CC - Item 4O - Approval of Proposal to Provide Engineering Services for Concrete Repairs E M F
// R
\ *rots / Staf
report
TO: HONORABLE MAYOR
AND MEMBERS
ROSEMEAD CITY COUNCIL
FROM: FRANK G. TRIPEPI, CITY MANAGER
DATE: JANUARY 20, 1999
RE: APPROVAL OF PROPOSAL TO PROVIDE ENGINEERING SERVICES
FOR CONCRETE REPAIRS AT VARIOUS LOCATIONS (FY 1998-99)
Attached for your consideration is an engineering proposal from Willdan Associates for
preliminary and final engineering design, design and construction survey, monument
restoration, utility coordination, contract administration, and construction observation for
the annual concrete repairs at various locations throughout the Rosemead Redevelopment
Agency and the City of Rosemead.
The concrete repairs project includes removal and reconstruction of existing damaged and
uplifted curb, gutter, sidewalk, and driveways as well as replacement of parkway trees with
root control barriers, if it is determined that uplifting is a result of the tree.
The list of locations for concrete repairs will be prepared as part of the engineer's design
effort. The project will also include citizen requests received during the past year that have
been verified as needing concrete repairs as well as the Los Angeles County's
maintenance list.
The total construction cost for the 1998-99 concrete repairs project is estimated to be
$89,000. The City's share is estimated at$31,000 and the Agency's estimated at$58,000.
The proposed project is currently programmed in FY 1998-99 City and Redevelopment
Agency budgets. The City budget utilizes SB 821 Sidewalk Grant funds.
I COUNCIL AGENDk1
JAN 2 61999
ITEM No. I ✓ . �� )
January 20, 1999
Page 2
The proposed fees are as follows:
• Preliminary and Final Design (Fixed Fee) $ 4,250
• Utility Coordination (Fixed Fee) $ 1,750
• Design Survey (Fixed Fee) $ 1,750
• Monument Restoration $ 8,250
• Construction Survey (Fixed Fee) $ 500
• Construction Observation (Fixed Fee) $ 7,500
• Contract Administration (Fixed Fee) $ 2.000
Total Proposed Fee $26,000
The total fee, excluding utility coordination and monument restoration, is in conformance
with that portion of the City's agreement with Willdan Associates which pertains to design
engineering services.
RECOMMENDATION
It is recommended that the City Council:
1. Approve the attached engineering proposal.
2. Direct staff to begin the preparation of the necessary plans and specifications.
Attachment
C:\1999RSMD\STAFFRPTCITY\Concrete Repairs FY9899.wpd
Ty WILLDAN ASSOCIATES ❑ ENGINEERS & PANNERS
Professional Consulting Services Since 7964
January 18, 1999
Mr. Frank G. Tripepi
City Manager
City of Rosemead
8838 E. Valley Boulevard
Rosemead, CA 91770
Subject: Proposal for Professional Engineering Design, Design and
Construction Surveying, Monument Restoration, Construction
Observation, Utility Coordination, and Contract Administration
for Concrete Repairs at Various Locations for FY 1998-99
Dear Mr. Tripepi:
As requested,we are pleased to be given the opportunity to submit this proposal for
the above-referenced services.
The locations for concrete repairs will be selected based on highest priority within
streets that are not identified for near-future street pavement upgrading. The
concrete repairs include curb, gutter, sidewalk, and drive approaches, as well as
parkway trees, if needed.
We propose to provide the following basic services for the project:
Design Survey
1. Provide locations of repairs by address.
2. Provide existing topographic features at locations of concrete repairs.
3. Provide length of curb and gutter to be removed and replaced.
4. Provide area of sidewalk and drive approach to be removed and replaced.
5. Provide area of street pavement to be removed and replaced along curb,
gutter, and drive approach.
6. Provide locations of parkway trees, if needed, to be removed and replaced.
Preliminary Design
1. Confer with City staff to review, in full detail, the requirements for the project.
Review available information and data assembled by City staff.
2. Review compiled data.
Donn^onccont'<cn-Qv“.,IAVcnI ITH . c,IT_oro• 9M1-`-I ICTPV CA! IgWni.o 017nR ry400•( 'n o1R-Frn• PAY ISF91CAR?17n
January 18, 1999
Page 2
3. Prepare a schedule of concrete repair locations.
4. Determine drainage correction requirements.
5. Review concrete repair locations for possible tree removal.
6. Develop preliminary cost estimates for construction.
7. Submit preliminary concrete repairs schedule to all affected agencies and
utility companies for review.
Final Design Phase
1. Prepare detailed final schedule, and attend coordination meetings, as
necessary, with City personnel at various times during the design phase to
obtain additional input and review work.
2. Prepare specifications and contract documents to conform to applicable
requirements of the City of Rosemead.
3. Prepare final project cost estimates.
Utility Coordination
1. Submit copies of final concrete repairs schedule to all affected utilities and
agencies.
2. Send notification to affected utility companies, other agencies, contractor, and
City staff, and attend and coordinate the preconstruction conference.
Monument Restoration
1. Tie out any monuments(public or private)to be destroyed by construction and
file corner record with County.
2. Reset destroyed monuments and file corner record with County.
Construction Survey
1. Mark the areas of various types of concrete repairs with paint.
2. Mark with paint the trees to be removed.
Contract Administration
1. Provide the City with 30 sets of final plans and specifications for bidding.
2. Assist the City in securing bids and awarding project.
January 18, 1999
Page 3
3. Attend preconstruction conference and prepare minutes.
4. Provide contract administration for proper enforcement of the contract plans
and specifications.
5. Provide engineering support, as needed, to make as-built revisions to the
original concrete repairs schedule.
6. Provide the necessary consulting services required to coordinate the efforts
between the City and contractor.
7. Review and approve progress payment requests.
8. Answer inquiries and complaints for the City relating to the project.
Construction Observation
1. Provide daily construction observation during the construction period.
2. Provide the necessary weekly, monthly, and final reports as needed.
3. Provide copies of daily construction observation reports on a weekly basis, if
requested.
4. Provide necessary coordination with other agencies to provide final inspection
of the project.
5. Perform as-built corrections on original concrete repairs schedule.
6. Provide report to City following final inspection stating that the project has
been completed, and provide necessary data for Agency acceptance of the
project.
Our proposed fees are as follows:
• Preliminary and Final Design (Fixed Fee) $ 4,250
• Utility Coordination (Fixed Fee) 1,750
• Design Survey (Fixed Fee) 1,750
• Monument Restoration (Fixed Fee) 8,250
• Construction Survey (Fixed Fee) 500
• Construction Observation (Fixed Fee) 7,500
• Contract Administration (Fixed Fee) 2 000
Total Proposed Fee $26,000
January 18, 1999
Page 4
The total estimated construction cost for the project is $89,000. The construction
contract period is estimated to be 20-working days. The design fee is based on the
fee curve schedule from the American Society of Civil Engineers. The total fee,
excluding utility coordination and monument restoration, is in conformance with that
portion of the City's agreement with Wilidan Associates which pertains to design
engineering services. Compensationforweekend inspection and inspection beyond
the allocated working days of the construction contractwill be on time-and-materials
basis.
If you have any questions regarding this proposal, please contact me at(562) 908-
6200.
Respectfully submitted,
WILLDAN ASSOCIATES
Richard L. Kopecky, P.E.
Senior Vice President