CC - Item 2A - Public Hearing on Expenditure of Commission Fundsi
ROSEMEAD CITY COUNCIL
STAFF REPORT
TO: THE HONORABLE MAYOR AND CITY COUNCIL
FROM: OLIVER CHI, CITY MANAGER ok~
DATE: AUGUST 26, 2008
SUBJECT: PUBLIC HEARING ON THE EXPENDITURE OF COMMISSION FUNDS
FOR THE FY 2008-09 CAPITAL IMPROVEMENT PLAN PURSUANT TO
HEALTH & SAFETY CODE SECTIONS 33679 AND 33445
SUMMARY
Redevelopment Law (Health and Safety Code Section 33445) requires that, if
redevelopment funds are to be used to pay for improvements which will be publicly
owned, both within and outside of the project area, the City Council and the Community
Development Commission must make three findings: a) that the proposed
improvements are of benefit to the Project Areas or the immediate neighborhood in
which the projects are located; b) that there are no other reasonable means of financing
the proposed projects available to the community; c) that the projects will assist in the
elimination of blighting conditions in the Project Areas and are consistent with the
adopted Implementation Plan.
For the FY2008-09 Capital Improvement Plan, there are two projects that require the
use of Commission funds.
1. The Rosemead Parks Trail Project was considered and approved by the
City Council as a part of the recently adopted budget. The Project will
beautify the park by adding landscaping, adding a new walking/jogging
trail around the park's perimeter, and adding new exercise and fitness
equipment adjacent to the new trail.
2. The Sewer Master Plan Project was also considered and approved by the
City Council as a part of the recently adopted budget. The Project will
conduct an overall analysis and needs assessment of the City's sewer
system infrastructure. The plan will also allow staff to develop needed
capital improvements projects over the next 5 and 10 years.
Construction of the Rosemead Park Trails is expected to occur between September
2008 and November 2008. The Sewer System Master Plan is expected to be
completed by April 2009.
APPROVED FOR CITY COUNCIL AGENDA: 6 ~ A
l ■
City Council Meeting
August 26, 2008
Page 2 of 3
Staff Recommendation
Staff recommends that the City Council adopt Resolution No. 2008-58 making the
appropriate findings under Health and Safety Code Section 33445 and the Council
consent to the proposed Commission expenditures.
ANALYSIS
Health and Safety Code Section 33445 Findings
As stated above, Health and Safety Code Section 33445 requires that the City Council
consent to the Commission expenditures for public improvement projects and that the
Commission and Council find that:
1) The use of Commission funds is of benefit to the project area(s) funding
the improvement.
The Projects are of benefit to the Project Areas as there are inadequate
and deficient public facilities within the Project Area including park facilities
and improvements and the sewer system infrastructure is in need of
improvements which will be identified in the Sewer Master Plan and permit
the City to create a plan for undertaking those improvements. These
projects will provide needed public facilities and improvements and will
therefore benefit the Project Areas. A description of the Projects and the
funding sources are attached to the Resolution proposed with this staff
report as Exhibit A; and
2) There is no other reasonable means of financing the improvements.
At this time, no other reasonable means of financing the Projects are
available from the City as the City is using its funds to undertake other
projects, services and public improvements throughout the City as
reflected in the City's FY 2008-09 Capital Improvement Plan; and
3) Funding the project will assist in the elimination of one or more blighting
conditions inside the project area.
The payment of funds for the Projects will assist in the elimination of
blighting conditions inside the Redevelopment Project Areas by providing
for the identification of needed public sewer system improvements and
additional public park facilities which are currently insufficient and in poor
condition; and
r
City Council Meeting
August 26, 2008
Paae 3 of 3
4) Consistency with 5-Year Plan
The use of Commission funds for these Projects is consistent with the
Commission's 5-year Implementation Plan for 2005-2009.
FISCAL IMPACT
The Community Development Commission approved $125,000 for the Sewer Master
Plan and $295,000 for the Rosemead Park Trails Project in the FY 2008-09 Capital
Improvement Plan budget.
PUBLIC NOTICE PROCESS
This item has been noticed through the regular agenda notification process.
