RRA - Item 3 – Award of Contract to Honeywell Inc. for City Hall Energy Retrofit Project 1
R R A ROSEMEAD REDEVELOPMENT AGENCY
8838 VALLEY BLVD.ROSEMEAD.CA 91770•(8'18)288-6671 •Telecoprer 8183079218
TO: HONORABLE CHAIRMAN
AND MEMBERS
ROSEMEAD REDEVELOPMENT AGENCY
FROM: FRANK G. TRIPEPI, EXECUTIVE DIRECTOR
DATE: JULY 23, 1998
RE: AWARD OF CONTRACT TO HONEYWELL INC. FOR CITY HALL
ENERGY RETROFIT PROJECT
This item has been before the Agency on two other occasions. At the Meeting of December 9,
1997, the Agency approved a Request for Qualifications for Energy Retrofit and Specifications
and Notice Inviting Bids for Ceiling Tile Replacement. The Agency received two proposals, one
from Honeywell, Inc. and one from Energy Pacific. At the April 14, 1998 Meeting, the Agency
approved staffs recommendation to award the bid to Honeywell, Inc.
Attached for your approval is the final contract in the amount of$555,000. Honeywell's initial
proposal was for $559,800. Staff hired a consultant to review the contract amount. After
reviewing Honeywell's contract he estimated the cost at $524,426 which is a difference of 6% or
$35,374.
Staff met with Honeywell and discussed the differences. They agreed to subtract $4,800 from the
original amount. Attached is a memorandum from the Deputy Building Official recommending
that the Agency accept the contract in the amount of$555,000. Also attached is the contract and
the consultant's estimate.
RECOMMENDATION
It is recommended that the Rosemead Redevelopment Agency approve the contract with
Honeywell, Inc. in the amount of$555,000.
AGENCY AGENDA
•
JUL 28 -mg
ITEM No. 3 1
MEMORANDUM
TO: FRANK G. TRIPEPI, EXECUTIVE DIRECTOR
FROM: STEVEN C. BAILEY, DEPUTY BUILDING OFFICI• /`
SUBJECT: ENERGY RETRO-FIT AND CEILING TILE REPLACEMENT
FOR THE CITY HALL BUILDING
DATE: JULY 23, 1998
After an extensive Request for Qualification (RFQ) process, Honeywell, Inc., was selected
in early April to develop a design/build retrofit program for our City Hall. After a two-month
development phase involving our staff, Honeywell delivered a proposal/contract in June. To
ensure competitive pricing we solicited an outside consultant to review Honeywell's scope
and price. The consultant estimated a total of$524,426, whereas Honeywell's design/build
price was $559,800. In comparing the proposal and estimate, we found that some of the
proposal items were high and some were low, however the net difference was 6%, or
$35,374. After direct negotiations, Honeywell has offered to subtract $4,800 from the
original price as good faith offering. Their new price would be $555,000.
In my experience, a difference of less than 10% between a preliminary estimate and a final
design is competitive. In addition, there is some concern that any further reduction in price
would jeopardize the quality of the project that has been designed for the City Hall. Whereas
a bid/specification contract would involve design cost and change-order costs, Honeywell's
proposal is a design/build performance contract, which has enabled us to avoid a design costs
up to this point. They have also arranged the installation so that the staff and citizens of
Rosemead will be minimally disrupted. Honeywell will perform a majority of the retrofits
especially the interior work, such as the lighting retrofits, ceiling tile replacement, duct
cleaning, and air-balancing, after hours or on weekends. Honeywell is a multi-national
Fortune 500:company with sales exceeding 8 billion annually. They have also successfully
implemented over forty (40) municipal design/build projects in California over the last five
years. Therefore, I am confident that Honeywell has the expertise, design, and competitive
price to perform the desired results for our City Hall. The City Attorney has reviewed the
contract and his recommendations have been included.
