to submit documents to the Department of Finance as necessary, including an amended Recognized Obligation Payment Schedule. SECTION 4. Successor Agency staff is directed to provide copy of this Resolution to the County Auditor Controller, the State Controller's Office and the State Department of Finance. PASSED, APPROVED AND ADOPTED THIS DAY OF ' 2016 ATTEST: Pat Wallach Chair Carol Cowley City Clerk APPROVE AS TO FORM: Rachel H. Richman City Attorney � S '388 a m'8 «�tl 8$-$$$$8888$m ess�og a$p 8� ° � &C�4gg aS GG p� =�s as ° $ssk ° o Y m FO 3 Oz °m 442 "= 4mm �CQ .. _d� - �� m .3 z �.� P C �d 3' �.$ �3`SWA %4h ➢ � S t ' -- « w s N i s s a s $$ s $ 8 k$ $ 8 0 8 S $ 8 8: 8$ 8 8 8 $ S 8$ 8 8 8 8 u F s3 a d w $ w $ S 9 8 8 a$ e B $ s k$ s 8 k k$$ 5 k 8 8 k $$$ k s m a v y s 88 a o s$ S w tt o o $ k $ $ 8 $ $ $ $ $ $ $ s k s a S s s a a a a s B a s sse ak s 8 s a s ss �� ° o Y m FO 3 Oz °m