CC - Item 4D - Accept Completed Improvements & File NOC for Catch Basin Upgrade Phase II Project No. 49018ROSEMEAD CITY COUNCIL STAFF REPORT TO: THE HONORABLE MAYOR AND CITY COUNCIL FROM: LILY VALENZUELA, ACTING CITY MANAGER W DATE: JULY 14, 2026 SUBJECT: ACCEPT COMPLETED IMPROVEMENTS AND AUTHORIZE THE FILING OF A NOTICE OF COMPLETION FOR THE CATCH BASIN UPGRADE PHASE II PROJECT NO.49018 On March 12, 2024, the City Council awarded a construction contract to United Stormwater, Inc. for the Storm Water Catch Basin Upgrade Project Phase II. The total approved construction budget, including a 10% contingency, was $207,460.00. All construction improvements have been completed and have been accepted by the City staff. A notice of completion will be filed with the Los Angeles County Recorder's Office upon approval by the City Council. The release of retention funds will take place upon the filing of the notice of completion. DISCUSSION The City is required to comply with the Los Angeles River (LAR) Trash Total Maximum Daily Load (TTMDL), which mandates a 100 percent trash load reduction, or a "zero" trash numeric effluent limitation. To support compliance with these requirements, the Catch Basin Upgrade Phase II Project installed sixty-six (66) Automatic Retracting Screen (ARS) Partial Capture Devices (PCDs). These improvements were implemented to address the requirements of the Municipal Separate Storm Sewer System (MS4) Permit and advance the City's progress toward regulatory compliance. The total construction contract cost was $189,625.00. All construction costs were fully funded through the approved project budget using Safe Clean Water Program funds. STAFF RECOMMENDATION It is recommended that the City Council: 1. Accept the completed improvements for the Catch Basin Upgrade Phase II Project No. 49018 as performed by United Stormwater, Inc. 2. Authorize the recordation of Notice of Completion with the Los Angeles County Recorder's Office and the release of retention funds. AGENDA ITEM 4.1) City Council Meeting July 14, 2026 Page 2 of 2 FISCAL IMPACT The project was included in the Fiscal Year 2023-2024 Capital Improvement Program (CIP) and consisted of an approved budget of $150,000. City Council authorized an additional appropriation of $60,000 in Safe Clean Water Program funds to the project at the time of the construction contract award. Final construction contract expenditures totaled $189,625.00. The following is the breakdown of the construction cost: Construction Budget $207,460.00 Approved Construction Contract $188,600.00 Approved Construction Contingency 10% $18,860.00 Expended Amount $189,625.00 Unexpended Amount $17,835.00 ENVIRONMENTAL REVIEW Section 15301 of the California Environmental Quality Act (CEQA) guidelines exempts projects consisting of the operation, repair, maintenance, permitting, leasing, licensing, or minor alteration of existing public or private structures, facilities, mechanical equipment, or topographical features, involving negligible or no expansion of use beyond that existing at the time of the lead agency's determination. The project is classified as a Class 1 Categorical Exemption, pursuant to Section 15301 of CEQA guidelines. STRATEGIC PLAN IMPACT The project is consistent with the City of Rosemead's Strategic Plan Goal C - Infrastructure and Facilities, which is to enhance streets, sidewalks, and public infrastructure; coordinate with relevant utility agencies regarding safety and enhancements; and modernize facilities by expanding the use of wireless network technology and renewable energy. PUBLIC NOTICE PROCESS This item has been noticed through the regular agenda notification process. Prepared by: --�A Ot" D elle Garcia, Public Works Fiscal and Project Manager Suplriled by: � 2e��� For Siffuel Gutierrez, Director of Public Works Attachment A: Notice of Completion Attachment A Notice of Completion RECORDING REQUESTED BY CITY OF ROSEMEAD AND WHEN RECORDED MAIL TO: Name City of Rosemead Street Address 8838 E. Valley Blvd. City & State Rosemead, CA 91770 ATTN: CITY CLERK SPACE ABOVE THIS LINE FOR RECORDER'S USE Notice of Completion Notice is hereby given that: 1. The undersigned is owner of the interest or estate stated below in the property hereinafter described. 2. The full name of the undersigned is: City of Rosemead 3. The full address of the undersigned is: 8838 E. Valley Blvd., Rosemead, CA 91770 4. The nature of the title of the undersigned is: In fee (If other than fee, strike "In fee" and insert, for example, "purchaser under contract of purchase", or "lessee") 5. The full names and full addresses of all persons, if any, who hold title with the undersigned are: Names Addresses N/A N/A 6. The names of the predecessors in interest of the undersigned, if the property was transferred subsequent to the commencement of the work of improvement herein referred to: Names Addresses N/A N/A no transfer made, insert, "none". 7. A work of improvement on the property hereinafter described was completed on: July 17, 2025 8. The name of the contractor, if any for such work of improvement was: United Stormwater, Inc. 9. The property on which said work of improvement was completed is in the City of Rosemead County of Los Angeles State of California, and is described as follows: Catch Basin Upgrade Phase II, Project No. 49018 10. The street address of said property is: 8838 E. Valley Blvd., Rosemead, CA 91770 no street address has been officially assigned, insert "none" Signature of owner named Dated: in paragraph 2: Samuel Gutierrez Director of Public Works By: City of Rosemead I certify (or declare) under penalty of perjury that the foregoing is true and correct. Date Samuel Gutierrez Director of Public Works City of Rosemead, California Rosemead, CA Place of Execution