tQ
e
TREAD L"CILY Li'CTI Cil 0L-,[D
'----- - ,FN;=iNEE^FING DESIGN CONS, Rl C-iON
07/18/98
Client: CITY OF ROSEMEAD Res. Ph: (626)288-6671
Address: 8838 E.VALLEY BLVD
ROSEMEAD, CA 91770 Fax: (626)307-9218
Contact: STEVE BAILEY Res. Ph: (626)288-6671
Estimator: EUGENE THATCHER Bus. Ph: (818)780-6208
Fax: (818)780-6208
Estimate: ROSEMEAD
File Number: ROSE
estimates and Thspectio^S
6920 Sepulveda Blvd., Suite TO • Van Nuys. California 91405
(818) 780-6208 • Fax (818r780-6208 • Pacer (818) 387-0585
CITY OF ROSEMEAD 07/18/98 Page:2
LIGHTING SYSTEMS
DESCRIPTION UNIT UNIT COST TOTAL
Purchase and Install 75 watt 19 EA 33.00 627.00
recessed can light R-30
complete; retrofit item
Remove and dispose of existing 19 EA 12.00 228.00
R-30 units; a compliance item
Purchase and Install 55 watt 41 EA 47.00 1,927.00
F32-T8 1x4 flour with
electronic ballast complete
Remove and dispose of existing 19 EA 16.00 304.00
F32-T8 units, a compliance item
Purchase and Install 92 watt 17 EA 86.00 1,462.00
FB31-T8 2x2 flour with
electronic ballast complete
Remove and dispose of existing 17 EA 16.00 272.00
FB31-T8 units, a compliance
item
Purchase and Install 26 watt 5 EA 39.00 195.00
recessed can light R-40
complete; new item
Remove and dispose of existing 5 EA 12.00 60.00
R-40 units; a compliance item
Purchase and Install 352 watt 12 EA 136.00 1,632.00
F32-T8 4x6 flour with
electronic ballast complete, a
retrofit item
Remove and dispose of existing 12 EA 16.00 192.00
FB31-T8 units, a compliance
item
CITY OF ROSEMEAD 07/18/98 Page:3
Continued - LIGHTING SYSTEMS
DESCRIPTION UNIT UNIT COST TOTAL
Purchase and Install 88 watt 5 EA 96.00 480.00
FB31-T8 4x2 flour with
electronic ballast complete, a
new item
Remove and dispose of existing 5 EA 16.00 80.00
FB31-T8 units, a compliance
item
Purchase and Install 150 watt 21 EA 62.00 1,302.00
recessed can light R-40
complete; new item
Remove and dispose of existing 21 EA 16.00 336.00
R-40 units, a compliance item
Purchase and Install 176 watt 95 EA 136.00 12,920.00
F32-T8 2x4 flour with
electronic ballast complete, a
retrofit item
Remove and dispose of existing 95 EA 16.00 1,520.00
F32-T8 units, a compliance item
Purchase and Install 100 2x4 19 EA 39.00 741.00
flour F17-T8 complete a
retrofit item
Remove and dispose of existing 19 EA 16.00 304.00
F17-T8 units, a compliance
Purchase and Install 52 watt 46 EA 29.00 1,334.00
recessed can light, hot wired
26W a retrofit item
Remove and dispose of existing 46 EA 12.00 552.00
R-30 units; a compliance item
CITY OF ROSEMEAD 07/18/98 Page:4
Continued - LIGHTING SYSTEMS
DESCRIPTION UNIT UNIT COST TOTAL
Purchase and Install 50 watt 8 EA 46.00 368.00
keyless CF BTX 20 complete
Remove and dispose of existing 8 EA 12.00 96.00
R-30 units; a compliance it
Purchase and Install 32 watt 1 EA 31.00 31.00
1x2 flour F 1728 retrofit item
Remove and dispose of existing 1 EA 16.00 16.00
R-40 units, a compliance item
Replace switch and wiring as 1 LS 5000.00 5,000.00
needed minimum charge; design
and build
LABOR TO INSTALL NEW AND 840 HR 39.00 32,760.00
RETROFIT FIXTURES INCLUDING
2ND SHIFT, SATURDAY AND SUNDAY
21 DAYS X 5 MEN=840 HOURS
NOTE; The above prices reflect state sales tax at .0825 to the dollar
NOTE; The wharehousing of replacement parts on your site as part of the warranty scheme,
the following;
Purchase and store F032 T-8 12 EA 19.60 235.20
lamps
Purchase and store F032 T-8 1 EA 19.60 19.60
lamps
Purchase and store F032 10 EA 12.40 124.00
electronic ballasts
Purchase and store Flourescent 10 EA 2.67 26.70
Tubes
CITY OF ROSEMEAD 07/18/98 Page:5
Continued - LIGHTING SYSTEMS
DESCRIPTION UNIT UNIT COST TOTAL
The rental of two manlift 42 DA 68.00 2,856.00
vechicles for 21 days
2x21=42days
Install 5/8 drywall on ceiling 1 LS 1500.00 1,500.00
as needed minimum charge; for
new and upgraded lights
Seal ceiling with PVA sealer 1 1 LS 0.00
coat as needed
Prep and paint ceiling to match 3,208 SF 1.95 6,255.60
existing