Sub by
Bria eki
Assistant City Manager
Attachment A: City Council Resolution No. 2008-58
0 0
RESOLUTION NO. 2008-58
A RESOLUTION OF THE CITY COUNCIL OF THE
CITY OF ROSEMEAD MAKING THE FINDINGS
REQUIRED BY SECTION 33445 OF CALIFORNIA
REDEVELOPMENT LAW AND DETERMINING
THAT THE PROVISION OF PUBLIC
IMPROVEMENTS FOR THE CREATION OF A
SEWER MASTER PLAN AND CONSTRUCTION OF
PARKS IMPROVEMENTS AT ROSEMEAD PARK IS
OF BENEFIT TO REDEVELOPMENT PROJECT
AREAS NOS. 1 AND 2
WHEREAS, the Rosemead Community Development Commission (the
"Commission") is a public body, corporate and politic, duly established and authorized
to transact business and exercise powers under and pursuant to the provisions of the
Community Redevelopment Law of the State of California, constituting Part 1 of
Division 24 of the Health and Safety Code of the State of California (the "Law"),
including the power to expend funds for public improvements for the benefit of
Redevelopment Project Areas Number 1 and 2 ("Project Areas"); and
WHEREAS, the City of Rosemead ("City") is the legislative body for the
community in which the Project Areas are located and pursuant to Health & Safety
Code section 33445 is required to consent to payments to be made by its
Commission for the provision of public improvements; and
WHEREAS, the provision of these projects are consistent with the
Commission's Five-Year Implementation Plan Goals adopted for 2005-2009; and
WHEREAS, there are appropriate facts supporting the findings required by
Health & Safety Code Section 33445 for the City Council to consent to the
Commission's expenditure of funds for provision of funds for the creation of a sewer
master plan and park related public improvements at Rosemead Park "the Project(s)";
and
WHEREAS, the Resolution is being considered at properly noticed Public
Hearing as required by Health and Safety Code section 33679.
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF
ROSEMEAD CALIFORNIA DOES HEREBY RESOLVE AS FOLLOWS:
SECTION 1. Recitals. The City Council finds and declares that the above
recitals are true and correct and incorporates them herein.
SECTION 2. Findings Required by Health & Safety Code Section 33445. The
City Council hereby determines that:
• •
(i) the Projects are of benefit to the Project Areas as there are
inadequate and deficient public facilities within the Project Areas
including park facilities and improvements and sewer system
infrastructure is in need of improvements which will be identified
in the Sewer Master Plan to permit the City to create a plan for
undertaking sewer system capital improvement. These projects
will provide those needed public facilities and improvements and
will therefore benefit the Project Areas. A description of the
Projects and the funding sources are attached here to as Exhibit
A; and
(ii) no other reasonable means of financing the Projects are
available from the City as the City is using its funds to undertake
other projects, services and public improvements throughout the
City as reflected in the City's Capital Improvement Plan and City
2008-2009 Budget a copy of which is on file with the City Clerk;
and
(iii) that the payment of funds for the Projects will assist in the
elimination of blighting conditions inside the Redevelopment
Project Areas by providing for the identification of needed public
sewer system improvements and additional public park facilities
which are currently insufficient and in poor condition; and
(iv) The use of Commission funds for these Projects is consistent
with the Commission's 5-year Implementation Plan for 2005-
2009.
SECTION 3. City Consent to use of Agency Funds. The City Council
consents to the use of Commission funds to pay $125,000 to fund in part the Sewer
Master Plan and $295,000 to fund in part the Rosemead Park facilities and
improvements for a total of $420,000 to permit the completion of the Projects.
SECTION 4. Effective Date: This Resolution shall take effect from and
after its date of passage; approval and adoption.
SECTION 5. Certification: The City Clerk shall certify to the adoption of
this Resolution.
PASSED, APPROVED AND ADOPTED this 26th day of August, 2008.
John Tran, Mayor
•
APPROVED AS TO FORM
ATTEST:
Joseph M. Montes, Special Counsel
Gloria Molleda, City Clerk
• •
EXHIBIT A
Rosemead Park Trails
The project will help beautify existing park landscaping at the Rosemead park, add a
new walking/jogging trail around the park's perimeter, and add new exercise
equipment adjacent to the new trail. This project was approved by the City Council
and Community Development Commission as part of the FY 2008-09 Capital
Improvement Plan ($295,000 - CDC funds, $155,000 - TDA funds, $50,000 -
sidewalk grant).
Sewer System Master Plan
The sewer system master plan will provide an overall analysis and needs assessment
of the City's sewer system infrastructure. The plan will also allow staff toe develop
needed capital improvements over the next 5 to 10 years ($125,000 - CDC funds,
$50,000 - gas tax fund).