RRA – Item 4 – Authorization to File Notice of Completion and Accept Garvey Park Pool Re-Piping Project ROSEMEAD REDEVELOPMENT AGENCY
R Ai
B83B VALLEY BLVD..ROSEMEAD.GA 91770•(818)288-6671•Telecopier 8183(879218
TO: FRANK G. TRIPEPI, EXECUTIVE DIRECTOR
FROM: MICHAEL D.BURBANK, DIRECTOR OF PARKS AND RECREATI.)
DATE: AUGUST 11, 1999
RE: AUTHORIZATION TO FILE THE NOTICE OF COMPLETION AND ACCEPT
THE GARVEY PARK POOL RE-PIPING PROJECT
The Contractor has completed the project for a total cost of$ 248,657.00 (see Exhibit"A").
RECOMMENDATION:
It is recommended that the Rosemead Redevelopment Agency accept the project and authorize
staff to file the Notice of Completion.
AGENCY AGENDA
AUG 2 4 1999
ITEM No.
•
•
07-n-b7s.docisb
EXHIBIT "A"
Project Budget and Cost
PROJECT BUDGET $ 250,000.00
PROJECT COST <$ 248,657.00>
Engineering $ 22,500.00
Construction $ 204,153.00
Change Order No. 1 $ 22.004.00 (1)
<$ 248,657.00>
TOTAL $ 1343.00
(1) Contractor lowered his charge on item#7, Slurry under deck, because
less materials were used. Change Order No. 1 was approved June 8, 1999,
in the amount of$ 23,130.00_
Note: Nadar Inc., was the next low bid at $ 212,400.00