Room Total: LIGHTING SYSTEMS 75,756. 10
LITE SYS OCCUPNCY SE
DESCRIPTION UNIT UNIT COST TOTAL
ELECTRICAL OCCUPANCY SENSOR 24 EA 136.90 3,285.60
LABOR TO INSTALL ROOM OCCUPANCY 72 HR 39.00 2,808.00
SENSORS
Room Total: LITE SYS OCCUPNCY SE 6,093.60
PNU CON SYS ENNC
DESCRIPTION UNIT UNIT COST TOTAL
Replace aircompresor, 4 ton, 1 EA 3876.00 3,876.00
including coil, new filters
and dryer
•
CITY OF ROSEMEAD 07/18/98 Page:6
Continued - PNU CON SYS ENHC
DESCRIPTION UNIT UNIT COST TOTAL
Replace thermostat - standard 10 EA 236.00 2,360.00
into new locations
Replace damper motors to 10 EA 187.00 1,870.00
operate zone dampers
Service clean and repair all 1 LS 600.00 600.00
leaks to existing pneumatic
lines, minimum charge
LABOR TO INSTALL THE ABOVE 72 HR 39.00 2,808.00
ITEMS INTO THE HONEYWELL
SERVICE NET
Room Total: PNU CON SYS ENHC 11,514.00
NERGY MGMT SYS
DESCRIPTION UNIT UNIT COST TOTAL
Purchase and install Excel 100 1 EA 167.00 167.00
controller
Purchase and install submodule 1 EA 322.00 322.00
Purchase and install IDEC relays 14 EA 143.00 2,002.00
Purchase and install duct 3 EA 132.00 396.00
discharge air sensors
Purchase and install high 1 EA 139.00 139.00
temperature sensor
Purchase and install water 3 EA 139.00 417.00
temperature sensors
CITY OF ROSEMEAD 07/18/98 Page:7
Continued - NERGY MGMT SYS
DESCRIPTION UNIT UNIT COST TOTAL
Purchase and install software 1 LS 76000.00 76,000.00
including monitors,
memory,hardrive disk, magnetic
tape, printed material and
other related materials and
will be tied into the
Honeywell Service Net
LABOR TO INSTALL THE ABOVE 64 HR 39.00 2,496.00
ITEMS INTO THE HONEYWELL
SERVICE NET 14 DAYS
Room Total: NERGY MGMT SYS 81,939.00
CENTAL PLNT ENHNCNNT
DESCRIPTION UNIT UNIT COST TOTAL
Purchase and install Carrier 40 1 LS 24200.00 24,200.00
ton chiller
LABOR TO INSTALL A CARRIER 40 1 LS 416.00 416.00
TON CHILLER
Purchase and install fiberglass 1 LS 21700.00 21,700.00
cooling tower 40 ton, with
condenser,pump, and chilled
water pump
LABOR TO INSTALL A COOLING TOWER 1 LS 709.00 709.00
Purchase and install 250 MBH 3 EA 1124.00 3,372.00
duct furnaces
LABOR TO INSTALL 3 DUCT 3 LS 423.00 1,269.00
FURNACES IN THE BASEMENT
CITY OF ROSEMEAD 07/18/98 Page:8
Continued - CENTRL PLNT ENHNCMNT
DESCRIPTION UNIT UNIT COST TOTAL
LABOR TO INSTALL DISCONNECT 1 LS 693.00 693.00
SWITCHES FOR COOLING, AND
HEATING UNITS
CRANE RENTAL TO HOIST COOLING 5 HR 165.00 825.00
UNITS INTO PLACE
Insulate new and existing 1 LS 354.00 354.00
hotwater lines for energy
requirements
Install gas line monitoring and 1 LS 396.00 396.00
exhaust system for chiller and
cooling tower water treatment
Room Total: CENTRL PLNT ENHNCMNT 53,934.00
COMPUTER RN HVC SYS
DESCRIPTION UNIT UNIT COST TOTAL
Purchase and install 1.5 split 1 LS 3265.00 3,265.00
system cooling unit for
computer room
Purchase and install computer 1 LS 1200.00 1,200.00
lines devices hardware and
conduit as needed minimum
charge
Install condensate line into 1 LS 600.00 600.00
nearest coded area, roof
drain, lavatory drain, may
need a visible line through
exterior
Room Total: COMPUTER RM HVC SYS 5,065.00
CITY OF ROSEMEAD 07/18/98 Page:9
CNCL CHMBRS HVAC
DESCRIPTION UNIT UNIT COST TOTAL
Purchase and install 10 ton gas 1 LS 10860.00 10,860.00
fired package unit
LABOR TO INSTALL A CARRIER 10 1 LS 416.00 416.00
TON GAS PACKAGE UNIT
Install roof curb for mounting, 1 LS 486.00 486.00
including isolation sound
absorbers
Install disconnect switch for 1 LS 360.00 360.00
package unit
Provide roof penetration and 1 LS 320.00 320.00
later restoration to match
existing including all
flashings
Purchase and install plenum 1 LS 567.00 567.00
drop from new unit to existing
ductwork
Purchase and install duct caps 1 LS 567.00 567.00
to isolate central air
distribution
Install gas line for new unit 1 LS 250.00 250.00
Install new pvc condensate 1 LS 165.00 165.00
lines to closest gutter
Purchase and install new twist 1 LS 320.00 320.00
type timer for new unit.
CITY OF ROSEMEAD 07/18/98 Page:10
Continued - CNCL CHMBRS HVAC
DESCRIPTION UNIT UNIT COST TOTAL
Provide roof beauty surround 80 SF 36.00 2,880.00
screens
Room Total: CNCL CHMBRS HVAC 17,191.00
AIR DUCT CLN HVC SYS
DESCRIPTION UNIT UNIT COST TOTAL
Provide cleaning, and 720 HR 39.00 28,080.00
sanitizing to all existing
ductwork, all inclusive,
approximately 1800 lineal feet
including certification
The rental of two manlift 42 DA 68.00 2,856.00
vechicles for 21 days
2x21=42 day
Cut and reinstall ductwork for 1 LS 567.00 567.00
the cleaning process
Install new ductwork at the 1 LS 3650.00 3,650.00
Parks and Recreation Rooms as
needed
Room Total: AIR DUCT CLT' HVC SYS 35,153.00
CITY OF ROSEMEAD 07/18/98 Page:ll
CEILING TILE
DESCRIPTION UNIT UNIT COST TOTAL
Purchase and install T bar 11,458 SF 5.20 59,581.60
ceiling seismic wire tie with
Armstrong fissure tile, 2x2
LABOR TO INSTALL T-BAR CEILING 720 EA 39.00 28,080.00
AND PLACE 2X2 TILES
The rental of two manlift 42 DA 68.00 2,856.00
vechicles for 21 days
2x21=42days
Remove and transport to dumpster 11,458 EA 2.36 27,040.88
Room Total: CEILING TILE 117,558.48
SUPERINTENDENT
DESCRIPTION UNIT UNIT COST TOTAL
Superintendent to oversee 12 WK 1560.00 18,720.00
entire project and interface
with the officials of the City
of Rosemead and General
Contractor
Room Total: SUPERINTENDENT 18,720.00
Line Item Subtotal: 422,924.18
•
CITY OF ROSEMEAD 07/18/98 Page:12
Summary
Total Line Items 422,924 .18
Overhead @ 12% x 422,924.18 50,750.90
Profit @ 12% x 422,924.18 50,750.90
Grand Total $524,425.98
1 .j
EUG.rE THA HER 7
Project Manager
CITY OF ROSEMEAD 07/18/98 Page:13
Recap By Room
Room:LIGHTING SYSTEMS 75,756.10 17.91%
Room:LITE SYS OCCUPNCY SE 6,093.60 1.44%
Room:PNU CON SYS ENHC 11,514.00 2.72%
Room:NERGY MGMT SYS 81,939.00 19.37%
Room:CENTRL PLNT ENHNCMNT 53,934.00 12.75%
Room:COMPUTER RM HVC SYS 5,065.00 1.20%
Room:CNCL CHMBRS HVAC 17,191.00 4.06%
Room:AIR DUCT CLN HVC SYS 35,153.00 8.31%
Room:CEILING TILE 117,558.48 27.80%
Room:SUPERINTENDENT 18,720.00 4.44%
Summary
Total Line Items 422,924.18
Overhead 0 12% x 422,924.18 50,750.90
Profit @ 12% x 422,924.18 50,750.90
Grand Total $524,425.98
CITY OF ROSEMEAD 07/18/98 Page:14
Recap By Category
Description: 00 Items Total Dollars %
ACOUSTIC CEILINGS 114,702.48 27.12%
CLEANING 28,080.00 6.64%
CARPENTRY 3,686.00 0.87%
DRYWALL 1,500.00 0.35%
ELECTRICAL 73,811.10 17.45%
EQUIPMENT 9,393.00 2.22%
HEAT, VENT 5 AIR CONDITIONING 163,310.00 38.61%
SUPERINTENDENT 18,720.00 4.43%
PLUMBING 1,765.00 0.42%
PAINTING 6,255.60 1.48%
SHEET METAL 1,701.00 0.41%
0&P Items Subtotal 422,924.18 100.00%
Overhead 12% 50,750.90
Profit 12% 50,750.90
Grand Total $524,425.98
CITY OF ROSEMEAD 07/18/98 Page:I5
GENERAL BUILDING NOTES
1. This estimate does not include any building code improvements or modifications of any
kind unless otherwise noted.
2. This estimate does not include any changes to specifications made by the department of
building and saftey unless otherwise noted.
3. This estimate does not include any changes and/or modifications made by any engineer
unless otherwise noted.
4. This estimate does not include any hidden damages of any kind.
5. This estimate does not include any hazardous material testing or removal unless
otherwise noted.